# Landmark entrances: reconcile the accessible route with the approved historic detail

A landmark entrance estimate needs a coordinated accessibility solution and an LPC-reviewed historic detail. Neither preservation approval nor a proposed ramp alone establishes the complete applicable code solution.

## Compare feasible routes and preserved fabric

[LPC's barrier-free access guide](https://www.nyc.gov/assets/lpc/downloads/pdf/LPCPermitGuidebook_Chapter9_BarrierFree.pdf) addresses entrances, ramps, lifts and grade changes alongside accessibility requirements. Depending on the proposal, application materials can include why an alteration to a historic entrance is necessary and why less-invasive alternatives are infeasible. The responsible design professional must establish the applicable code and the project's actual options.

| Option component | Evidence needed | Scope interface |
| --- | --- | --- |
| Door and threshold | Existing dimensions and reviewed detail | Door hardware, finish and historic fabric |
| Grade and route | Survey and coordinated route | Civil work, drainage and adjoining finishes |
| Ramp | Design, landing and railing details | Structure, paving and attachment |
| Lift | Location, support and access | Power, enclosure and maintenance access |
| Alternative | Explanation of feasibility and historic impact | Design and approval effort |

## Illustrative entrance comparison

At a hypothetical Manhattan landmark, one proposal changes a historic threshold; another introduces a lift at a different location. Request drawings of the entire route, affected fabric, structural attachments and finishes for both. The designer evaluates accessibility and preservation feasibility; the estimator identifies the scope and cost differences. Do not describe either option as compliant or approved without the applicable review.

Carry surveys, temporary access during construction, reinstatement and the responsible applicant. If the selected solution is unresolved at bid, state which option is in the base and price any defined alternate on the same access assumptions. See [NYC building code preconstruction review](https://piper-ai.com/resources/nyc-building-code-preconstruction-review) and the [tenant improvement scope review](https://piper-ai.com/resources/tenant-improvement-preconstruction-scope-review).