# I-10 White Oak Bayou kept the same girder length and changed six bid quantities

TxDOT’s I-10 White Oak Bayou bid package in Houston still showed **246,174.560 linear feet across six prestressed girder items** after Addendum 3. The six item quantities all changed. On two bridge sheets, TxDOT corrected five bid-code headings while the girder descriptions and the lengths beneath those headings stayed the same. If your takeoff and supplier quote already agree on the pieces, reconcile that code change in the estimate before you carry a new price. [Addendum 2 plan revisions, pp. 53–54](https://ftp.txdot.gov/plans/State-Let-Construction/2024/08%20August/08%20Revisions/Harris%200271-07-326R2.pdf#page=53), [Addendum 3 plan revisions, pp. 25–27](https://ftp.txdot.gov/plans/State-Let-Construction/2024/08%20August/08%20Revisions/Harris%200271-07-326R3.pdf#page=25)

## Follow the codes on the two bridge sheets

On **sheet 2227**, the I-45 HOV to I-10 westbound direct connector extension, the TX28 and TX40 columns both kept their lengths. On **sheet 2249**, the I-10 eastbound to I-45 northbound direct connector, the TX34, TX46 and TX54 columns kept theirs. Comparing the July 29 and July 30 issues gives these five transfers. [July 29 revision, sheets 2227 and 2249](https://ftp.txdot.gov/plans/State-Let-Construction/2024/08%20August/08%20Revisions/Harris%200271-07-326R2.pdf#page=53), [July 30 revision, sheets 2227 and 2249](https://ftp.txdot.gov/plans/State-Let-Construction/2024/08%20August/08%20Revisions/Harris%200271-07-326R3.pdf#page=26)

| Sheet | Girder series | Length carried | Prior sheet code | Corrected code |
| --- | --- | --- | --- | --- |
| 2227 | TX28 | 240.660 LF | 425-6038 | 425-6035 |
| 2227 | TX40 | 390.970 LF | 425-6039 | 425-6037 |
| 2249 | TX34 | 3,444.600 LF | 425-6038 | 425-6036 |
| 2249 | TX46 | 1,364.800 LF | 425-6039 | 425-6038 |
| 2249 | TX54 | 1,731.200 LF | 425-6040 | 425-6039 |

The five corrected columns cover **7,172.230 linear feet**. One reason the change is easy to miss is that some bid codes gained and lost length. Item 425-6039, for example, lost 390.970 and 1,364.800 feet and picked up 1,731.200 feet. Its project quantity moved by only 24.570 feet. The TX34 item, 425-6036, moved from 2,062.590 to 5,507.190 feet. Both changes reconcile to TxDOT’s replacement bid insert and the project quantity sheet, 40B. [Prior bid insert, p. 10](https://ftp.txdot.gov/plans/State-Let-Construction/2024/08%20August/08%20Proposal%20Addenda/Harris%200271-07-326%20AD2.PDF#page=10), [Replacement bid insert, p. 9](https://ftp.txdot.gov/plans/State-Let-Construction/2024/08%20August/08%20Proposal%20Addenda/Harris%200271-07-326%20AD3.PDF#page=9), [Revised sheet 40B](https://ftp.txdot.gov/plans/State-Let-Construction/2024/08%20August/08%20Revisions/Harris%200271-07-326R3.pdf#page=25)

## Check the price at the item level

At the August 1, 2024 letting for CSJ **0271-07-326**, TxDOT tabulated **$407,810,028.26 from Webber, LLC** and **$459,501,382.24 from Williams Brothers Construction Co., Inc.**, a difference of **$51,691,353.98 for the whole contract**. The public tab shows why the estimating key matters. Webber’s submitted unit prices for TX34 and TX46 were $211.190 and $201.260 per foot, respectively. Williams Brothers’ were $135.000 and $150.000. The tab reports submitted prices and final bid quantities. It gives no breakdown of the causes of the overall spread. [TxDOT project bid tab](https://www.dot.state.tx.us/insdtdot/orgchart/cmd/cserve/bidtab/08013001.htm)

## Reconcile the bid form and the supplier quote

Start with the changed bridge columns. Keep the bridge, girder series, length and corrected bid code together on each estimate row. Check the resulting item totals against the final bid insert, then match the supplier quote to the series and pieces it covers. If the quote used the old codes, ask the supplier to confirm which pieces, delivery and erection it priced before rolling the quote into the corrected items. Resolve any remaining scope or price question at that line while you can still trace it back to the sheet. The [construction addenda management guide](https://piper-ai.com/resources/construction-addenda-management-for-gc-estimators) covers the wider process for review and acknowledgment.