# NYC sidewalk sheds: reconcile height, lighting and the filing basis

A sidewalk shed quote should be leveled against its filing basis and site geometry, not just its linear footage. For an NYC GC pricing facade or other work, the practical decision is whether the quoted design, lighting, installation and maintenance cover the same documented arrangement. Obtain the submission date and design professional's drawings before deciding whether a lower quote is comparable.

## Establish the filing basis and geometry

[DOB's height notice](https://www.nyc.gov/assets/buildings/pdf/ll47height-in.pdf) says shed construction documents submitted on or after August 15, 2025 generally require 12 feet of clear ceiling height. Documents submitted earlier do not require the shed to be raised under that notice. Site-specific provisions allow a registered design professional (RDP) to document a different height where the notice's light and air or egress conditions apply. Egress must not be obstructed. Have the RDP determine and document the applicable design; do not infer an exception from a photograph.

The notice also explains how certain lights and bracing are treated in measuring clear height. Request a coordinated drawing showing the relevant existing openings, entrances, obstructions and adjoining frontage. An estimate can carry the issued design without pretending to resolve the engineering.

## Connect lighting to the electrical package

For documents submitted on or after August 15, 2025, [DOB's lighting notice](https://www.nyc.gov/assets/buildings/pdf/ll47light-in.pdf) identifies a minimum of 1.5 foot-candles (17 lux) at the walking surface, rising to 5 foot-candles (55 lux) within 10 feet of a subway entrance, bus shelter or similar transit facility. Earlier submissions may retain the prior 1 foot-candle level under the notice, and voluntary upgrades are possible.

Ask the design and electrical teams to identify the applicable area, fixture and power basis, installation, connection, operation, maintenance and removal. A shed bidder's fixture allowance and an electrician's power exclusion can leave a gap even when both bids mention lighting. Establish who verifies the completed installation against the design and who responds to failures during the shed's term.

## Level a fictional quote pair

Assume a new filing for a facade repair, with a bus shelter near one end of the proposed shed. Quote A includes the structure and fixtures but excludes power and ongoing maintenance. Quote B includes power and maintenance but does not identify the transit-adjacent lighting basis. Neither quote is ready to compare solely on price. Send both the same issued drawings and request the electrical and lighting boundaries in writing. The design team must confirm the actual layout and applicable requirements.

| Source or assumption | Scope | Owner | Estimate treatment | Closure evidence |
| --- | --- | --- | --- | --- |
| Filing receipt and DOB notices | Applicable height and lighting basis | Filing lead and RDP | Carry issued design or explicit unresolved qualification | Submission record and design confirmation |
| RDP drawings and site survey | Height, egress, light and air interfaces | RDP and shed trade | Include documented geometry and any approved change | Issued drawings and applicable RDP notes |
| Electrical and shed proposals | Fixtures, power, operation and repairs | Electrical and shed leads | Add back exclusions once and assign duration | Leveled quotes and written handoff |
| Project schedule | Moves, maintenance and removal | GC operations | Carry periods and remobilizations on stated sequence | Schedule and responsibility matrix |

Keep permit and design questions open until the responsible team resolves them. The [facade scope review](https://piper-ai.com/resources/nyc-local-law-11-facade-construction-scope) connects the temporary arrangement to repair quantities and closeout, which remain separate from the shed quote.