# Put experience into every bid: turn lessons into pre-bid survey questions

A company’s hardest lessons usually sit in closeout reports and in the heads of two or three senior people. They only change the next bid when they are written as questions, with a rule for what counts as a red flag, and asked of every bid’s documents.

## A lesson only changes the next bid if it becomes a question

On a fast bid, with the senior person on another job, the questions that came from past losses do not get asked.

Putting experience into every bid means writing each lesson as a question with a red-flag rule, asking it of every bid’s documents, and treating “not found in the documents” as a finding rather than a blank.

## Worked example: four of a company’s 24 questions, on one new bid

Hypothetical: a GC’s survey template, owned by the chief estimator, has 24 questions in four sections. Three of these came from jobs that hurt. The red-flag rules are the company’s own.

| Where | What it says | If nobody connects it |
| --- | --- | --- |
| Who provides temporary heat and winter protection? | Rule: red if the GC provides it and exterior work runs December to March. Answer: Spec 01 51 00 puts temporary heat on the contractor, and Addendum 2 moves the structural pour to January. | Red. Without the question, winter protection is assumed to sit with the concrete sub, who will exclude it. |
| Liquidated damages, and is there a cap? | Rule: red if over $2,500 a day or no cap. Answer: Agreement Article 5, $3,000 a day, no cap stated. | Red. The final review checks this against the schedule duration you carry. |
| Is a geotechnical report part of the bid documents? | Rule: red if not found. Answer: not found in the bid documents. | Red. “Not found” becomes a pre-bid question before the deadline, not an assumption. |
| Is a project labor agreement required? | Rule: note only. Answer: yes, Instructions to Bidders, item 14. | Cited, so labor pricing starts from the right basis. |

The temporary heat answer is why the estimator adds winter protection to the GC’s own scope, and why it matters again when both concrete bids exclude it in leveling. One question, three workflows.

> **Bring the questions your team asks on every bid.** Send ten of your standard pre-bid questions and one current bid package. In the demo we run them on your documents together and look at the red flags and the answers that were not found. [Book a project demo](https://piper-ai.com/demo)

## Twelve questions to seed a pre-bid survey

A starting point. The value is in your own list and your own red-flag rules.

1. **Delivery method and contract form.** And who holds design risk.
2. **Bid security and bonds.** Form, percentage, surety rating, and whether you have the capacity.
3. **Liquidated damages.** Rate, cap and any consequential damages language.
4. **Schedule constraints.** Duration, milestones, phasing, occupied building or night work.
5. **Work assigned to the GC.** Temporary utilities, winter conditions, hoisting and site logistics.
6. **Owner-furnished items.** Who receives, stores and installs them.
7. **Allowances, alternates and unit prices.** The ones the owner sets.
8. **Labor requirements.** Prevailing wage, PLA, apprenticeship, local hire, and M/WBE or SDVOB goals.
9. **Missing documents.** Geotechnical report, hazmat survey, existing-conditions drawings.
10. **Insurance beyond your standard program.** Builder’s risk, wrap-ups, limits.
11. **A past lesson, as a question with a trigger.** “If an occupied hospital, does the spec require ICRA Class IV containment?”
12. **Go/no-go signals your company agreed on.** Answered by people, with the document answers in front of them.

## Questions the documents and the law make worth asking

- To get a bond, a contractor must meet the surety’s credit, capacity and character requirements, so bonding capacity is a go/no-go input, not a formality. Source: [U.S. Small Business Administration](https://www.sba.gov/funding-programs/surety-bonds).
- Performance and payment bonds are required on federal construction contracts over $150,000. Source: [FAR 28.102-1](https://www.acquisition.gov/far/28.102-1).
- On New York public work above set cost thresholds, the owner prepares separate specifications for plumbing, HVAC and electrical, which changes who the GC can coordinate and carry. Source: [NY General Municipal Law §101](https://newyork.public.law/laws/n.y._general_municipal_law_section_101).

## Related guides

- [Building a pre-bid questionnaire](https://piper-ai.com/resources/survey-pre-bid-questionnaire): the question set, flagging answers, and follow-ups.
- [Lessons learned are useless if they stay in closeout](https://piper-ai.com/resources/lessons-learned-useless-if-they-stay-in-closeout): why experience has to be asked, not archived.
- [Why construction estimates start from zero](https://piper-ai.com/resources/why-construction-estimates-start-from-zero): company knowledge that never reaches the next bid.
- [Performance and payment bonds in bid review](https://piper-ai.com/resources/construction-performance-payment-bonds-bid-review): the bond questions to settle before you bid.
- [Pre-bid RFIs and scope review](https://piper-ai.com/resources/construction-rfi-prebid-scope-review): what to do with the answers that were not found.
- [Estimating is risk management](https://piper-ai.com/resources/estimating-is-risk-management-not-cost-calculation): the case for asking the same questions every time.

## Where Piper fits

- Keep company survey templates with your own questions, instructions and red and green flag rules.
- Run a survey on each project. Answers cite the page in the bid documents they came from.
- When an answer is not in the documents, Piper says so instead of guessing.
- Attach a survey template to a project template so every new project starts with it.
- The answers stay in the project where scope generation, bid leveling and final review can read them. Your team makes the go/no-go call.

See how the [pre-bid survey workflow](https://piper-ai.com/use-cases/survey) works, or [book a project demo](https://piper-ai.com/demo) and bring the documents from a bid you are working on now.