# Advancing Data Center Construction West 2027: utility questions for preconstruction

Take one unresolved utility assumption to Advancing Data Center Construction West and return with a verification owner and a date. The point is to turn a possible power or water alternative into a documented estimate basis, not to infer that any utility has committed service.

The [organizer’s event page](https://advancing-data-center-construction-west.com/paged-7/2/) lists March 23–25, 2027 in Phoenix and identifies workshops on alternative power and water and market entry. Match the workshop to the assumption: an electrical preconstruction lead can assess a power dependency, while a mechanical or process lead can pursue the water boundary. Check the current organizer agenda and attendance terms before selecting a delegate. These questions are independent preparation, not a description of individual panels.

## Build a utility gate grid

| Gate | Evidence and date to request | Temporary alternative to evaluate | Trigger to reopen estimate |
| --- | --- | --- | --- |
| Permanent power | Written project-specific service scope and anticipated availability | Temporary power basis, fuel, duration and connections | Capacity, energization date or responsibility changes |
| Water supply | Project-specific source, quantity, quality and availability evidence | Temporary supply or revised construction sequence | Source, volume, connection date or quality basis changes |
| Interface and approvals | Current drawings, owner responsibilities and applicable approval schedule | Alternate route or staged commissioning basis | Design or approval path changes |

The grid is an estimating tool, not evidence that any of those services or alternatives is available. Assign the owner’s utility contact or design lead to seek project-specific documentation. Record its revision and date; distinguish a discussion from a written commitment and the latter from an approved construction plan.

## Price the alternative as a chain

In a hypothetical estimate, permanent power is assumed available for testing on a particular date. If that date is unconfirmed, a temporary-power carry may need equipment, connections, fuel, delivery, operation, removal and testing support. Identify who includes each item and the duration basis. A changed date can affect both the temporary system and commissioning sequence; check for duplication with trade bids before adding a GC allowance.

After the event, use the [data center preconstruction checklist](https://piper-ai.com/resources/data-center-precon-checklist) to assign the open interfaces. Set a date for utility evidence, the person responsible for obtaining it and the specific capacity or schedule change that triggers redesign and repricing.