---
title: 'How to write a tile scope of work subs will price the same way'
url: 'https://piper-ai.com/resources/tile-scope-of-work'
description: 'Write a tile bid scope around complete assemblies, substrate handoffs and a defined allowance basis, with reusable language for membranes, prep and trim.'
contentTypes: [guide]
publishedAt: '2026-11-29T11:39:26.848Z'
author: 'Ido Gedanken, CEO'
readingTime: 11
---

# How to write a tile scope of work subs will price the same way

1. Define each tile assembly by location, substrate, installation method and finished elevation.
2. Assign membrane and backer work separately, including the inspection that releases tile installation.
3. Keep installed area, purchasing waste and owner maintenance stock separate in tile allowances.
4. Price unknown substrate correction against a defined baseline, not an unlimited floor-prep obligation.

For a GC estimator issuing a commercial restroom or tenant-improvement tile package at bid CDs, the scope should define the **complete assembly and its handoffs**, not just the tile finish tags. Give every bidder the same locations, installation basis, substrate condition, membrane responsibility, trim details and material allowance rules.

The position here is simple: do not ask the tile subcontractor to price an undefined inherited surface. Either define the correction work in the base bid or establish a common correction allowance and adjustment mechanism. Otherwise, a clean square-foot price can conceal several different construction plans.

This guide addresses conventional ceramic and porcelain floor and wall tile. It is not an installation specification or a design for shower waterproofing. Gauged panels, exterior tile, stone assemblies and chemical-resistant applications need their own project-specific requirements. The design team establishes the technical assembly; the GC makes its procurement boundaries explicit.

## Start with an assembly schedule, not a finish schedule

A finish schedule identifies the visible selection. Your bid scope also needs to identify what supports it and what happens at its edges.

For each distinct installation, record:

- Room or area and floor, wall, base or other surface.
- Tile tag, size, thickness, finish and selection status.
- Extent, including wall height, returns, niches, curbs and concealed terminations where shown.
- Substrate and specified installation method.
- Mortar or adhesive, grout type and joint requirements.
- Backer, waterproofing and crack-isolation treatment, where required.
- Pattern, orientation, borders and alignment requirements.
- Finished elevation, drain interfaces, thresholds and adjoining finishes.
- Source drawing, detail, specification paragraph and applicable addendum.

The federal [UFGS 09 30 10 guide specification](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2009%2030%2010.pdf) separates substrates, waterproof membranes, crack-isolation membranes, setting materials and transition strips. Its designer notes also call for drawings that establish the work's extent and project-specific installation methods. These are useful categories, not requirements automatically imposed on a private project.

The distinction changes the bid instruction. “Provide PT-1 in Rooms 101 through 106” is not equivalent to “Provide the scheduled PT-1 floor assembly, including the specified membrane, setting materials, grout, perimeter treatment and transition details in Rooms 101 through 106.” The second still needs named sources, but it tells bidders which construction system they must cover.

Use the [construction scope generation guide](https://piper-ai.com/resources/construction-scope-generation-guide) for the overall package-building process. The tile-specific work is the assembly schedule and the ownership decisions below.

## Reference the documents that determine the assembly

Issue a dated document register with the scope. Include the actual project sections, not just a blanket reference to Division 09:

- Tiling, often Section 09 30 13, or the project's alternative numbering.
- Gypsum board and cementitious backer provisions.
- Waterproofing and joint sealant sections affecting tile work.
- Concrete or floor-underlayment requirements affecting receiving surfaces.
- Division 01 requirements for submittals, mockups, temporary conditions, protection and closeout.
- Architectural finish plans, interior elevations, wall types, enlarged wet-area details and transition details.
- Plumbing drain and receptor details relevant to the tile assembly.
- Issued addenda and incorporated prebid clarifications.

Do not silently replace the contract's referenced standards with a different edition. The UFGS file retrieved for this guide identifies an August 2020 section with references coordinated to October 2026, yet its reference list still names a 2017 TCNA Handbook. That is a reason to check the project's references, not permission to update them yourself. Resolve a material discrepancy through the design team's clarification process.

