# NYC Local Law 97 retrofit bids: price the selected work, not a compliance promise

NYC Local Law 97 establishes building greenhouse-gas requirements for covered properties. A compliance analysis can lead to a construction project, but it is not itself a complete retrofit scope. A GC preparing a commercial retrofit bid needs the selected measures, issued design requirements and operating constraints translated into packages the trades can actually price.

[DOB's current LL97 guidance](https://www.nyc.gov/site/buildings/codes/ll97-greenhouse-gas-emissions-reductions.page) is the starting point for the owner and responsible advisers to confirm the applicable requirements and available pathways. The contractor's estimate should identify the work it is pricing rather than imply that buying a piece of equipment guarantees a compliance outcome.

## Identify the selected project basis

Obtain the owner-approved measures and issued technical documents. Distinguish a concept, an energy study, a design package and an accepted construction scope. Record the performance and reporting responsibilities the contract assigns to each party.

Ask who confirms the emissions analysis and compliance treatment. A mechanical bidder's equipment selection and a contractor's estimate approval are not substitutes for that determination.

## Review the interfaces around the primary equipment

An illustrative electrification package may affect electrical service, controls, distribution, supports, penetrations, temporary operation and commissioning. The exact work depends on the selected design and existing conditions. Give each interface a responsible package and check it against proposals.

Use the [electrical-exclusion review](https://piper-ai.com/resources/common-electrical-bid-exclusions-gcs-should-review) and [HVAC leveling guide](https://piper-ai.com/resources/hvac-scope-gaps-and-double-ups-bid-leveling) to investigate boundaries. A complete equipment quote can still leave a gap between systems.

## Carry the operating constraints into the price

Review the building's occupied condition, permitted shutdown windows, access and temporary-service requirements. Identify the sequence assumed by the design and the bidders. If existing services must remain available while new work is installed, determine which package carries the temporary arrangement.

A quote based on an unrestricted replacement is not equivalent to one based on staged operation. Preserve the different assumptions before selecting the carry.

## Separate construction completion from verified performance

Record the testing, controls integration, commissioning, training and documentation included in the scope. Identify who verifies performance and who prepares any required compliance submission. The handoff should show which contractor deliverables support those responsibilities.

The [NYC code-review guide](https://piper-ai.com/resources/nyc-building-code-preconstruction-review) covers the related need to confirm the project's governing technical basis. Treat current LL97 rules and the project's actual approvals as sources, not a fixed checklist copied across buildings.

## Give the prebid review a connected requirements file

Piper's [Scope Generation](https://piper-ai.com/use-cases/scope-generation) can help organize the issued retrofit requirements into trade scope, while [Final Bid Review](https://piper-ai.com/use-cases/final-bid-review) compares the estimate with project documents and proposals. Findings remain connected to their sources and the project understanding used earlier in the work.

The owner, advisers and responsible professionals still determine compliance. The GC approves scope coverage, estimate assumptions and the construction commitment it is prepared to make.