# Summit Playground Reconstruction: project status and contractor scope review

This project will reconstruct Summit Playground in Macombs Dam Park. The [NYC Parks tracker record](https://data.cityofnewyork.us/resource/4hcv-tc5r.json?trackerid=9972) identifies tracker **9972**, FMS **846 P-104SMPG**, at Summit Avenue and West 161st Street, Bronx. The recorded phase is **procurement**. The dataset row was last updated November 13, 2026 and this research was checked November 15, 2026. The practical decision is whether the issued scope and current procurement documents justify a pursuit, not whether the tracker phase implies a live bid.

## Recorded project status

The tracker reports design 100% complete, procurement 40% complete and construction 0% complete. These percentages describe separate phases. Project funding is **between $1 million and $3 million**, with source listed as City Council; this is funding, not a bid price or award.

The row records design start: June 1, 2024; original projected design completion: June 1, 2025; actual design completion: June 1, 2025; procurement start: August 1, 2026; projected procurement completion: August 1, 2027. Projected and adjusted dates are forecasts, not evidence that a milestone occurred. Any construction start shown in a procurement-phase record is a scheduled field, not confirmation that work began. A past forecast is not a current deadline or proof of completion; where it has elapsed, the current schedule is unknown. The [dataset and data dictionary](https://data.cityofnewyork.us/Recreation/Capital-Project-Tracker/4hcv-tc5r) provide the context for the tracker fields.

## The drinking fountain decision

A [2024 Design Commission certificate](https://www.nyc.gov/assets/designcommission/downloads/pdf/meeting-minutes-certificates-11-18-2024.pdf) records preliminary approval with a request to study an additional drinking fountain. Check the issued drawings for the fountain decision and the limits of any related connections. The preliminary review does not confirm that an additional fountain is in the contract.

## Check the current procurement documents

Use the tracker to identify the project, then obtain the controlling solicitation, drawings, specifications and addenda from the agency. Verify the current status, eligibility and deadlines before assigning bid resources. The tracker does not itself establish an open solicitation or a contractor award. The [NYC public bid review](https://piper-ai.com/resources/nyc-public-construction-bid-review-checklist) helps record those decisions, and the project directory places this guide among other named projects.

## Review the playground package

With the actual documents in hand, Piper's [scope-generation workflow](https://piper-ai.com/use-cases/scope-generation) supports a document-based review. See also the [construction scope review guide](https://piper-ai.com/resources/construction-scope-generation-guide). This is independent Piper analysis, not an NYC Parks notice or affiliation. Research checked November 15, 2026.