# Schedule logic checks to run before the schedule goes in the bid

1. Check whether each activity's finish affects the work it releases, not just whether it has a successor.
2. Review calendars before treating negative float as a need for acceleration.
3. Keep contractual deadlines separate from the dates the network calculates.
4. Test changes on a diagnostic copy and carry the resulting decisions into the estimate.

Before a GC submits a CPM schedule with a commercial hard bid or a CMAR pricing commitment, the scheduler should test whether it responds to changes in the work. A schedule that lands on the owner's date is not enough. Its procurement, field production and acceptance paths need to explain how it gets there.

Run the checks in this order: establish the calculation basis, find disconnected starts and finishes, inspect leads and lags, challenge imposed dates, then trace float and test the driving path. That order matters. A calendar error can look like a duration problem. A missing finish relationship can look like available float. A forced date can hide both.

**The release question is not “How many warnings remain?” It is “Which unresolved warning could change the date or the number we are committing to?”**

This guide is a prebid review of a logic-driven schedule. It is not a full schedule risk analysis, a delay-entitlement analysis or a substitute for the project's scheduling specification. For organizing the draft before this review, use the separate preconstruction schedule tips.

## Use DCMA as context, not a bid-release certificate

The DCMA 14-point assessment is useful context for schedule-quality review. GAO's December 2015 *Schedule Assessment Guide*, GAO-16-89G, describes its measures as covering logic, leads, lags, relationship types, constraints, float, durations and other subjects, including baseline execution. That is a broader scope than a first-draft bid schedule. See [GAO's discussion of schedule assessment](https://www.gao.gov/assets/d1689G.pdf).

Do not describe the checks below as the full assessment or as proof of compliance with a current DCMA requirement. A prebid network without execution history cannot answer the same questions as a progressed schedule with a baseline. Report what was checked and what was not applicable.

Keep three authorities separate:

- **The solicitation and incorporated scheduling specification** determine this bid's requirements.
- **Government guides and review checklists** provide reference methods within their stated scope.
- **The GC's release gate** is a professional judgment about the commitment the team can defend.

For example, [UFGS 01 32 01.00 10, August 2026](https://legacy.wbdg.org/FFC/DOD/UFGS/UFGS%2001%2032%2001.00%2010.pdf), addresses calendars, open-ended logic and lags in sections 3.3.10, 3.3.11 and 3.3.16. It is a guide specification intended for project-specific editing, not a rule automatically governing every commercial bid.

The distinction is practical: a documented exception acceptable in an internal commercial review may still violate an incorporated contract clause. Neither a clean metric nor an explanatory note overrides that clause.

## 1. Establish the calendar and calculation basis first

Before interpreting dates or float, record the schedule's data date, assumed start, duration units, hours per working day, activity calendars, deadline settings and calculation options. Then recalculate the file being reviewed.

Ask which durations represent **crew work** and which represent **elapsed time**. A field installation, an owner review and a cure period do not necessarily belong on the same calendar.

The August 2026 UFGS requires calendars appropriate to the activities, a default calendar matching the physical work plan, and seasonal calendars where applicable. Separately, [NAVFAC's January 2025 baseline review checklist](https://www.wbdg.org/FFC/NAVGRAPH/01%2032%2017.00%2020_Contractor_Baseline_Project_Schedule_Review_Checklist_2025.pdf) checks both calendar assignments and working-hour settings, and connects work calendars to the working-hours specification. Those federal documents are examples of why checking a calendar's name alone is inadequate.

For a commercial prebid review, inspect the actual exceptions and assignments:

- Does the field calendar reflect the shifts priced in the estimate?
- Are holidays and restricted access periods represented where they affect work?
- Is an elapsed review duration accidentally consuming only working days?
- Is weather applied to affected field work, rather than indiscriminately to indoor work and procurement?
- Does a displayed “day” represent the hours assumed in the production basis?

Do not use this pass to validate every production rate. Establish that the units agree first; use the separate guide to durations from takeoff quantities for the production-rate review.

The bid-week failure is to shorten an activity until the date looks right without discovering that the activity is on the wrong calendar. That changes the production commitment to repair a calculation-basis error.

## 2. Find dangling finishes, not just missing successors

An open end is a missing connection needed to make the network respond to the work. Checking activities with no predecessors or no successors is necessary, but insufficient.

Inspect the **endpoint** each relationship controls. Finish-to-start links a predecessor's finish to a successor's start. Start-to-start links their starts. An activity can have a successor and still have a finish that controls nothing.

The August 2026 UFGS makes this distinction explicit: except for its designated first and last activities, section 3.3.11 requires a start-controlling predecessor relationship and a finish-controlling successor relationship. NAVFAC's January 2025 baseline checklist also checks for open start or finish relationship logic. These are more demanding tests than counting connected activity IDs.

### Illustrative failure: the wall package appears connected

Assume a commercial interior package contains these activities:

1. Install in-wall services.
2. Inspect and release the wall zone.
3. Insulate and close the wall zone.

The draft connects services to inspection using only start-to-start logic. Inspection then connects finish-to-start to wall closure. A missing-successor report finds a successor for every activity.

