# A scope gap register: close the coverage and the carry separately

1. Track each unresolved obligation once, then link the affected packages and proposals.
2. Coverage resolution and estimate reconciliation are separate closure tests.
3. A bidder clarification does not change the owner's requirements.
4. Replace provisional carry with confirmed pricing rather than stacking both.

A scope gap register should tell the chief estimator two things separately: **who will perform the required work, and where its cost sits in the current estimate.** Do not close an item merely because a subcontractor answered the question. Close it when the answer has reached the scope, the applicable proposal and the number being carried.

For a GC pricing commercial work at late CDs or setting a CMAR GMP, this is a decision register, not another list of drawing comments. Each entry connects a requirement to an unresolved boundary, a responsible reviewer, a clarification and a specific estimate treatment.

The useful discipline is simple: **one obligation, one record, two closure tests.** That prevents an issue from disappearing between trades. It also prevents the same exposure from being carried as a bid addback, a separate GC line and a leftover plug.

## Track the obligation, not every place someone noticed it

A scope gap is an unresolved mismatch between required work and its intended coverage. It may be missing from all proposals, included by two packages, or assigned without confirmation that the bidder priced it. A drawing conflict can create a gap, but not every drawing comment is a scope gap.

Use a register entry when the team must decide ownership, pricing treatment or the basis on which work will be solicited. Keep ordinary document questions in their appropriate review process and link them when they affect that decision.

The obligation is the record's identity. For example, “firestop cable penetrations through Level 2 rated corridor walls” is an obligation. “Electrical exclusion,” “low-voltage clarification” and “architectural detail review” are different evidence and action records attached to it. Creating three independent gap entries invites three independent carries.

Split the obligation when the work can genuinely be resolved separately. Penetration firestopping and head-of-wall joints should not share a single closure status merely because both appear in Division 07. The common scope gaps between trades guide covers the interfaces to look for; the register controls what happens after one is found.

This distinction has a contractual basis, but the register structure is estimating advice. In unmodified AIA A201-2017, Section 1.2.1 makes the contract documents complementary, while Section 1.2.2 says their organization does not control how the contractor divides work among subcontractors. Read together, those provisions separate **the existence of a project obligation** from **the GC's package assignment**. A specification reference proves neither that a particular bidder accepted the work nor that its price includes it. See the [publisher's A201-2017 sample, Sections 1.2.1 and 1.2.2](https://assets.aiacontracts.com/ctrzdweb02/zdpdfs/preview_a201-2017.pdf).

Check the actual agreement and supplementary conditions. A201 is an example, not a universal contract rule. The publisher continues to list the [2017 document in its current document catalog](https://learn.aiacontracts.com/articles/list-of-all-current-aia-contract-documents).

## Use columns that force a decision and a price destination

The following is a recommended register structure, not a prescribed industry form. Each table row describes a column or linked field group. Keep the main view readable and put long source passages or proposal details in linked records.

| Field or field group | What to record | What it prevents |
| --- | --- | --- |
| Gap ID and obligation | Stable ID; work, location and system; parent or related ID | Multiple records carrying the same work |
| Requirement basis | Drawing and detail; spec paragraph; revision or addendum; applicable contract basis | Treating a company preference as an owner requirement |
| Coverage evidence | Intended packages; exact proposal inclusions, exclusions or silence; proposal versions | Assigning work based on the trade name alone |
| Gap type | Missing coverage, overlap, ownership ambiguity, design ambiguity or stale basis | Sending every issue to the same clarification route |
| Action owner and decision authority | GC reviewer driving closure; bidder or design authority needed for the answer | Confusing the person chasing an answer with the person authorized to give it |
| Next action and needed-by point | Specific question; recipient; response required before solicitation, carry or buyout | A due date unrelated to the decision it protects |
| Coverage status | Unverified, clarification pending, confirmed or accepted assumption | Calling an unconfirmed assignment resolved |
| Pricing basis and exposure | Quantity and unit; estimate or quote basis; selected scenario; uncertainty | An unsupported lump-sum plug |
| Current carry destination | Estimate line or bid adjustment; amount; included, additive or replacement treatment | Counting both the plug and the confirmed price |
| Resolution and propagation | Response reference; scope version; proposal version; estimate version; reviewer | Closing an answer that never reached the documents or number |
| Reopen trigger | Changed source, quote, boundary, quantity or sequence that requires another check | Treating yesterday's resolution as permanent |

**Keep action owner, work owner and decision authority separate.** The MEP estimator may chase the answer. The firestopping subcontractor may perform the work. The design team's authorized representative may need to resolve the technical detail. Putting all three under “responsible party” makes the row look complete while leaving the next action unclear.

