# What’s missing from these plans? Find unowned scope before the question deadline

Most scope that looks missing from a bid set is written somewhere in it and shown or owned nowhere else. Find those requirements before the question deadline, ask about them so the answer comes back as an addendum, and price what stays open.

## Look for requirements nobody shows, not blank space on a sheet

The contract documents are complementary: a requirement in the specs binds as if it were drawn, and how the specs are organized does not decide which trade does the work. So the expensive “missing” item is rarely absent. It is stated in one place and shown, powered or owned nowhere else.

The useful question before the question deadline is: what will I be held to that this set does not show clearly, which of those must I ask about, and which do I have to price as an assumption? On a sealed public bid you cannot qualify the number afterwards.

## Worked example: ten electrified doors that no drawing powers

Hypothetical: a public renovation of a four-story city-owned library in New York City, lump-sum sealed bid. Bid due in 12 days, questions due in 5.

| Where | What it says | If nobody connects it |
| --- | --- | --- |
| A-601 and spec 08 71 00 | The door schedule says “HW set per spec”. The spec says hardware is furnished “in sets as scheduled on the drawings”. | No hardware set schedule exists anywhere. Each document points at the other, and each looks complete on its own. |
| Spec 08 71 00, Part 2 | Electric strikes and request-to-exit at 6 exterior doors, and magnetic hold-opens released by fire alarm at 4 smoke doors. | A spec-only system: nothing for it appears on any other discipline’s drawings. |
| E-201 and FA-101 | No power, pathway, back boxes or fire alarm relays at any of the 10 doors. | Electrical prices what is drawn. The fire alarm sub prices what is drawn. |
| Spec 28 13 00 | Card readers and the access control panel are furnished and installed by the owner’s security vendor. | Power supplies, conduit, door position switches and wiring from door to panel belong to nobody. |
| Sub quotes | Hardware excludes “power supplies and wiring by electrical”. Electrical excludes “low voltage and access control by others”. | Each quote is reasonable. Together they leave 10 openings with nobody carrying the interface, and the bid form cannot be qualified to fix it. |

Ask for the hardware schedule by addendum, ask who owns the door interfaces, and write the answer you expect into each sub’s scope as an inclusion so silence shows up in leveling.

> **Bring a bid set you are pricing now.** In the demo we run your drawings, specs and addenda in Piper together and look for requirements that appear in one document and are shown or owned nowhere else, with the source pages for each. [Book a project demo](https://piper-ai.com/demo)

## Finding what the set does not show

Work through this before the question deadline, not before the bid date.

1. **Confirm you hold the complete official set.** From the issuing source, with every addendum to date.
2. **Note the question deadline and the channel.** On New York State work, also note the designated contact. Questions go only to them, in writing.
3. **Search for circular references.** “See spec”, “as scheduled”, “refer to” where the target does not exist.
4. **Find each spec system on the other drawings.** Power, pathway, support and connection for every device a spec section adds.
5. **Read Division 01 before calling anything missing.** Summary of work, owner-furnished items, allowances and unit prices. On NYC DDC work that is the “Addendum to the General Conditions”.
6. **Check schedules against plans, both directions.** Door, finish, equipment and fixture schedules against the tags on plan.
7. **Check details against wall types and ratings.** A rated wall implies rated doors, firestopping and head-of-wall work somewhere.
8. **List every “by others”, NIC and “by owner”.** And ask who the other is.
9. **Write each question so only an addendum can answer it.** “Please confirm by addendum.” An emailed answer or a pre-bid remark is not binding.
10. **Price what is still open at the deadline.** Write it into sub scopes as an inclusion. Do not qualify the bid form.
11. **Keep each open item with its source pages.** So the next addendum can be checked against it.

## Bidding rules that shape the answer

- Under the standard AIA Instructions to Bidders, bidders must report errors, inconsistencies or ambiguities, with written clarification requests due at least seven days before bid receipt by default. Interpretations made any other way than by addendum are not binding. Source: [AIA A701-2018, §3.2](https://web.archive.org/web/20200331135737/http://content.aia.org/sites/default/files/2018-10/A701_2018.sample.pdf).
- On federal sealed bids, a bid that imposes conditions modifying the invitation’s requirements is rejected, so open questions have to be answered or priced, not qualified. Source: [FAR 14.404-2](https://www.acquisition.gov/far/14.404-2).
- On New York State procurements, bidders may contact only designated staff during the restricted period, and written questions go through the method the solicitation states. A second violation within four years can bar a firm for four years. Source: [NY State Finance Law §139-j](https://web.archive.org/web/2025/https://www.nysenate.gov/legislation/laws/STF/139-J).
- NYC DDC puts all Division 01 general requirements in a document called the Addendum to the General Conditions, handles unknown quantities through a Unit Price Schedule, and does not permit bid alternates on publicly bid projects. Source: [NYC DDC Design Consultant Guide 2025](https://www.nyc.gov/assets/ddc/downloads/publications/guides-manuals/Design_Consultant_Guide_2025.pdf).

## Related guides

- [Estimating design intent from incomplete drawings](https://piper-ai.com/resources/design-intent-estimating-incomplete-drawings): when the set is complete but ambiguous.
- [Reading between the drawings](https://piper-ai.com/resources/reading-between-the-drawings): trade interfaces and implied design intent.
- [Pre-bid RFIs and scope review](https://piper-ai.com/resources/construction-rfi-prebid-scope-review): turning a question into a pricing decision.
- [MEP coordination in preconstruction scope](https://piper-ai.com/resources/mep-coordination-preconstruction-scope): supports, controls and power that fall between trades.
- [Spot scope gaps before you carry](https://piper-ai.com/resources/spot-scope-gaps-before-you-carry): the review sequence for work nobody owns.
- [NYC public construction bid review checklist](https://piper-ai.com/resources/nyc-public-construction-bid-review-checklist): agency-specific guides for New York public work.

## Where Piper fits

- Piper reads the full bid package, drawings, specs and addenda, and answers questions about it with the source page.
- Scope generation pulls requirements from every document, including obligations outside the trade’s own section, and flags unclear ownership, gaps and coordination items for your estimators.
- Your company’s standard questions can run on every set and flag what the documents do not answer.
- Bid leveling and final review read the same project, so an open item stays visible until bid day.
- Piper does not decide who owns a boundary or submit questions for you. Your team does.