---
title: 'How to write a site utilities scope subs will price on the same basis'
url: 'https://piper-ai.com/resources/site-utilities-scope-of-work'
description: 'Define storm, sanitary and water scope by connection, trench, restoration and acceptance limits, with a reusable outline and clear unit-price rules for bidders.'
contentTypes: [guide]
publishedAt: '2026-11-29T07:44:22.842Z'
author: 'Ido Gedanken, CEO'
readingTime: 12
---

# How to write a site utilities scope subs will price on the same basis

1. Define both the physical endpoint and the acceptance responsibility for every utility run.
2. Separate utility-owner fees and tap operations from the contractor's connection support.
3. Make excavation, replacement backfill and restoration treatment explicit in each price.
4. Issue depth-band and unit-price rules with the scope, not after proposals arrive.

For a GC estimator issuing a storm, sanitary and water package on a ground-up commercial project, the scope should define **a complete installation from an identified connection to an identified handoff, including the trench, restoration and evidence of acceptance**. A list of pipe sizes and specification sections is not enough to establish a common pricing basis.

Write two boundaries for each system: where the subcontractor's physical work stops, and what testing or connection responsibility remains after that stop. Then state which costs are included in the base, which belong to named others, and how uncertain quantities will be measured.

This guide applies to a contractor-designed trade package based on issued project documents. It is not a utility design specification, a substitute for utility-owner approval, or a universal rule for public unit-price contracts. At DD or an early GMP, unresolved connections and profiles need explicit pricing assumptions rather than language pretending the design is complete.

## Start with the document basis, not Division 33 alone

Build a dated package register before drafting the inclusions. For the general process, use the [construction scope generation guide](https://piper-ai.com/resources/construction-scope-generation-guide). The site-utility register should identify:

- Civil utility plans, profiles, structure schedules and connection details.
- Grading plans showing existing, interim and finished surfaces.
- Plumbing and fire-protection plans at building entries.
- Earthwork requirements and the geotechnical information issued for bidding.
- Pavement, curb, sidewalk and landscape restoration details.
- Utility-owner standards, approved connection details, permit conditions and written correspondence included in the solicitation.
- Applicable Division 01 requirements, bid instructions and every issued addendum.

Use actual sheet numbers, section titles, revisions and attachment dates. Do not write only “latest drawings.” Identify the set everyone received and require acknowledgement of subsequent revisions.

Useful technical references include the current posted UFGS masters for [33 11 00, Water Utility Distribution Piping](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2033%2011%2000.pdf), [33 30 00, Sanitary Sewerage](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2033%2030%2000.pdf), and [33 40 00, Stormwater Utilities](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2033%2040%2000.pdf). The water master is dated August 2024, the sanitary master May 2018, and the storm section is designated 11/21. The fetched files carry October 2026 reference updates.

These are federal guide specifications requiring project editing, not requirements automatically governing a commercial job. Use them to challenge the completeness of the issued package, not to import every material option or test into it.

One important interaction appears in the water master: its earthwork clause refers trench and bedding work to Section 31 00 00. **A requirement located in Division 31 can still belong in the utility subcontract.** Technical location and commercial assignment are different decisions. Reference the earthwork requirements and then expressly assign the utility trench work.

## Define endpoints by system and task

Prepare a boundary schedule with one row per run or connection. Use structure IDs, stations, coordinates or dimensioned details, not “to building” and “to street.” Give each row a size, material, elevation basis, physical endpoint, final connection owner and acceptance owner.

The water master terminates its scope approximately five feet from the building unless otherwise indicated. That is a useful document convention, not an automatic assignment for every project or every system. The [plumbing and site-utility boundary guide](https://piper-ai.com/resources/plumbing-underground-scope-boundary) develops that handoff separately.

For the package being issued, make the assignment inspectable:

| Interface | Physical work to assign | Responsibility beyond the endpoint |
| --- | --- | --- |
| Building service handoff | Identified stub, cap, coupling and surveyed elevation | Final joining, test-section completion and release for use |
| Water-main connection | Tap or tee, sleeve, valve, excavation and access support | Authority to operate valves, witness testing and restore service |
| Sanitary connection | Named main or manhole, opening, connector and channel work | Connection inspection and verification of the receiving system |
| Fire and domestic split | Named branch, valve, vault or riser handoff | Separate test requirements and acceptance participants |
| Pavement handoff | Trench backfill, temporary surface and final patch limits | Maintenance until final restoration and turnover condition |
| Dry-utility crossing | Protection and crossing support assigned to this package | Conduit, duct bank, cable or relocation assigned elsewhere |

Do not let “utility company taps excluded” exclude the entire connection operation. Ask who furnishes the sleeve and valve, exposes the main, prepares the excavation, provides access, coordinates the shutdown and backfills afterward. The water UFGS distinguishes connection coordination and valve-operation authority; it also contains agency-specific options splitting tapping-machine work from contractor support. Those options demonstrate why a fee, a tap operation and connection support should be separate scope entries, not one exclusion.

