# LPC Notice of Compliance: price the evidence needed for closeout

An LPC Notice of Compliance is not required for every permit. Confirm the reason for it on this project, then assign the photographs, deviation record and submission before the scaffold or other access is removed.

## Establish the closeout obligation

[LPC's Notice of Compliance guidance](https://www.nyc.gov/site/lpc/applications/notices-of-compliance.page) says an NOC is required for open violations and permits connected with related Department of City Planning approvals; DOB often requires it for final closeout. Check the actual permit, violation status and DOB filing with the applicant. Do not assume that either agency's closeout automatically completes the other's.

The Portico post-approval request calls for color photographs of all approved exterior work, including work not visible from a public thoroughfare, and a list of as-built differences from the original approval. The responsible designer should compare the final record to approved revisions and resolve deviations with LPC as appropriate. A photograph alone does not approve changed work.

## Completion-evidence handoff

| Evidence | Collection point | Responsible party to name |
| --- | --- | --- |
| Approved scope and revisions | Before work starts | Applicant or design lead |
| Street and concealed-from-street exterior photos | Before access is removed | Field lead and trade |
| As-built differences | As changes occur | Superintendent and designer |
| Review and Portico submission | Before closeout deadline | Authorized applicant |
| DOB closeout handoff | After applicable LPC action | Filing professional |

For an illustrative rear-facade repair, include close photographs of completed work and location views that let the reviewer relate them to the approved drawings. Budget the lift or scaffold time, photo organization and return visit if evidence is missing. If the trade changed a repair detail, flag it before the NOC request rather than treating the final invoice as evidence of approval.

[Turn the closeout requirement into scope](https://piper-ai.com/resources/construction-code-requirements-scope-review) and use a [prebid RFI](https://piper-ai.com/resources/construction-rfi-prebid-scope-review) to name the submitter and acceptance record.