An official [municipal ceramic-tiling specification](https://wbmlp.org/bids/Specifications-Phase-I/Technical%20Specifications/093013%20-%20CERAMIC%20TILING_SP.pdf) demonstrates why drawings remain essential: it sends tile, base and transition selections to the interior drawing series while separately specifying backer units, waterproofing and installation methods. A subcontractor reading only the tile section would not have the full selection basis.

For the bid package, use a requirement-to-location cross-check: every assembly must have both a source for its technical requirements and a source for its extent. A general membrane clause without a coverage drawing is still an open pricing question.

## Assign backer and waterproofing by operation and release point

“Waterproofing by others” is too coarse for a wet-area package. Separate the operations before deciding who owns them.

The [NYCHA sample ceramic-tiling specification](https://designguidelines.nycha.info/wp-content/uploads/2024/05/09-30-13-Ceramic-Tiling.pdf) illustrates this distinction. It assigns liquid waterproofing for thinset floors within the tile section, while requiring verification that sheet waterproofing for thickset systems has been installed and leakage-tested under a separate waterproofing section. It also requires approval of the liquid membrane before thinset floor tile proceeds. This is a sample specification with older references, not a general rule for other owners.

Read that alongside the UFGS substrate provisions, which offer an installation reference to the gypsum-board section. The combined lesson is a procurement decision: neither “tile owns waterproofing” nor “drywall owns backer” can safely be inferred from the finish tag or section title.

Use a boundary schedule like this, completed for each assembly:

| Operation | Bid scope must name | Evidence needed before the next operation |
| --- | --- | --- |
| Backer board | Furnisher, installer, fasteners, joint treatment and receiving framing condition | Specified board installed and deficiencies reported |
| Shower receptor or sloped base | Builder of the slope, liner or bonded membrane, and drain connection | Required inspection or testing completed |
| Wall and floor membrane | Coverage, upturns, seams, corners and penetration treatment | Required cure, test and acceptance recorded |
| Tile installation | Setting system, layout, grout and trim | Substrate and membrane released for covering |
| Finished protection | Initial protection, maintenance and removal responsibility | Handoff condition recorded |

The non-obvious consequence is that **membrane ownership and permission to cover the membrane are separate obligations**. Even when the tile subcontractor excludes its installation, the tile sequence may still require that subcontractor to verify its release before proceeding.

Include three practical instructions in the scope:

1. Identify who requests and who performs each required test or inspection.
2. Identify who documents acceptance and communicates permission to cover.
3. Identify who repairs damage occurring between membrane acceptance and tile installation.

Do not insert a generic flood-test duration. Use the applicable contract, adopted code and approved system instructions. A shower-pan handoff must also identify the drain interface; “pan by plumbing” alone does not allocate the adjacent sloped base, wall membrane or tile work.

## Define floor preparation without transferring an unknowable condition

Separate preparation necessary to install the specified system from correction of an undefined receiving surface. Then decide how the latter is priced.

The UFGS preparation note explicitly calls for coordination with concrete and masonry specifications, including concrete surface finish and removal of curing-compound or wax conflicts. Its execution provisions also require inspection of the receiving surface. Those two requirements work together: inspecting a slab does not establish who pays to correct it.

For a new commercial building with coordinated substrate requirements, a defensible scope can assign the substrate-producing trade to deliver the specified condition, with tile responsible for inspection and its defined installation preparation. For an existing TI slab that cannot be surveyed before bidding, competent estimators may instead carry correction in the tile package. The deciding factors should be access to measurements, the extent of demolition, and who can practically execute the repair.

Specify one of these pricing bases:

- **Measured correction in base:** identify areas, treatment and depth range.
- **Defined allowance:** identify the included amount and how actual authorized work adjusts it.
- **Unit-price correction:** identify the baseline condition, measurement procedure, thickness bands and included materials and labor.

