# 35th Avenue and Van Buren BRT: what concurrent design and CMAR need to resolve

For a GC following Phoenix’s 35th Avenue and Van Buren BRT work, the useful preconstruction question is how a developing design will define access and temporary operating responsibilities before the CMAR team prices them. The August 2026 report is a dated baseline, not proof of today’s procurement stage.

The [Citizens Transportation Commission August packet](https://www.phoenix.gov/content/dam/phoenix/publictransitsite/documents/CTC_August_2026_Packet_F.pdf) reported 15% design complete, a center-running preferred lane after outreach, and proposed separate final-design and construction RFQs with concurrent design and CMAR services. Check later city records and any issued solicitation before using those statements as a current milestone or bid instruction.

## Put the interfaces on one estimate register

The following are estimating questions, not commitments made by the city or contract requirements.

| Interface | Assigned check | Trigger to reprice |
| --- | --- | --- |
| Business and driveway access | Logistics lead maps affected frontages and asks design team for phase drawings | Closure duration or access arrangement changes |
| Temporary stops and passenger routes | Transit interface lead checks owner requirements and operating plan | Stop locations, accessibility route or duration changes |
| Signals and traffic control | Civil estimator checks agency approvals and electrical scope boundaries | Signal sequence, cutover windows or responsibility changes |
| Utilities and drainage | Utility coordinator checks drawings and owner information | Conflict resolution changes work sequence or quantities |

For example, a hypothetical quote may include pavement replacement but exclude temporary business access. The GC should identify whether another package includes a temporary crossing, traffic control and reinstatement. A blank proposal is not evidence of inclusion. Request clarification, carry a named provisional basis if appropriate, and show the cost and schedule consequences of a changed phase.

## Separate design maturity from permission to work

Concurrent design and preconstruction can expose constructability questions early, but a preferred lane concept does not settle property access, signal approvals or an operating plan. Record the decision owner, required evidence and date needed for each assumption. When the next design issue arrives, compare the changed work limits to quantities, work windows and trade exclusions, then revise the carry together.

Use the [construction-access assumptions review](https://piper-ai.com/resources/construction-logistics-plan-estimate-review) to connect the drawing to handling, staging and repeated moves. Actual obligations follow the issued contract and agency approvals.

## Track the community scope before final pricing

The [November 4 Council agenda and supplemental memo](https://www.phoenix.gov/content/dam/phoenix/cityclerksite/city-council-meeting-files/2026/11-4-26%20Formal%20Agenda%20-%20FINAL%20REVISED.pdf) add a coordination signal beyond the August design summary. Transit staff identified a local Community Advisory Board and an emphasis on local workforces as examples to bring into the solicitation process. Track community liaison effort, work-window changes and business access assumptions in the estimate. Assign an owner to read the final solicitation and move each item from a planning note to a priced obligation only when the issued language supports it.

## Check the roadway baseline by segment

The City’s [Van Buren workshop](https://meetphoenixbrt.com/online-meeting/) described mixed running between 7th and Central avenues. Confirm that transition in the issued alignment before using a single cross-section for the corridor. On 35th Avenue, the [separate Safety Corridor award](https://phoenix.legistar.com/LegislationDetail.aspx?G=3F9B5896-D56F-4AD3-85AD-A8E5E58DD74C&GUID=306805B0-522E-46B9-969B-7258CFEC5D92&ID=7777767&Options=&Search=) establishes another work package. Request current records for safety-project work before assuming which pavement, medians or signals the BRT scope must retain, modify or replace. Keep the safety package and the BRT pursuit distinct in the estimate.