# Landmark window bids: compare the approved opening and profile, not just the unit count

For a designated Manhattan building, a unit count alone does not establish a comparable window bid. Classify the facade, identify the historic and existing window, and match each proposed repair or replacement to the reviewed detail.

## Build the window-type register

[LPC's windows and doors guide](https://www.nyc.gov/assets/lpc/downloads/pdf/LPCPermitGuidebook_Chapter2_Windows.pdf) distinguishes primary, visible secondary and non-visible secondary facades. Dimensions, operation, material, finish and documented exceptions affect the review. The applicable criteria and approved drawings must be checked for each project; visibility alone does not authorize a particular replacement.

| Register field | Evidence to request | Bid-leveling consequence |
| --- | --- | --- |
| Location and facade | Elevation, opening identifier and visibility | Separate different review conditions |
| Existing condition | Survey and photos, with repair assessment | State repair or replacement assumption |
| Configuration | Operation, glazing proportions and dimensions | Compare like window types |
| Detail and finish | Comparative sections, material and color | Expose profile or finish exclusions |
| Release | Approved type and applicable variation | Hold fabrication of unresolved types |

A conditions assessment and comparative details can support certain replacement applications. Repair or retrofit may be an alternative, and an approved master plan may define repeated work. Obtain the actual documents before describing either as the project's decision.

## Example: two quotes, one window schedule

An illustrative bid has one quote for all openings and another separating a street-facing type from a rear type. Ask both vendors to identify opening IDs, operation, sections, finish, perimeter treatment and access. Carry surveys and any unapproved exceptions separately. The lower total is not comparable if it omits historic profile matching or assumes replacement where the issued scope calls for repair.

Tie access and facade work to [Local Law 11 facade scope](https://piper-ai.com/resources/nyc-local-law-11-facade-construction-scope), and normalize [subcontractor exclusions](https://piper-ai.com/resources/review-subcontractor-exclusions-and-qualifications) before buyout.