The GC should verify the actual utility owner's rules before assigning those entries. An unconfirmed tap arrangement belongs in clarifications with a common pricing basis, not in a blanket “by utility” note.

## Describe complete installations for storm, sanitary and water

Organize inclusions by system first, then shared construction work. This lets a bidder price each system without interpreting an undifferentiated list of appurtenances.

### Storm drainage

List every scheduled run and structure, including connections from the building storm system where assigned. Identify pipe material, size, class or strength, joint requirements, bedding detail and installation limits. Add inlets, catch basins, manholes, frames, grates, outlet structures, headwalls and end sections shown in the package.

Assign trench drains, downspout boots and detention or retention systems individually when shown. For an underground chamber system, identify responsibility for excavation, stone envelope, geotextile, chambers, distribution piping and access provisions rather than describing only the storage product.

The storm UFGS asks the designer to show pipe-class limits, invert elevations, watertight runs and special bedding conditions. It also addresses underground storage systems and post-installation inspection. The practical scope rule is to connect **each special condition to a named run**, not to bury it in a general note. A bidder should know which installed footage carries a different joint or bedding requirement.

### Sanitary sewer

Separate gravity sewer from pressure sewer if both are present. List runs, service branches, wyes, cleanouts, manholes and other scheduled structures. State the existing connection, required opening or core, connector, channel treatment and abandonment work expressly assigned to this package.

Reference the profile for line and grade, the structure details for incoming and outgoing elevations, and the specification for pipe and joint requirements. Do not resolve contradictory inverts by telling the bidder to “field verify” after award. Request a design clarification or issue an identical, clearly identified estimating assumption to every bidder.

The sanitary UFGS distinguishes pressure-line tests, nonpressure leakage tests, deflection testing and connection inspections. Its optional dye and smoke tests check that the sanitary connection has not entered the storm system. These are different acceptance questions. Write the applicable tests individually rather than “all testing included.”

### Water and fire service

Identify domestic, fire and combined services separately. List mains and branches, fittings, valves and boxes, hydrants, meters, backflow assemblies, vaults, restraints, thrust blocks and tracer wire where required by the project.

Assign furnish versus install responsibilities for owner-supplied meters or assemblies. For a vault, name responsibility for its base, structure, piping, enclosure and any electrical or control connections shown. Do not assume the water package includes the electrical work merely because the device serves a water system.

The water UFGS includes flushing, disinfection, hydrostatic and leakage testing, bacteriological testing, backflow testing, special fire-service tests and tracer-wire continuity. Select the applicable requirements from the project documents. Identify who supplies test water, temporary connections, disposal arrangements, testing services and acceptance records.

The companion site-utility scope gaps guide addresses omitted interfaces; here, the objective is to turn the selected assignments into a package bidders can price.

## Assign the trench through its final restored condition

Choose a deliberate excavation boundary. For a utility subcontract on a hard-bid warehouse, a workable basis is to assign utility-specific excavation, bedding, pipe-zone backfill and trench backfill together, while identifying any mass grading or final paving performed by others. This is estimating advice, not a mandatory trade split.

State the surface from which trench depth is priced. A run installed before site fill placement is a different pricing basis from the same run excavated through finished grade. Also name responsibility for layout, existing-utility verification, trench protection, spoil handling, import, compaction, testing coordination and temporary drainage.

Federal OSHA's current [1926.651](https://www.osha.gov/laws-regs/regulations/standardnumber/1926/1926.651) requires locating expected underground installations before excavation and determining their exact locations by safe means as work approaches them. It also addresses water accumulation and competent-person inspections. [1926.652](https://www.osha.gov/laws-regs/regulations/standardnumber/1926/1926.652) governs cave-in protective systems, subject to stated exceptions. These obligations should inform the package's priced work; an exclusion does not waive the applicable employer duty.

