# SOLAR 2026 Austin archive: PV and energy-storage scope questions for GCs

For a commercial GC or CM estimator, a PV and energy-storage price is ready to compare only when the proposals describe the same system and assign its interfaces. A battery price alone is not a complete storage-system scope. Record the equipment, designer or vendor's power and energy basis, connection drawings, trade boundaries, and closeout evidence before choosing a carry. If those are unresolved, identify the gap and its cost treatment rather than treating silence as inclusion.

This guide uses the past [SOLAR 2026 Austin edition](https://ases.org/conference/) as a starting point for a practical scope review. The American Solar Energy Society says the conference took place October 19–21, 2026, at the Palmer Events Center with the Texas Solar Energy Society. Its [course descriptions](https://ases.org/conference/events/) advertised PV and NEC, energy-storage systems, and energy-storage and NEC workshops. They are descriptions of proposed course content, not evidence of what an instructor actually taught or a substitute for project design. SOLAR 2027 is scheduled for Golden, Colorado, not Austin.

## Separate the labels before leveling prices

Ask each bidder to identify the PV equipment and work, the storage system and its included components, and any battery-only supply. A proposal titled “solar plus battery” can leave the estimator unable to tell whether another package must furnish conversion equipment, controls, connections, roof work, or testing. Use the design and bidder documents to determine what is actually included; do not assume a particular configuration from the title.

The advertised storage course itself distinguishes storage systems from batteries and lists AC and DC coupling and power and energy ratings as topics. For leveling, request the designer's or vendor's stated power and energy basis, units, and equipment schedule for each offer. A power figure and an energy figure answer different questions; neither alone identifies the full scope. Have the responsible designer evaluate any alternatives and their compatibility. The estimator should not infer sizing or performance from a proposal label.

## An illustrative PV and storage boundary register

The following is a **hypothetical review aid**, not a design or a complete contract scope. Assume a commercial building bid has a roof-mounted PV proposal and a separately priced storage proposal. No design values or drawing numbers are supplied here. Replace every placeholder with the actual revision, proposal reference and written answer. Assign the named reviewer for coordination; that person is not automatically the party performing or paying for the work.

| Boundary and system description | Basis and drawing reference to obtain | Ownership question and evidence request | Accountable reviewer |
| --- | --- | --- | --- |
| PV array and mounting | Designer's equipment schedule and stated PV power basis with units; roof plan and electrical interface drawing and revisions | Who furnishes and installs modules, mounting and associated wiring? Request equipment schedule, exclusions and roof interface details. | PV package estimator |
| Storage system and batteries | Vendor's system and battery description, stated power and energy ratings with units, and one-line and equipment layout revisions | Is the offer batteries only or the described system? Who furnishes enclosures, conversion equipment and associated work? Request itemized equipment and boundary list. | Electrical estimator |
| AC/DC connection and distribution | Designer's one-line and interface drawings identifying proposed AC or DC coupling, connection points and revisions | Who supplies and installs each side of each handoff, including conductors, terminations and distribution modifications? Request marked-up boundaries and bid inclusions. | Electrical lead with design team |
| Controls and operating interface | Controls narrative, interface diagram and revisions identifying equipment and signals | Who furnishes controls, wiring, programming and integration with building or owner systems? Request interface schedule, startup and functional-test responsibilities. | Controls coordinator |
| Roof and structural interfaces | Roof plan, mounting details, structural design and revisions; equipment locations and loads as provided by designer or vendor | Who reviews supports and loading, installs supports and penetrations, and handles roofing and warranty coordination? Request written trade boundaries and design-team disposition. | GC design coordinator |
| Commissioning and turnover | Project commissioning and closeout specifications, system test plan and current drawing revisions | Who performs startup, participates in witnessed tests, corrects and retests, and supplies records, training and manuals? Request a responsibility matrix and deliverables list. | GC commissioning lead |

A single owner name in the register closes the review loop, not the subcontract scope. The reviewer should obtain a written answer from each affected bidder and the design team, then record the proposal revision, outstanding question and funded party. For example, if the PV bidder includes roof mounting but excludes roofing repairs, and the roofer's offer is silent, the boundary remains open. Ask both parties to price or explicitly accept the relevant work against the same detail. Do not count the PV bidder's mounting price as proof that the roof interface is covered.

Power and energy bases that differ between offers also prevent a like-for-like comparison. Record each bidder's stated basis without converting it into an assumed design. Request a common basis or a designer-reviewed alternate, and show the price adjustment and remaining uncertainty on the bid tab. If the connection drawing is missing or the controls interface is undefined, a low number may omit work that another bidder included. Seek a clarification or priced add-back; if the answer cannot arrive before the carry, document the basis and owner of any GC plug and revisit it at buyout.

## Keep the course edition separate from the project code basis

The course descriptions reference the 2026 NEC. Separately, [Austin's building technical codes table](https://www.austintexas.gov/development-services/building-technical-codes) lists the 2026 NEC effective September 1, 2026 and links local amendments. That table is a starting point, not a determination of the edition or provisions applicable to a particular permit. The conference date and course title do not establish that project's code basis.

Ask the responsible design professional and permitting authority to confirm the applicable jurisdiction, permit and application basis, edition, local amendments and any relevant approvals for the actual project. Record the response and the documents or revisions supporting it. If the basis is unresolved, show the open question and its potential effect on the proposals; do not interpret technical code requirements from a workshop title. For the broader document trail, [verify the project code basis](https://piper-ai.com/resources/construction-code-requirements-scope-review).

## Resolve the carry and transfer the decisions

Before the carry, freeze the drawings, specifications, addenda and proposal revisions used for each comparison. For every open register row, choose a written disposition: bidder clarification and revised price, a priced add-back or documented GC plug, an accepted exclusion assigned elsewhere, or a revised solicitation when the boundaries cannot be compared. Keep the submitted price distinct from the evaluated amount and carry, and state the assumptions and confidence behind any plug.

After award, move the resolved responsibilities and required evidence into the appropriate scope exhibits and buyout record. Track unresolved design and permitting questions to a named owner and due date. Use the broader [electrical bid exclusions](https://piper-ai.com/resources/common-electrical-bid-exclusions-gcs-should-review) review for other electrical boundaries that the PV and storage register does not cover.