# LPC permit routing: establish the review path before the Manhattan bid schedule

For a Manhattan designated property, carry LPC review and DOB filing as separate schedule gates. Establish the review route from the actual proposal with LPC, then release procurement against the approved documents and any remaining permit conditions.

## Decide the route from the submitted work

[LPC permit types](https://www.nyc.gov/site/lpc/applications/permit-types.page) explain that staff determine the permit type after reviewing the application. Exterior work can need LPC approval even where DOB approval is not required. Staff review and Commission consideration are distinct paths; do not promise either from a trade description alone. Ask the applicant to identify the designation, scope, drawings, visibility and relevant approved history before assigning a bid milestone.

[Portico](https://www.nyc.gov/site/lpc/applications/apply.page) receives applications and supporting documents and returns permits and approved drawings. An incomplete submission is not a reliable start for a processing assumption. Commission approval can still leave final filing drawings to complete. Coordinate the preservation route with the design professional's DOB strategy and the actual contract responsibilities.

## Routing and release register

| Gate | Evidence to request | Bid consequence if open |
| --- | --- | --- |
| Application completeness | Scope, photographs and filing drawings accepted for review | Carry design and submission work, not a presumed review duration |
| Design review | Staff or Commission path and decision | Keep long-lead design-dependent items conditional |
| Final drawings | Approved details and any remaining filing revisions | Level bids against the same revision |
| Procurement release | Owner and designer authorization against approved detail | Record fabrication hold and vendor validity |
| Work permits | Applicable LPC and DOB permits and conditions | Sequence field start against actual approvals |

In an illustrative storefront bid, a proposed new surround is still under design. The estimator can price a defined provisional detail, identify who completes the application, and request a dated decision on review path. A submitted application is not a fabrication release. If the final approved profile changes, reconcile the quote and schedule before buying material.

Use [NYC building code preconstruction review](https://piper-ai.com/resources/nyc-building-code-preconstruction-review) for the separate DOB basis and [prebid RFI review](https://piper-ai.com/resources/construction-rfi-prebid-scope-review) to assign the unresolved answer.