# Phoenix Fire Station 15 bid tab: when the lowest total differs from the award

Phoenix’s April 2025 bid tab for Fire Station 15 includes two totals below the $11,010,000 award amount. The June Council record identifies those two offers as nonresponsive. A bid team that records only opening prices misses the condition that determined which bid the City could accept. [City bid tab](https://solicitations.phoenix.gov/Solicitations/GetSolicitationAttachment?attachmentId=19675) · [Adopted Council award](https://phoenix.legistar.com/LegislationDetail.aspx?G=3F9B5896-D56F-4AD3-85AD-A8E5E58DD74C&GUID=5305FD50-D979-4B96-B7C4-57C835CBA8FA&ID=7419935&Options=&Search=)

## Trace the numeric ranking to the award

| April bid tab | Reported total | What the June Council record says |
| --- | --- | --- |
| BPR Companies | $9,795,873 | Nonresponsive |
| BFL Construction | $11,003,075 | Nonresponsive |
| Danson Construction | $11,010,000 | Lowest-priced responsive and responsible bidder |

The difference between the lowest listed total and the awarded amount was $1,214,127. The difference between the second listed total and the award was $6,925. The adopted record identifies the responsiveness outcomes. Use the City's own project-specific evaluation record if you need to know why a particular offer failed.

## Run a release check while corrections are still possible

Give every mandatory form and attachment a named owner and a checked copy of the exact submission version. In the [preliminary bid record](https://solicitations.phoenix.gov/Solicitations/GetSolicitationAttachment?attachmentId=19623) for this project, the City separately tracked acknowledgments, proposal forms and subcontractor-related paperwork. The solicitation and its issued amendments set the checklist for the next pursuit. Have the final uploader verify the file set against that checklist shortly before release.

## Keep the tab useful for estimating

The tab also splits building, on-site and off-site work into different lump-sum lines. The public totals help you identify where to ask a question. A bidder’s own takeoff, written scope and revisions explain whether two prices include comparable work. Carry the total-price comparison and the responsiveness evidence as two separate parts of the [bid evaluation workflow](https://piper-ai.com/resources/bid-tabulation-vs-bid-leveling-vs-bid-evaluation).