“Include minor prep” is not a measurable baseline. Define what it covers, such as the specified cleaning and a stated patching quantity, without pretending it covers every out-of-tolerance condition.

**Illustrative correction example:** after demolition, a joint survey identifies 180 square feet requiring an approved correction treatment within a defined thickness band. At an illustrative all-in unit rate of $4.50 per square foot, the authorized correction is 180 × $4.50 = **$810**. If the base bid already includes a $500 allowance for that same work, the additional amount is $310, not $810. The scope must say that the allowance is credited against authorized correction; otherwise the estimate can carry both.

This is not a production benchmark. It demonstrates why the baseline, approval and allowance reconciliation belong in the bid instruction rather than being negotiated after the slab is exposed.

## Treat thresholds as an elevation decision, not an accessory count

A threshold can be fully counted and still be wrong for the assembly.

The UFGS designer notes establish a top-of-tile datum so other trades can determine the required subfloor elevation. The [ADA Accessibility Standards](https://www.access-board.gov/ada/) separately regulate changes in level. Where such changes are permitted, Section 303 allows a vertical change up to 1/4 inch, requires beveling between 1/4 and 1/2 inch, and requires ramp treatment above 1/2 inch. Door thresholds have additional provisions under Section 404.2.5, including exceptions for certain existing or altered thresholds.

**Illustrative coordination check:** a tile assembly builds up 3/4 inch above a common substrate, while the adjacent resilient finish builds up 1/8 inch. The difference is 3/4 minus 1/8 = **5/8 inch**. Where Section 303 applies, that exceeds the 1/2-inch change addressed by a simple beveled transition. Merely assigning a metal strip to the tile bidder does not resolve the condition.

The GC should obtain a coordinated detail for a recess, adjacent build-up or other compliant treatment. The estimator should not redesign it in the scope sheet. Carry the resulting work in the named package and ensure the adjacent flooring bid uses the same elevation basis.

For each transition, request the profile, length, finish, fixing or bedding responsibility and finished levels on both sides. Include door clearance and drain elevation questions in the coordination review rather than leaving them to the installer.

## Separate installed area, waste and maintenance stock in allowances

A tile allowance needs a purchasing basis as well as a dollar rate.

State whether the allowance covers tile material only or an installed assembly. For material-only allowances, define whether freight, tax, purchasing waste, carton rounding, trim and owner maintenance stock are included. Keep installation labor, mortar, grout and membranes identifiable outside that allowance unless the package explicitly includes them.

The UFGS extra-material provision uses an editable percentage of each tile type. The NYCHA sample uses a different basis: at least one box for each 25 boxes or fraction thereof, along with separately stated base and sealer quantities. Neither is a universal spare-stock percentage. Their interaction shows why a single “waste and attic stock” factor is not an adequate scope instruction.

**Illustrative allowance example:** assume 1,200 square feet of net installed floor tile, an agreed 10% purchasing-waste assumption for the documented layout, and 24 square feet of separately required maintenance stock. Assume no carton rounding for this example.

- Installation purchasing quantity: 1,200 × 1.10 = 1,320 square feet.
- Total tile purchased: 1,320 + 24 = 1,344 square feet.
- At an illustrative material allowance of $6 per purchased square foot: 1,344 × $6 = **$8,064**.
- Applying the same rate only to net installed area gives $7,200, understating this defined material basis by **$864**.

The 10% is an example assumption, not recommended waste for every pattern. Require bidders to include the documented layout in their base price and disclose purchasing assumptions for allowance reconciliation. Do not pay installation labor on delivered maintenance stock unless there is a separately justified handling charge.

If a tile selection remains open, define its size, thickness and pattern envelope. A material allowance should not imply that any later selection has the same labor or substrate requirements.

## Use this reusable tile scope outline

Complete the fields below, attach the assembly and boundary schedules, and delete inapplicable items. This is a drafting outline, not a substitute for the project's technical specification.

### General and document basis

“Provide the tile work identified in assembly schedule [reference] using document register [date/revision], including listed addenda. Base pricing on the specified installation systems, location limits, layout and finish elevations. Identify proposed deviations separately; do not substitute them into the base price.”

