# How to read Phoenix MAG specifications and City supplements before pricing

Build the estimate from the documents incorporated into the particular contract, not from a folder labeled “MAG.” Phoenix lists its City supplements to the regional specifications separately from supplements to standard details. Those labels do not establish which edition governs a particular bid.

The [Office of the City Engineer](https://www.phoenix.gov/administration/departments/city-engineer.html) lists 2024 City supplements to the MAG 2023 Standard Specifications, with a March 2026 update, separately from City supplements to MAG 2024 Standard Details. The [City specification supplement](https://web-prod.phoenix.gov/content/dam/phoenix/streetssite/documents/2024-COP-Supplements-to-MAG-2023-Standard-Specifications_Final.pdf) describes a regional base with City supplements. Confirm the editions and applicable changes in the issued solicitation and contract documents.

## Make an issue-specific document register

The following is an illustrative register, not a statement that these editions govern every job.

| Document | Record before pricing | Review owner |
| --- | --- | --- |
| Regional base specification | Edition, section and issued reference | Civil estimator |
| City specification supplement | Edition, update date and affected section | Civil estimator |
| Standard details and City detail supplement | Each edition and applicable detail number | Civil estimator and designer |
| Project special provisions | Package issue, addenda and specific provision | Proposal lead |
| Drawings and clarifications | Sheet revision, question and response | Document controller |

A register is useful only if it points to the actual requirement. Read the relevant base section, the matching City modification, the applicable detail and the package special provisions together. Where they appear inconsistent, send a precise question citing each document and revision. Do not infer a precedence order from this article; use the contract's own order of precedence and obtain clarification when needed.

## Carry the requirement to trade coverage

For a hypothetical pavement restoration item, the estimator records the location and quantity basis, the requirement and source version, and whether the paving subcontractor, earthwork subcontractor or GC carries testing and restoration. Ask each bidder to identify exclusions and any assumed limits of work. If a required test is not covered, price a separate carry or resolve the responsibility before bid; if two bids include it, avoid double counting.

The point is not that every Phoenix project has the same testing or restoration obligation. The question is whether the issued requirement has a named owner and a traceable cost. Extend this approach with the [specification scope review](https://piper-ai.com/resources/construction-specifications-masterformat-scope-review).