Boston permanent drainage: reconcile infiltration, UIC and maintenance scope

Level Boston permanent drainage bids using the engineer’s infiltration basis, UIC decision, maintenance responsibilities and as-built records.

Guide1 min read

Published

Tower crane against an overcast sky

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Civil scope and evidence checklist
  2. Resolve construction interfaces before leveling

For a Boston site subject to BWSC’s permanent stormwater requirements, compare civil bids against the engineer’s approved infiltration design and its evidence requirements. Do not use a rainfall factor alone as a construction design or assume every renovation needs the same site-plan approval.

BWSC’s storm drain requirements describe a criterion of one inch of rainfall times impervious area for projects below 100,000 square feet of floor area, and 1.25 inches at or above 100,000 square feet. Floor area selects the criterion; the impervious area is the surface used in the calculation. The engineer must determine applicability and prepare the project-specific analysis.

Civil scope and evidence checklist

ItemProject input to obtainBid and handover question
Design basisFloor area, impervious catchment and drainage analysisAre all contributing surfaces and connections included?
SubsurfaceSoil infiltration testing and engineer’s assumptionsWho pays for testing and changes if conditions differ?
Infiltration systemApproved location, excavation, media and protectionWho installs and protects it during construction?
UICDetermine whether the new system requires an approval numberWho obtains and supplies the number to BWSC?
OperationsO&M plan and assigned maintenance responsibilityAre access and turnover documents included?
As-builtGreen infrastructure documentation and surveyWhich contractor collects records before concealment?

BWSC describes testing, drainage analysis, O&M and as-built green-infrastructure documentation, and requires UIC approval numbers for applicable new infiltration systems. It also states that GCOD infiltration systems may not use underdrains or stormwater capture and reuse. BWSC requirements

Resolve construction interfaces before leveling

For an illustrative underground chamber, compare excavation limits, bedding, connection elevations, protection from construction sediment and survey responsibilities across civil and plumbing bids. A low installation price can leave testing or reinstatement unassigned. Reconcile plumbing and site utilities, and keep permanent drainage separate from temporary SWPPP and dewatering decisions in the Boston obligation guide.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.