Now increase the services duration by five working days in a diagnostic copy. Its start does not change. The start-to-start relationship therefore does not, by itself, move the inspection start. Wall closure may remain unchanged even though services finish later.

The problem is not simply a preference for finish-to-start relationships. The network lacks a defined **release boundary**. Does inspection require all services in that zone, or can inspection and closure proceed through smaller released areas?

The scheduler and superintendent should decide between two defensible models:

- If the entire zone must be complete before inspection, connect that completion to the inspection start.
- If work rolls through smaller areas, split the zone into meaningful release packages and connect each package to its actual inspection and closure handoff.

Do not attach every activity arbitrarily to the final milestone just to clear the report. That supplies a successor without explaining the construction sequence. Conversely, making every rolling operation finish-to-start can manufacture a delay by denying a buildable overlap.

**Acceptance test:** the prerequisite finish must affect the release it genuinely controls, at the geographic resolution used to plan and price the work.

## 3. Inspect every lead and material lag as a hidden assumption

A lead is a negative lag. A positive lag inserts time between linked endpoints. Neither tells the reviewer, by itself, what happens during that interval.

Section 3.3.16 of the August 2026 UFGS prohibits leads and start-to-finish relationships, and says lags must not replace realistic durations or proper logic, or artificially create or absorb float. NAVFAC's January 2025 baseline checklist requires prior approval for lead or lag logic within its applicable review framework. These are contract-specific reference positions, not universal commercial prohibitions.

Our prebid decision rule is narrower: **if the interval contains a deliverable, responsible party or release decision, model that work explicitly rather than burying it in a lag.**

A submittal review followed by fabrication deserves a review activity when approval releases fabrication. A fixed elapsed wait may remain a lag where the contract permits it, but its duration basis and calendar treatment still need checking.

For each material lag, record the predecessor and successor endpoints, reason for the interval, source or assumption, elapsed or working-time basis, and the calendar actually used by the calculation. Test its date effect in the scheduling file. Do not assume the predecessor's calendar governs it.

### Illustrative worked review: a false four-day delay

Assume a small concrete equipment-pad package has these explicitly hypothetical conditions:

- Placement finishes Friday at 17:00.
- The specified release condition is a seven-calendar-day wait, represented here as exactly 168 elapsed hours.
- Installation starts at the next available shift after release and needs ten eight-hour working days.
- Installation works Monday through Friday, with no holidays.
- The owner requires completion 24 elapsed days after placement, at Monday 17:00.

The correct wait ends the following Friday at 17:00. Installation starts Monday and finishes after two working weeks, on Friday at 17:00. That is **21 elapsed days after placement**, leaving a three-calendar-day margin to the stated deadline.

Now put the seven-day wait on the installation's five-day calendar. Seven working days count Monday through Friday, then Monday and Tuesday. The wait ends Tuesday at 17:00. Installation starts Wednesday and finishes ten working days later, on Tuesday at 17:00: **25 elapsed days after placement**.

The incorrect model finishes four calendar days later and one calendar day beyond the deadline. If the illustrative site-overhead allowance is $1,200 per calendar day, an estimator extending overhead to match that false delay adds **4 × $1,200 = $4,800**.

Those margins are simple deadline comparisons, not reported CPM total-float values. The scheduler must confirm actual dates and float in the full network.

The contribution is the diagnostic order: inspect the release requirement, wait calendar and installation shift boundary before buying acceleration or extending overhead. Merely replacing a lag with a named activity does not solve the problem if the replacement retains the wrong calendar.

Also check that the same wait is not already included in the placement duration. A named cure activity plus a cure allowance inside placement would count the obligation twice.

## 4. Separate the required date from the calculated date

List every date constraint and identify its authority. Is it a contractual completion date, an access restriction, a supplier assumption or an internal presentation target?

A contract deadline and a network forecast answer different questions. The deadline says when the work is required. The forecast says when the modeled sequence can finish.

[GAO's presentation explaining its final Schedule Assessment Guide](https://www.evmpforum.com/uploads/4/0/1/0/40106223/gao_evmp_2016_presentation_on_gao_schedule_guide.pdf) advises minimizing and justifying constraints and lags, explaining that constraints can prevent activity dates from responding dynamically to predecessor changes. NAVFAC's January 2025 baseline checklist separately examines contractually defined constraints and projected completion against contract completion.

Use a diagnostic copy to investigate presentation constraints. Do not remove genuine contract requirements from the submitted schedule.

| Date condition | Diagnostic question | Prebid treatment |
| --- | --- | --- |
| Contractual completion deadline | Does the calculated forecast meet it? | Preserve the obligation and explain any shortfall |
| Documented access restriction | What external event releases the work? | Retain the restriction and identify its basis |
| Assumed supplier delivery date | What approval or release starts the procurement sequence? | Expose the assumption and connect the supporting work |
| Internal target imposed on an activity | Does the network reach it without the imposed date? | Test without the target in a copy and resolve the difference |

A genuine external restriction can control a path without being a logic defect. The error is treating a desired date as though it were a documented external release.

