# Landmark HVAC openings: confirm the approved location before buying the equipment

For a landmark HVAC bid, establish the reviewed facade opening and its interfaces before buying equipment. A unit that fits mechanically does not establish that the sleeve, louver or infill is acceptable to LPC.

## Locate the proposed opening

[LPC's HVAC guide](https://www.nyc.gov/assets/lpc/downloads/pdf/LPCPermitGuidebook_Chapter12_HVAC.pdf) distinguishes through-window and through-wall installations and explains that building and facade characteristics affect review. Give the designer the actual facade location, equipment dimensions, visible finish and proposed opening. Confirm the applicable approval and approved drawing revision rather than assuming a standard detail applies everywhere.

| Interface | Scope to compare | Decision owner |
| --- | --- | --- |
| Sleeve and louver | Opening dimensions, material and finish | Mechanical trade and designer |
| Window or storefront infill | Framing, glazing and appearance | Glazing trade and preservation designer |
| Support | Anchors and load path | Structural designer and installing trade |
| Weather seal | Flashing, sealant and transitions | Envelope trade and mechanical trade |
| Restoration | Cut edges and historic material repair | Restoration trade and designer |
| Approval | Submitted and approved opening detail | Applicant and owner |

## Illustrative bid-leveling check

One vendor quotes the unit and sleeve, while another includes a louver but excludes cutting and making good. Compare both to a single approved section through the opening. Identify the party furnishing each part, the actual finish and the responsibility for water-tight transitions. If the opening remains under review, show a provisional detail and hold the fabrication-dependent purchase until the design team releases the approved revision.

Use [HVAC scope gaps and double-ups](https://piper-ai.com/resources/hvac-scope-gaps-and-double-ups-bid-leveling) to level the mechanical bids and [scope generation](https://piper-ai.com/resources/construction-scope-generation-guide) to assign the envelope interface.