Likewise, distinguish exposure from adjustment. Exposure is the cost consequence under a stated scenario. The adjustment is what must change in the estimate now. They may be different because some work is already priced elsewhere.

Do not add every register amount into a project total. Rival bidder adjustments are mutually exclusive, overlaps may require deductions, and some exposure is already included in the carry. Summarize only the selected scenario's unreconciled adjustments.

## Route design questions and coverage questions differently

Start with a check sequence that separates authority from estimating judgment:

1. **Establish the requirement.** Read the current drawing, relevant specification and governing contract basis together. Record ambiguity rather than manufacturing certainty.
2. **Map intended ownership.** Identify every package that could reasonably carry the work and the issued boundary language.
3. **Test actual coverage.** Read each relevant proposal and attachment. Silence remains unverified until the team has an adequate basis to treat it otherwise.
4. **Send the right question.** Ask the design authority about the required result. Ask the bidder whether its price carries the defined work.
5. **Choose interim treatment.** If the answer will miss the carry decision, record a reviewed assumption and a supported cost basis.
6. **Propagate the resolution.** Update scopes, affected bids and estimate treatment, then perform both closure tests.

Do not ask a subcontractor to resolve an owner-document conflict merely because it is pricing the affected system. Its response can establish its proposed scope and price, not necessarily the governing design requirement.

For a federal contract incorporating [FAR 52.236-21, February 1997](https://www.acquisition.gov/far/52.236-21), paragraph (a) requires discrepancies to be submitted to the contracting officer for a written determination; contractor adjustments without that determination are at the contractor's risk and expense. That requirement is specific to applicable federal contracts. For other projects, use the authority and communication route established by the actual solicitation or agreement.

The register should therefore contain two linked questions when necessary: “What is required?” and “Does your revised price include that requirement?” An answer to the second cannot substitute for the first.

## Work a firestopping gap through to the number

**Illustrative example only. All quantities, quotes and rates below are synthetic estimating inputs, not market benchmarks or project results.** Assume a GC is pricing a commercial building at late CDs. The project specification adopts firestopping sequencing language like UFGS 07 84 00.

That official guide specification covers both penetrations and construction joints or gaps. Its Section 1.3 calls for coordination with other trades and inspection and approval before assemblies conceal installed firestop. The available document is dated May 2010, Change 1 August 2013, with references aligned to the July 2026 UMRL. It is an editable military guide specification, not a requirement automatically applicable to commercial projects. See [UFGS 07 84 00, Sections 1.1 and 1.3](https://legacy.wbdg.org/FFC/DOD/UFGS/UFGS%2007%2084%2000.pdf).

In this hypothetical project, the documents require penetration firestopping and pre-concealment inspection. The electrical and low-voltage proposals exclude firestopping. Drywall includes head-of-wall joints only. The GC creates SG-014 for cable penetration firestopping, with a linked inspection action rather than treating the drywall inclusion as complete coverage.

### Establish the provisional carry

The estimator's illustrative basis is:

- 120 cable penetrations at $85 each: **120 × $85 = $10,200**.
- Two planned installation visits at $900 each: **2 × $900 = $1,800**.
- Independent inspection, carried separately by the GC in this scenario: **$2,000**.

Total provisional project treatment is **$10,200 + $1,800 + $2,000 = $14,000**. The installation plug is $12,000; the inspection line is $2,000. SG-014 records both destinations and their relationship.

The important source interaction is not the multiplication. Penetration scope establishes the work, while the pre-concealment requirement makes the work dependent on access and inspection timing. The register must test the proposed number of visits against the planned wall-close sequence, not just against penetration count.

### Clarify both extent and operating conditions

A useful illustrative bidder question is:

> Confirm pricing for the 120 identified cable penetrations in the attached location list, excluding head-of-wall joints. Identify included visits, access assumptions and documentation. Installation must support the project's pre-concealment inspection sequence. Independent inspection is carried separately by the GC. Identify any exclusions from this basis.

Suppose the subcontractor responds with a synthetic quote of **$13,500**, including the identified penetrations, documentation and **three** installation visits, excluding independent inspection. The GC's operations reviewer confirms that three visits match the current planned close-in sequence.

The reviewed project treatment becomes **$13,500 + $2,000 = $15,500**. Compared with the provisional $14,000, the estimate moves **up $1,500**.

That is not evidence that the initial unit rate was wrong. The provisional assembly assumed two visits; the confirmed coverage includes three and defines documentation. The register explains why the price moved instead of reporting an unexplained variance.

### Replace the plug rather than add the answer

Remove the $12,000 installation plug and replace it with the $13,500 confirmed quote. Retain the $2,000 inspection line because that work remains outside the installation quote.