In particular, distinguish ordinary trench-water control from an engineered groundwater-lowering system. If the latter remains unresolved, state the base assumption, who will develop the approach, and the pricing mechanism if it becomes required. “Dewatering excluded” is not a complete description of how the work is intended to proceed.

Restoration needs its own limits. Identify sawcutting and removal, temporary patching, final pavement width and section, curb and sidewalk replacement, landscaping repair and surface maintenance between utility completion and final paving. Where final paving is by others, define the accepted backfill elevation and condition they receive.

Competent estimators may disagree about keeping final restoration in the utility package. Decide from the phasing: who controls the open trench, how long the temporary surface remains, and whether a separate paving mobilization is already planned. Do not decide solely from which subcontractor has the cheaper patch rate.

## Make unit prices describe the same commercial treatment

Every requested unit price needs a unit, quantity basis, inclusion list, authorization rule and relationship to the base bid. State whether it is a complete installed rate or an incremental adjustment. Define who verifies quantities and how additions and deductions are treated.

For depth bands, name the measurement datum. “Over eight feet deep” could refer to pipe invert, trench bottom or cover. Those are not interchangeable. Define band endpoints and how a run crossing a boundary is allocated. Keep structure-depth adjustments separate from pipe-depth adjustments.

The water UFGS measures pipe along centerlines without deducting valves or fittings and includes fittings in the pipe payment while providing separate payment for specified appurtenances. The storm UFGS likewise has a centerline pipe rule, separate structure pricing and a structure-depth adjustment. **An installed pipe rate is not necessarily a purchase quantity or a list of separately payable parts.** Copying a rate without its inclusion rule can double-price fittings or omit structure depth.

### Illustrative pricing example

Assume a bid package expressly defines 600 LF of pipe as 400 LF at trench-bottom depths up to eight feet and 200 LF over eight through twelve feet. These quantities, rates and conditions are hypothetical, not market pricing or a prescribed measurement method.

- Shallow complete-installed rate: $110/LF.
- Deep complete-installed rate: $155/LF.
- Four structures: $6,000 each, to the scheduled depths.
- Final paving restoration by a separate package: 300 SY at an illustrative $45/SY.

The utility base is **400 × $110 + 200 × $155 + 4 × $6,000 = $99,000**. With the separate $13,500 restoration carry, the GC's combined position is **$112,500**.

If the deep price is presented as an increment instead, the equivalent deep add is $45/LF: **600 × $110 + 200 × $45 + $24,000 = $99,000**. Applying the full $155 deep rate on top of all shallow footage would incorrectly produce $121,000 before restoration, a $22,000 overstatement. The scope's “complete rate” versus “incremental add” instruction prevents that error before quotes arrive.

Now assume an authorized 30 CY of rock. The storm UFGS's example rock payment includes replacement backfill and cautions that rock pricing is independent of common excavation unless stated otherwise. For this illustration only, suppose the subcontract instead defines a **$180/CY incremental rock adjustment**, including disposal and replacement backfill. The adjustment is $5,400. Adding another illustrative $55/CY for that same replacement backfill would duplicate $1,650.

The decision is not which rate is normal. It is whether every bidder prices the same replacement and whether the adjustment supplements or replaces work already carried. Put that rule beside the rate request.

## Write acceptance responsibilities that cross the physical handoff

A five-foot handoff can divide installation while a test section crosses it. Treat the physical split and the acceptance split as separate decisions.

For example, an illustrative water service ends at a capped site-utility stub. Plumbing later joins the building service. If the project requires testing of the joined section, a pre-handoff test record alone does not answer who tests the final joint. Assign the joint, test limits, temporary equipment, witnesses and final report expressly. Do not make both subcontractors price a complete test setup merely to appear conservative.

A sanitary connection presents a second interaction. The UFGS's optional dye test observes the receiving sanitary system while monitoring downstream storm structures or outfalls. If that test is retained in the project specification, the acceptance activity reaches beyond the new pipe's physical limits. The package should assign observation access and coordination, not just the person introducing dye.

For storm pipe, list CCTV and deflection testing separately if required. The storm UFGS treats them as distinct activities and calls for inspection records. Define the runs, timing, report responsibility and treatment of repair and retest obligations.

