---
title: 'Plug numbers in bid leveling: when to plug, how much, and how to show it'
url: 'https://piper-ai.com/resources/plug-numbers-bid-leveling'
description: 'A defensible bid plug prices a named gap and a credible way to buy it. Separate quote, adjustment and exposure, then retire the plug when coverage changes.'
contentTypes: [guide]
publishedAt: '2026-11-30T15:52:15.877Z'
author: 'Ido Gedanken, CEO'
readingTime: 10
---

# Plug numbers in bid leveling: when to plug, how much, and how to show it

1. A plug should represent a credible procurement path, not just the missing quantity.
2. Keep bidder price, GC scope adjustment and residual exposure separate.
3. Use the bidder-switch threshold to prioritize clarifications.
4. Retire a plug only when replacement coverage matches its scope and conditions.

On a hard-bid commercial project approaching bid day, use a plug when required work is unpriced and you can describe a credible way to buy it. Do not use one merely to make the bid tab look complete.

A **plug**, as used here, is a GC-developed provisional estimate for missing scope or an unquoted package. It is not a subcontractor offer. The number should price the scope, the conditions of execution and the likely procurement route. Keep it separate from the bidder's price, assign a follow-up owner and state what evidence will replace it.

Our position: **a defensible plug is an estimate of a purchase, not just an estimate of work.** The same missing quantity can cost different amounts when added to an incumbent subcontractor's work versus bought as a separate package. That distinction can change which bidder you carry.

For the underlying process, use the [construction bid leveling guide](https://piper-ai.com/resources/construction-bid-leveling-guide). This article addresses the provisional dollars inside that process.

## Decide what the plug is replacing before pricing it

Separate three situations before entering an adjustment.

**Known missing scope.** A proposal excludes a required item, or a clarification confirms it was not priced. You need an estimate of that item and a proposed owner. Examples include joint sealant excluded from concrete work or temporary protection excluded from a finish package.

**Uncertain coverage.** The quote is silent, or its qualification conflicts with the issued scope. Silence alone does not tell you whether to add dollars. Mark the coverage unresolved, ask a targeted question and, if you need a provisional number, label the assumption under which it applies. Do not present an assumed exclusion as a confirmed finding.

**No quote for a required package.** You need an independent package estimate, including the costs of delivering that package. A blank bidder column does not become a subcontractor bid because a GC puts a number in it.

This distinction matters at handoff. The PM needs to know whether to confirm an inclusion, negotiate an addback or procure an entirely new package. Those are different assignments even when the estimate contains the same dollars.

Do not solve a design question with an unexplained plug. At 50% CDs under CMAR, define the assumed system or performance basis first. At hard bid, follow the solicitation's clarification and qualification rules. An internal plug does not authorize a change to the offered scope or cure a submission requirement.

The framework below is estimating advice, not a contract rule. Its sources have narrower applications: the February 2026 UFS construction estimating supplement is informational unless incorporated into contract requirements; the IPA documents address UK government infrastructure estimates; FAR proposal-analysis provisions govern federal acquisition analysis. None establishes a universal GC plug percentage.

## Choose a cost basis that survives the actual purchase

Use the strongest applicable evidence, not automatically the newest number.

| Available basis | Use it when | Check before carrying it |
| --- | --- | --- |
| Same bidder's written addback | The bidder agrees to provide the missing work under matching conditions | Scope, revision, execution window, exclusions and validity |
| Another bidder's item price | The item is separately identified and genuinely comparable | Whether the price is incremental within that bidder's package or available separately |
| Takeoff plus current unit costs | Scope can be measured and a credible crew or supply basis can be built | Labor, equipment, material, fixed costs and subcontractor markup |
| Historical comparable work | Saved detail permits adjustment to this project's conditions | Scope, quantity, age, access, labor basis and embedded markups |
| Whole-package benchmark | Detailed information is not available for an early estimate | Use as a cross-check or provisional model, not proof of buyout coverage |

### Build up the unquoted work to a subcontract purchase basis

The current [UFS 3-740-05, sections 3-5.4 and 9-2](https://www.wbdg.org/FFC/DOD/UFC/ufs_3_740_05_2026.pdf), describes developing task costs from labor, equipment and materials. In lieu of a subcontract quotation, it describes pricing the tasks as direct costs and adding appropriate subcontractor overhead and profit.