If the estimator adds the confirmed quote without removing the plug, the project carries **$12,000 + $13,500 + $2,000 = $27,500**. The overstatement is **$12,000**, exactly the abandoned installation plug.

Coverage may now be confirmed while estimate reconciliation remains open. That is why a single “resolved” checkbox is inadequate. SG-014 closes only after the scope boundary, quote reference and replacement estimate entry agree.

## Decide whether to centralize the work or assign it to each trade

Competent estimators can disagree about the package boundary. For the illustrative firestopping obligation, one may prefer a specialist package across trades. Another may prefer each penetrating trade to carry its own work.

Decide based on the project's installer requirements, access sequence, available qualified bidders and ability to maintain location-specific coverage. Centralized installation can make one boundary easier to inspect, but it still needs handoffs from the penetrating trades. Distributed installation can align work with each trade's progress, but it requires consistent treatment of documentation, inspection coordination and later penetrations.

Do not resolve that disagreement by picking the smallest isolated addback. Compare complete execution arrangements. In the register, record the selected arrangement and its interfaces, then issue consistent inclusions and exclusions to every affected package.

For requirements outside technical sections, use the Division 01 scope review rather than rebuilding that checklist inside each gap entry.

## Close coverage and carry, then preserve a reopen trigger

Use two independent closure tests:

**Coverage closure:** Is the requirement sufficiently defined, assigned and supported by the applicable proposal or other documented execution commitment? If unresolved, who approved the interim assumption, and what remains to be confirmed?

**Carry closure:** Does the current estimate reflect that treatment once, with superseded plugs removed and retained costs explained?

An accepted assumption is not confirmed coverage. Keep it visible as an exception in final review even when the estimate has a complete provisional treatment.

After award, transfer the agreed boundary into the subcontract documents rather than relying on the register to create the obligation; see bid scope sheets versus subcontract exhibits.

Reopen an entry when its supporting basis changes. For SG-014, triggers include changed penetrations, a revised rated-wall layout, a different close-in sequence or a quote that no longer includes the agreed visits. Preserve the prior resolution and create a new review state instead of overwriting the history.

Receipt and reconciliation are separate here too. Under applicable federal invitations incorporating [FAR 52.214-3, December 2016](https://www.acquisition.gov/far/52.214-3), bidders must acknowledge amendments, and unmodified terms remain unchanged. Acknowledgment documents receipt; it does not establish that affected subcontractor prices and estimate entries were reconciled. The guide to scope gaps created by addenda addresses that change review.

Before submission, filter the register for unconfirmed coverage, unreconciled carry, overdue decisions and accepted assumptions. Review those exceptions against the selected bids, not every possible bidder combination. The aim is a defensible commitment, not a dashboard full of closed rows.

## Keep scope decisions connected to the project and the bids

A register works when the requirement, package boundary, proposal response and carry share one evolving project basis. A spreadsheet can support this discipline if the team maintains those connections. The failure is not the file format; it is treating an answer as finished before its consequences reach the work being issued and priced.

Piper's [Scope Generation](https://piper-ai.com/use-cases/scope-generation) organizes requirements from drawings, specifications, addenda and company knowledge into trade-specific scopes, links items to their sources and surfaces unclear boundaries for review. Its [Bid Leveling](https://piper-ai.com/use-cases/bid-leveling) checks proposals against intended scope and surfaces exclusions, gaps and potential adjustments with their evidence.

Those workflows support the register's two tests: establish coverage, then reconcile what is being carried. Piper drafts and checks; the estimator decides ownership, clarification treatment and the final number.

### What is a scope gap register?

A scope gap register is a decision record connecting unresolved project obligations to trade coverage, clarifications and estimate treatment. Track the requirement once and link affected packages and proposals. Its purpose is to show both whether the work is covered and where its cost sits in the current carry.

### When should a scope gap be marked closed?

Close it only after coverage and estimate treatment are both reconciled. A clarification response may settle the boundary without updating the number. Confirm the applicable scope and proposal versions, replace superseded plugs, and identify retained costs before closing the record. Keep accepted assumptions distinguishable from confirmed coverage.

### Should every open gap receive a plug number?

No. First determine whether the work is already carried elsewhere or represents a mutually exclusive bidder scenario. When provisional pricing is necessary, record its quantity or quote basis, assumption and estimate destination. Do not sum every exposure as an additional project cost; reconcile only the selected carry scenario.

### Is the register the same as an RFI log?

No. An RFI log tracks document questions and responses; this register tracks the coverage and pricing decisions those answers affect. Link the formal question rather than duplicating it. A design answer may define the requirement while leaving bidder acceptance, execution ownership and the estimate adjustment unresolved.