Use a small acceptance register containing: system/run, required test, test limits, performer, water or access provider, witness, hold point and deliverable. That register combines the physical boundary schedule with the project testing clauses. It is more useful than a broad “complete and operational” sentence because it identifies what must happen before each handoff can close.

## Reusable site-utilities scope outline

Use the following as an editable bid-package structure. Replace every placeholder and resolve assignments before issuing it; this is not ready-made legal subcontract language.

### General and referenced documents

- Identify the storm, sanitary, domestic-water and fire-service systems included.
- List drawings, specifications, utility-owner attachments and addenda by revision.
- State the installation phase, access assumptions and trench-depth datum.
- Attach the run, connection, boundary and acceptance schedules.

### Inclusions

- Enumerate pipe runs and complete structures by ID and system.
- Assign fittings, branches, valves, restraints, tracer wire and scheduled accessories.
- Assign excavation, protection, bedding, backfill, spoil, import and compaction responsibilities.
- List connection support, shutdown coordination, temporary work and restoration limits.
- List each applicable test, inspection, record and closeout responsibility.

### Exclusions

- Identify only work deliberately excluded and its treatment elsewhere in the estimate.
- Separate utility fees from tap operations and connection support.
- Define treatment of rock, unstable material and groundwater conditions rather than listing bare exclusions.
- State the limits of excluded final paving, existing-system abandonment and dry utilities.

### By others

- Name the responsible package or owner for each excluded obligation.
- Describe its handoff condition and prerequisites.
- Distinguish furnish-only, install-only, connection and acceptance assignments.

### Clarifications and bidder response

- Require acknowledgement of the document register and all issued addenda.
- Require bidders to list deviations against the specific scope item.
- Identify unresolved connection elevations, materials, access and utility approvals.
- Give every bidder the same interim pricing assumption where clarification is pending.

### Alternates

- Define the base condition and the complete changed installation.
- Include related bedding, structures, testing and restoration changes.
- State whether the alternate is an add or deduct and what approvals remain necessary.

### Unit prices

- List size/material/depth bands, structure-depth adjustments, rock and replacement-material rates as applicable.
- Define measurement, included operations, base quantities and authorization.
- State complete versus incremental treatment and addition versus deduction rules.

Before release, walk one storm run, one sanitary connection and one water-service handoff through all seven headings. If the physical endpoint is clear but no one owns its acceptance, the outline is not finished. For later revisions, use the [drawing revision cascade guide](https://piper-ai.com/resources/drawing-revisions-cascade-scope-bids-estimate) to keep changed sources connected to affected scope and pricing decisions.

## Keep source-backed assignments connected to the package

The useful system is one that holds the run, its document basis, the trade assignment and the unresolved decision together. Changing an invert or connection detail should prompt review of the affected depth band, trench treatment and acceptance plan, not just a new sentence in the scope sheet.

[Piper's Scope Generation workflow](https://piper-ai.com/use-cases/scope-generation) organizes requirements from drawings, specifications, addenda and company knowledge into trade-specific scopes with source references. It surfaces unclear responsibilities and potential gaps or overlaps for estimator review, and affected scope can be surfaced when upstream project information changes.

For site utilities, the team's consequential decisions remain the connection basis, trench ownership, restoration limits and acceptance assignments. Piper prepares and checks the scope; the GC decides what the subcontractor is asked to carry.

### Does the site-utility subcontract always stop five feet from the building?

No. Confirm the project documents and define an exact handoff for each system. The water UFGS uses approximately five feet unless otherwise indicated, but that does not assign every project's plumbing or fire-service boundary. Identify the endpoint, coupling, final connection and testing responsibility separately.

### Should utility-company fees and taps be excluded?

Only when the package names who carries them and separates them from contractor support. Identify the fee payer, authorized tap performer, material supplier, excavation provider, shutdown coordinator and restoration owner. An exclusion for the tap operation should not silently exclude the work needed to make that operation possible.

### How should bidders price trench depth?

Issue a common datum, band boundaries and allocation rule with the bid request. State whether each band is a complete installed rate or an incremental adjustment to the base rate. Keep structure-depth pricing separate, and identify whether trench depth is measured from existing, interim or finished grade.

### Can testing be covered by one general inclusion?

List applicable testing separately instead. Pressure, leakage, disinfection, bacteriological, deflection, CCTV and connection-verification activities answer different questions. Use the project's selected requirements and assign limits, performers, witnesses, temporary provisions and reports, especially where a test section crosses the installation handoff.
