# Landmark facade restoration: carry the approved repair method into the trade scope

An inspection finding can define a condition needing attention without establishing the preservation repair method. For a Manhattan landmark facade bid, carry substrate, extent, method, testing and approval together rather than pricing an unexplained repair quantity.

## Match the method to the fabric

[LPC's restoration guide](https://www.nyc.gov/assets/lpc/downloads/pdf/LPCPermitGuidebook_Chapter1_Restoration.pdf) distinguishes repair from replacement and addresses material-specific conditions. Its mortar guidance considers compatibility, joint removal, tooling and color; it also discusses conditions assessments, probes and mortar analysis. The appropriate method is project-specific, not a universal mortar recipe.

| Location and substrate | Basis to obtain | Work and uncertainty to carry |
| --- | --- | --- |
| Masonry joints | Condition survey and proposed mortar characteristics | Joint preparation, sample and tooling approval if required |
| Stone element | Extent and repair versus replacement detail | Access, protection and measured repair limits |
| Architectural metal | Existing condition and specified treatment | Preparation, finish and protection of adjoining work |
| Concealed interface | Defined probe and structural review | Temporary closure and unresolved quantity |

The designer should identify what evidence and samples are needed for the actual application. Give the restoration trade the same approved revision and distinguish field survey quantities from an allowance. Record who owns protection, sample panels, access, testing and disposal, and how a discovered condition reaches the designer.

## Illustrative bid adjustment

Suppose the facade survey identifies deteriorated joints but does not define their depth or approved mortar. Obtain a bounded quantity and a stated preparation and sample assumption for the base bid. Carry additional hidden deterioration under an explicit allowance or change mechanism consistent with the contract. Do not treat that allowance as an approved repair method.

Coordinate the inspection and access scope with [Local Law 11 facade construction](https://piper-ai.com/resources/nyc-local-law-11-facade-construction-scope) and keep uncertainty visible in the [contingency and allowance review](https://piper-ai.com/resources/construction-contingency-allowances-estimate-review).