For a GC plug, that gives a useful check sequence:

1. Identify the required work and document revision.
2. Measure or define the quantity on an explicit basis.
3. Build the variable cost from applicable rates and production assumptions.
4. Add fixed costs for the proposed delivery route, including any separate mobilization.
5. Identify subcontractor overhead and profit already included or still required.
6. Apply GC-level markups in the normal estimate structure without duplicating them inside the plug.

The supplement's section 9-1.2 also includes mobilization, transportation, setup and subcontractor overhead and profit in subcontract cost. The practical implication is more important than the checklist: **a crew-rate calculation and a subcontract purchase price are not necessarily the same amount.**

### Borrow scope evidence, not another bidder's economics

Another bidder may provide a useful current check. But an item carried inside a larger package is not automatically a price available to your chosen subcontractor or to a separate specialist.

Ask what the item price assumes: shared access equipment, one mobilization, continuity of work, or a minimum package size. Do not use the difference between two whole bids as the price of one exclusion. Other differences remain unresolved until checked.

If the bids use different units or quantity bases, settle that comparison first using normalizing unit-price and lump-sum bids.

### Reprice historical work instead of escalating a total blindly

[FAR 15.404-1(b)(2)(ii)](https://www.acquisition.gov/far/15.404-1) requires federal historical-price comparisons to use a valid prior basis and adjust for material differences in terms, quantities, market factors and the items themselves. It is not a private-GC leveling mandate, but it provides a sound test for borrowed prices.

For an occupied renovation, an old new-construction rate may need more than an inflation adjustment. Access, protection, fragmented work windows and separate mobilizations can change the assembly. Conversely, a historical change-order price may contain costs that do not belong in planned base work.

Write the adjustments rather than burying them in a multiplier. If the historical record does not preserve enough detail to explain them, use it as a cross-check, not the sole basis of a consequential plug.

## Worked review: the procurement route changes the apparent low bid

**Illustrative scenario. All quantities, prices and rates below are invented to demonstrate the method, not market benchmarks.**

A GC is leveling a concrete package for a hard-bid warehouse at bid-ready CDs. The issued package requires 1,200 linear feet of joint sealant at identified slab locations. Bid A explicitly excludes that sealant. Bid B confirms inclusion under the same scope and execution conditions. Assume all other package differences have been resolved.

- Bid A raw proposal: **$184,000**.
- Bid B raw proposal: **$195,000**.
- Required sealant quantity: **1,200 LF**.
- Assumed direct variable cost: **$6/LF**.
- Assumed subcontractor overhead and profit: **12%** of direct cost.

Both bidders exclude laboratory testing, but the GC already carries testing in a separate estimate line. That common exclusion needs a coverage reference, not another plug in both bid columns.

### Route 1: add the work to Bid A's planned operation

Assume Bid A can add the sealant through its planned operation, with $1,800 of incremental setup and access cost:

- Variable direct cost: 1,200 × $6 = **$7,200**.
- Direct cost including setup: $7,200 + $1,800 = **$9,000**.
- Estimated purchase adjustment: $9,000 × 1.12 = **$10,080**.
- Bid A provisional leveled amount: $184,000 + $10,080 = **$194,080**.

A appears lower than B by **$920**. But this is a GC estimate of an incremental addback. A has not agreed to perform it at that price.

### Route 2: buy the sealant separately

Assume a separate specialist would require $3,600 of setup, mobilization and access cost, with the same variable rate and markup:

- Direct cost: $7,200 + $3,600 = **$10,800**.
- Estimated separate purchase: $10,800 × 1.12 = **$12,096**.
- Combined cost using A plus the separate package: $184,000 + $12,096 = **$196,096**.