For procurement, carry only the interface question here: connect the delivery commitment to its release basis, then use the guide to long-lead procurement in the preconstruction schedule for that chain's detailed review.

## 5. Trace float and prove that the driving path responds

Total float describes schedule flexibility within the network's calculation basis. GAO's guide presentation treats logic, reasonable float and a valid critical path as interrelated, not independent checks.

When negative float appears, investigate in this order:

1. Confirm the deadline, including its time of day and authority.
2. Confirm calendars and duration units.
3. Inspect the relationships, lags and constraints on the affected path.
4. Confirm the scope and release conditions represented by its activities.
5. Only then evaluate production, sequencing or procurement changes.

Negative float is not automatically an instruction to add a crew. Positive float is not automatically an available contingency. A disconnected finish or an omitted acceptance step can make apparent flexibility untrustworthy.

Trace the calculated driving path to each commitment that matters: phased access, substantial completion and final completion where the contract distinguishes them. Explain every gap between activities. A weekend transition may be legitimate; an unexplained lag or imposed date requires a decision.

[NAVFAC's January 2025 monthly review checklist](https://legacy.wbdg.org/FFC/NAVGRAPH/01%2032%2017.00%2020_Contractor_Monthly_Update_Schedule_Review_Checklist_2025.pdf) reviews reasonable longest-path workflow, government activities in the logic stream and gaps on that path. It applies to monthly contract schedule review, but provides a useful reference for the questions to ask before making a bid commitment.

Finally, perturb the diagnostic copy. Extend one driving field activity, then one procurement or approval activity that the team expects to matter. Recalculate and record which milestone moves, or which genuine restriction absorbs the change. Restore the copy after each test.

An unchanged finish is not necessarily a defect: available float, another parallel driving path or an external restriction may explain it. The failure is an unchanged finish that nobody can explain.

## Release a decision register with the schedule

Close the review with an exception register, not an unexplained warning count. Use one entry for each issue that could change a commitment:

> **Activity or relationship:** specific ID and affected endpoint.  **Evidence:** document, revision and page, or named planning assumption.  **Interaction:** the requirement plus the calendar, relationship or constraint that changes its effect.  **Diagnostic result:** before-and-after milestone dates from the tested copy.  **Estimate treatment:** duration-related carry, shift assumption, allowance or qualification affected.  **Decision:** correct, retain with basis, seek clarification or escalate.  **Owner:** person responsible for resolution and release.

Our proposed release gate is that every material exception has a disposition the scheduler and precon lead can defend. That does not mean every flag disappears. It means no unresolved item silently contradicts the bid's promise.

FHWA's [Contract Time Determination Technical Advisory, October 15, 2002](https://www.fhwa.dot.gov/construction/contracts/t508015.cfm), considers production resources alongside review periods, curing, utilities and work restrictions. Its highway-owner context is different from a commercial GC bid, but the useful interaction is the same: time assumptions cannot be reviewed independently of the resources and restrictions behind them.

When correction changes a date or shift basis, pass that decision into estimate and schedule alignment; do not let the scheduler repair the plan while the estimator carries the superseded basis.

## Make source-linked review part of schedule drafting

The repeatable workflow is a shared project basis: current documents, proposed sequence, calculation settings and an exception register that preserves why the team accepted each material assumption.

[Piper's scheduling workflow](https://piper-ai.com/use-cases/scheduling) drafts a CPM schedule from drawings, specifications and project documents, links activities to their sources, and checks logic using checks based on the DCMA 14-point assessment that apply to preconstruction. It asks where the documents are silent rather than inventing a start date or milestone.

Those checks support review; they do not establish that the modeled sequence is buildable or that a bid satisfies every contract requirement. Piper drafts and checks. The scheduler owns the logic, durations and final schedule, while the precon team owns the pricing commitment that follows.

### Is this a full DCMA 14-point assessment?

No. This is a prebid logic review informed by schedule-quality assessment concepts. It does not claim full DCMA coverage or current contractual compliance. State which checks were performed, which execution or baseline checks were not applicable, and which requirements come from the actual solicitation.

### Can an activity have a successor and still have an open finish?

Yes. A start-to-start successor relationship alone does not make that successor respond to the predecessor's finish. Check the actual release boundary. Use finish-controlling logic where completion is required, or smaller release packages where rolling inspection and follow-on work are genuinely planned.

### Should every lag become an activity?

Not necessarily. Our recommendation is to expose intervals containing work, a deliverable or a release decision as activities. A permitted elapsed wait may remain a lag, but its basis and calendar treatment need verification. The incorporated scheduling specification may impose a stricter rule.

### Does negative float mean the estimate needs acceleration cost?

Not by itself. Verify the required date, calendars, units, relationships and constraints before pricing acceleration. If the validated sequence still misses the obligation, evaluate a buildable recovery plan and its estimate impact. Do not shorten durations or remove genuine requirements merely to clear the warning.