88 Black Falcon M683-C2: separate underpier repairs and alternates
Review the gallery access basis and keep the base and three alternates separate until the M683-C2 issue set defines their repair areas.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 2 min
- Published
On this page
For a GC estimator reviewing M683-C2, the first decision is whether the repair carry and the access carry describe the same underdeck work. Keep the base and each alternate in separate rows, and leave their physical boundaries unassigned until the issued documents define them. A single marine repair allowance cannot explain which work or access changes when an alternate is selected.
What the notice establishes
Massport's M683-C2 notice advertised marine structural concrete repairs to beams and deck beneath the pier deck at 88 Black Falcon. It described a prebid visit through the gallery beneath the concrete deck. Attendees were to bring a harness and confined-space entry documentation; a tripod and ladder were offered for that meeting. That meeting arrangement does not establish construction access equipment or classify the entire work area.
The historical notice gave owner estimates of $1,255,000 for the base and $800,000, $595,000 and $560,000 for add alternates A1, A2 and A3. These are dated estimates, not bids or current price benchmarks. The notice does not map the alternates to repair locations. Its September 30, 2026 deadline differs from the October 7 date in the public listing; the listing alone does not explain the revision.
Build the access and alternate register
Use this estimator-created register as a starting point, not an owner-issued method:
| Carry | Evidence established | Decision still needed |
|---|---|---|
| Base | Beam and deck repair under pier is the advertised work | Mark repair limits and quantities on the issued drawings |
| A1 / A2 / A3 | Each has a separate owner estimate | Identify each alternate's locations, quantities, inclusions and dependencies |
| Access | Prebid route entered the gallery beneath the deck | Confirm construction routes, access restrictions, equipment responsibility and any access changes by area |
For every repair location, record the drawing and revision, elevation or gallery reference, work description, quantity basis, trade carry and access assumption. Add a separate field for the alternate designation rather than assigning it from the owner estimate. Ask bidders to identify whether their access and mobilization are included in each alternate or shared with the base. Compare those qualifications before adding any shared cost back to a bid.
Close the unanswered package questions
Obtain the issued plans, specifications and addenda to identify repair boundaries, access requirements and the controlling dates. The prebid equipment offer should be recorded as meeting-specific, not as an owner-furnished construction allowance. Keep the C2 notice separate from other Black Falcon packages until documents establish an interface. Use the Boston public construction source guide to verify the issued project scope and trace scope changes to the controlling revision before finalizing the register.
Related reading
Construction addenda management for GC estimators
Addenda are official bid-document revisions. Log them, distribute them, retakeoff the deltas, and require subcontractor acknowledgments so your estimate and every bid reflect the final scope.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.