B is now lower by **$1,096**.

The quantity has not changed. The rate has not changed. The extra fixed cost of the separate purchase reverses the ranking.

This is the interaction to check before carry: UFS guidance builds a subcontract estimate from tasks plus subcontractor markup, while its subcontract-cost discussion includes mobilization and setup. Read together, those principles require the estimator to identify **which procurement route the plug prices**. Pricing an incumbent's marginal operation while planning a separate purchase leaves a gap even if the takeoff is correct.

### Use the switch threshold to write the clarification

The maximum adjustment before A reaches B is:

**$195,000 − $184,000 = $11,000.**

That is the bidder-switch threshold, not the presumed value of the sealant inside B's quote.

The useful clarification to A is specific: confirm a complete addback for the identified 1,200 LF, the applicable joint detail, preparation, execution window and access basis. A confirmed addback below $11,000 would preserve A's numerical advantage under the example's assumptions. An addback above it would not.

Do not send another bidder's pricing to obtain that response. Ask A to price the defined work independently.

Competent estimators can disagree about carrying the incremental route before written confirmation. The deciding issue should be evidence that A can and intends to execute that route, not a preference for the lowest spreadsheet total. In this example, our recommendation is to use the separate-purchase basis until A confirms the complete addback.

## Test whether uncertainty can change the decision

Do not give every plug the same blanket cushion. Test the uncertain inputs that affect the purchase.

The [IPA's 2021 Cost Estimating Guidance, pages 17 and 23 onward](https://assets.publishing.service.gov.uk/media/6050c9528fa8f55d324b0c84/IPA_Cost_Estimating_Guidance.pdf), distinguishes base cost, uncertainty around assumptions and probability-driven risk. Applying that distinction here, the sealant is required base scope. Uncertainty concerns its purchase cost. A possible additional remobilization would be a separate event to assess, not a reason to hide the required sealant in general contingency.

**Illustrative sensitivity, continuing the same example:** vary the separate-purchase direct rate from $5.50 to $7/LF while retaining $3,600 fixed cost and 12% markup.

- Lower tested adjustment: [(1,200 × $5.50) + $3,600] × 1.12 = **$11,424**.
- Upper tested adjustment: [(1,200 × $7) + $3,600] × 1.12 = **$13,440**.
- A's combined amount spans **$195,424 to $197,440**.

B remains numerically lower across those tested assumptions. This is not a statistical confidence interval and does not prove the range captures every outcome. It shows that refining the variable rate within this range will not reverse the choice; confirming an incremental execution route might.

Use that distinction to prioritize calls. Where reasonable assumptions cross the bidder-switch threshold, clarification can change the carry. Where they do not, spend review effort on confirming coverage and procurement feasibility rather than chasing immaterial unit-rate precision.

For one proposal with no competing offer, there is no switch threshold; the separate decision is addressed in single-bidder trade coverage.

## Show the plug as a decision record, not a modified quote

Keep three amounts visible:

- **Raw proposal:** what the subcontractor actually offered.
- **Scope-adjusted comparison:** raw proposal plus identified GC adjustments.
- **Selected estimate carry:** the chosen coverage route, including any separately identified residual exposure.

Do not rewrite A's quote as $196,096. Its offer remains $184,000. The extra $12,096 belongs to the GC's proposed separate procurement.

The [IPA Cost Estimating Requirements, pages 4, 9 and 12](https://assets.publishing.service.gov.uk/media/6050f086e90e07527e988210/IPA_CostEstimatingRequirements.pdf), connects estimates to source calculations, assumptions, scope documents, ownership and change controls. The following compact register applies those principles to bid-week plugs. It is a recommended GC artifact, not a mandated IPA form.