State work areas, access dates, phased releases, mobilizations, storage arrangements and applicable temporary-condition responsibilities. Include required product data, samples, layout drawings and mockups with their approval basis.

### Inclusions

List tile and base by tag and location. Include the applicable setting materials, grout type, cuts, drilling, returns, trims, edge profiles and thresholds. State whether borders, niches, benches, curbs and other detailed surfaces are included.

Assign backer supply, installation and joint treatment. Assign waterproofing, crack isolation, seam and penetration treatment by assembly. Distinguish specified movement-joint work from ordinary grout work and identify who supplies and installs the required sealant or profile.

Define substrate examination, included preparation and authorized correction. Include required cleaning, sealer where specified, initial protection, maintenance stock, closeout information and warranty responsibilities.

### Exclusions and work by others

For each exclusion, name the receiving package and its handoff condition. Use separate entries for structural substrate correction, framing, backer, membrane, drain installation, final cleaning or ongoing protection if any are outside tile.

An exclusion accepted in the tile package should appear as an inclusion somewhere else. Record unresolved assignments in the scope gap register; the separate tile scope gaps guide addresses the omissions that this process is intended to catch.

### Clarifications

Record unresolved selection limits, substrate survey access, joint-layout questions, membrane extents and transition elevations. Give every bidder the same issued answer. Distinguish an estimator's bid assumption from an approved design clarification.

### Alternates and unit prices

Describe each alternate as a complete change to the base assembly. Identify changes to tile, setting system, grout, prep, trim and labor rather than requesting a material substitution price alone.

For unit prices, state the unit, authorized measurement basis, depth or condition limits, included materials and labor, minimum charges, and whether the rate is additive or deductive. Require correction allowances to be reconciled against the same authorized work.

### Bid response and buyout reconciliation

Require bidders to identify exclusions, deviations, allowance basis, membrane and backer coverage, and acknowledged document revisions. Before award, reconcile those responses into the scope rather than attaching conflicting documents without resolving them. Keep the bid scope sheet and subcontract exhibit aligned so the priced basis survives buyout.

## Keep the assembly decisions connected to their sources

The useful deliverable is not a longer tile scope. It is a scope in which each assembly has a location, each boundary has an owner, and each unresolved condition has a stated pricing treatment.

Piper's [Scope Generation workflow](https://piper-ai.com/use-cases/scope-generation) brings drawings, specifications, addenda and company requirements into trade-specific scopes, links items to their sources and surfaces unclear responsibilities for estimator review. Existing company scope structures can inform the draft, and affected scope can be surfaced when upstream information changes.

For tile, that supports maintaining the connection between a revised shower detail, membrane coverage, backer assignment and issued bid scope. The estimator still decides the trade boundaries and pricing treatment. The software does not approve the assembly or choose the subcontract commitment.

### What should a tile scope of work include?

Include the complete assembly by location, not just tile tags and quantities. Define substrates, backer, membranes, setting materials, grout, pattern, trim, transitions, preparation, protection and maintenance stock. Attach the document basis and identify exclusions, work by others, clarifications, alternates and unit-price rules.

### Should waterproofing and backer board be included in the tile subcontract?

Include them only where the project and procurement plan assign them to tile. Either assignment can work if the adjacent package carries the corresponding work and the scope defines inspection, testing and release before covering. Do not infer ownership from a finish tag or specification section title.

### How should unknown floor preparation be priced?

Use a defined baseline with measured correction, a stated allowance or authorized unit-price work. Specify the treatment, thickness limits, measurement and approval procedure. An unlimited preparation clause does not give bidders a common quantity basis when they cannot inspect the receiving substrate before bidding.

### Does a tile material allowance include waste and attic stock?

Only if the scope explicitly says so and defines the calculation. Keep net installed area, layout-related purchasing waste, carton rounding and owner maintenance stock separate. State whether freight, tax and trim are included, and whether installation costs remain outside the material allowance.
