# Preconstruction agreements: reconcile paid services, authority and the next commitment

Before a GC or CM accepts paid preconstruction work, reconcile the promised outputs with the time, compensation and authority needed to produce them. An agreement to prepare an estimate is incomplete for planning purposes if the team cannot identify its document baseline, revision allowance, recipient and the person who can resolve a request outside that baseline.

Start with the proposed agreement and all incorporated exhibits, amendments and schedules. The register below is a review aid, not a contract form or a determination of rights. Have counsel and authorized signatories settle the terms. Use it to make the questions they need to answer traceable.

## Find the boundaries in the actual agreement

For a CM-at-risk assignment, distinguish the preconstruction engagement from the later construction commitment. The [AIA A133-2019 public instructions](https://help.aiacontracts.com/hc/en-us/articles/1500009312921-instructions-a133-2019-standard-form-of-agreement-between-owner-and-construction-manager-as-constructor-where-the-basis-of-payment-is-the-cost-) provide one bounded example: they address preconstruction services and compensation separately from construction compensation, and describe an owner who may accept, reject or negotiate a GMP proposal. They are instructions for a particular form, not the executed agreement or a universal fee rule.

Even in that example, do not treat GMP acceptance as the only conceivable start route. The [AIA CMc FAQ](https://help.aiacontracts.com/hc/en-us/articles/1500009311261-faqs-construction-manager-as-constructor-family-cmc) describes commencement through a GMP amendment or a written agreement before GMP acceptance. Read the actual documents to determine what, if anything, has been authorized. A paid preconstruction engagement alone should not be treated as a construction award.

## Build an agreement review register

The following is an illustrative register for a commercial CM estimating assignment. Replace every assumption with the applicable section, exhibit and named project role before relying on it. The rightmost question is an open decision, not a proposed contract clause.

| Review item | Example baseline to reconcile | Evidence and decision to obtain |
| --- | --- | --- |
| Service and output | Two estimates at identified design milestones, with documented assumptions and exclusions | Identify the scope exhibit, versions of drawings and specifications, and whether trade pricing is included |
| Revisions and duration | One reconciliation of each estimate during the stated service period | Find the revision allowance and end date; ask who decides whether a later redesign is within scope |
| Staffing and dependencies | Estimating lead and trade input depend on timely design and owner information | Identify named resources or effort assumptions, information providers, expected dates and the response to missing inputs |
| Receipt and acceptance | Deliver estimate to the owner's designated representative | Record the recipient, required format, acceptance criteria and evidence; distinguish receipt from acceptance |
| Fee and billing | Fee and invoice milestones identified in the agreement | Record billing basis, deliverable or time support, invoice reviewer and the person authorized to approve payment |
| Reimbursables | Travel or specialist input only if the agreement provides for it | Identify eligible expenses, required advance approval, approver and supporting records |
| Extension and additional work | A later estimate or delayed input may exceed the described period or allowance | Identify the trigger and who can agree to scope, fee and schedule changes; leave unresolved items open |
| Early work and next commitment | Pricing an early equipment package is distinct from placing an order | Identify procurement authority, spending limit, required written authorization and separate construction start or commitment documents |

The estimate itself needs a reliable decision baseline. [Define the deliverables supporting the next decision](https://piper-ai.com/resources/preconstruction-services-deliverables-gc) alongside this commercial review: an acceptance rule cannot compensate for an unidentified drawing set or an unclear exclusion.

## Separate six decisions that can look like approval

An owner's review of information may request clarification without accepting the deliverable. Acknowledging receipt may establish delivery without resolving whether the submission meets the agreement. Acceptance, if defined in the documents, is a separate decision from approving an invoice. Likewise, permission to investigate a long-lead item is not necessarily authority to issue a purchase order, and an early procurement authorization is not necessarily a notice to begin all construction or a final construction commitment.

For each step, record the document and version, decision sought, authorized role, required form of record and any conditions or dollar limits. If the agreement is silent or documents conflict, mark the authority unresolved and route the question to counsel and the authorized signatories. Do not infer authority from a meeting invitation or an email acknowledgment.

## Work through a third estimate request

Suppose the agreement describes two estimates during a six-month service period, with one reconciliation of each. After that period, the owner asks for a third estimate using a substantially revised mechanical design. This is a hypothetical review, not a conclusion that extra compensation is automatically owed.

The preconstruction lead should log the dated request and revised design set, compare them with the service and revision language, and identify the staffing and trade-pricing time needed. Ask the authorized parties to resolve whether the request falls within the agreed scope, what compensation and reimbursables apply, and whether the schedule or service period changes. Record the agreed direction and its authority before treating the revised forecast as a committed deliverable. If the owner also asks to reserve equipment, separately identify whether a purchase commitment is authorized and on what terms.

The handoff is ready when the team can point to the governing records for the current service, the next decision and any open commercial issue. If a decision remains open, assign a person and a date for resolution rather than silently carrying the request in the fee.