For every material plug, record:

- **ID and scope boundary:** named work, location, quantity and exclusions.
- **Requirement evidence:** drawing/detail, specification or issued scope, with revision.
- **Quote evidence:** proposal version and exact exclusion or unresolved language.
- **Procurement route:** bidder addback, separate purchase or self-perform basis.
- **Calculation:** quantity, unit, rate source/date, fixed costs and markup treatment.
- **Ownership:** estimate line, planned trade owner and person responsible for follow-up.
- **Decision sensitivity:** tested assumptions and whether they change the carry.
- **Status and replacement test:** what response is needed and when the team will revisit it.

In the example, the sealant record should say that the $12,096 prices a separate specialist and does not buy Bid A's acceptance. It should also reference the testing carry so neither the estimator nor PM adds laboratory testing again.

A color is useful for scanning. The record must still explain itself when printed or handed to someone who did not build the bid tab.

## Retire the plug by reconciling coverage, not deleting a cell

**Illustrative continuation:** A later issues a complete revised proposal of **$194,800**, incorporating a **$10,800** sealant addback under the required conditions.

The previous provisional combined amount was $196,096. Replace the $184,000 base plus $12,096 separate-purchase plug with A's $194,800 revised offer. The net reduction is:

**$196,096 − $194,800 = $1,296.**

It is not a $12,096 saving. The revised proposal has already added $10,800 of work.

Two opposite errors are possible:

- Retaining the old plug alongside the revised offer produces $194,800 + $12,096 = **$206,896**, duplicating coverage.
- Removing the plug from the old base without incorporating the addback returns the estimate to **$184,000**, dropping the sealant cost.

The replacement check catches both. Confirm the revised offer covers the same quantity, preparation, timing and access basis; then retire the old plug and preserve the reconciliation. If the response covers only part of the work, replace only that part.

For the broader revision workflow, use leveling revised quotes after addenda. The plug-specific discipline is simple: one scope boundary, one current coverage route, one explained movement in the number.

## Keep provisional adjustments connected to the project

A plug becomes difficult to defend when its scope, price basis and replacement response live in different places. A revised proposal should prompt a check of the adjustment it replaces, not just an update to the quote total.

[Piper's bid leveling workflow](https://piper-ai.com/use-cases/bid-leveling) compares proposals against the intended scope, extracts exclusions and qualifications, and surfaces differences with their sources. Raw bids, leveling adjustments and open clarifications remain visible together as revised proposals and addenda change the comparison.

That supports the distinction this article argues for: the subcontractor's offer stays identifiable, the GC's provisional adjustment stays explainable, and the team decides which coverage route and number to carry. Piper supports that review; it does not decide consequential assumptions or the final carry.

### When should a GC use a plug in bid leveling?

Use a plug when required work is unpriced and the team can define a credible procurement basis. Identify whether it replaces missing scope within a bid or an entirely unquoted package. If coverage is merely unclear, keep that uncertainty visible and seek clarification rather than treating silence as a confirmed exclusion.

### How much should a plug be?

Price the defined work under the intended delivery conditions, including applicable fixed costs and subcontractor markup not already included. Use a matching written addback where available, or build and cross-check an independent estimate. There is no universal percentage in the sources cited here; test uncertainty separately from required base scope.

### Can I use another subcontractor's price for the missing item?

Use it as evidence only after checking the scope and commercial basis. A price incremental to that bidder's larger package may not be available as a separate purchase. Confirm quantity, preparation, access, mobilization and embedded markup before using it to adjust a different bidder's proposal.

### Is a plug the same as contingency?

No, under this article's framework a plug estimates named unpriced work, while a separate uncertainty or risk provision addresses what remains uncertain. Required sealant belongs in scope cost even when its purchase price is provisional. Do not bury that cost in contingency and then leave trade ownership unresolved.

### When can I remove a plug?

Remove it when replacement coverage matches the scope and conditions it priced, and reconcile the net change. A revised quote may already incorporate an addback, so deleting the plug is not the whole calculation. Preserve the original basis and response; retain an adjustment for any portion still uncovered.
