Circuit Drive: separate speed tables from future drainage reconstruction
Distinguish Circuit Drive speed tables and pipe investigation from future drainage reconstruction and bicycle infrastructure.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 2 min
- Published
On this page
The November 2025 Phase 1 concept combines speed tables and crosswalks with pipe investigation and cleanout. Keep major future drainage reconstruction and bicycle separation in separate potential phases until the issued package says otherwise.
The following register is an estimator's interpretation of the cited public records, not a contract scope or a substitute for the current procurement documents.
Separate speed tables, crossings and pipe investigation
| Work or location | Public record | Estimator's review |
|---|---|---|
| Speed tables | Traffic-calming devices proposed through the bike lane | Verify count, locations, sections and pavement restoration. |
| Crosswalks | Unraised in Phase 1 to preserve existing drainage patterns | Coordinate ramps, markings and signs with the issued plans. |
| Pipe work | Investigation and cleanout in Phase 1 | Define inspection, disposal and repair limits. |
| Future work | Longer-range stormwater and dedicated bicycle infrastructure | Do not silently price curb relocation as Phase 1. |
Keep dated concept counts out of final takeoffs
The design team described ten proposed tables and said it would explore adding more. Ten is a dated concept count, not a final quantity. The notes describe a 22-foot speed table and a six-foot speed hump as different treatments; use the actual design detail for takeoff rather than substituting one for the other.
Crosswalks were not proposed to be raised in Phase 1 because the team intended to preserve drainage patterns. The same notes said flashing beacons were not proposed under the budget at that time. Neither statement settles the final issue set.
The primary records are Franklin Park: Circuit Drive Traffic and Drainage official City project page Meeting 3 Notes (November 13, 2025).
Reconcile crossing levels and the end of pipe-work scope
Build separate pavement, traffic-control, accessibility and drainage rows. For each crossing, ask how the surface treatment meets the gutter and existing flow path, and whether pipe work ends with cleaning or includes repairs. Obtain the latest approved plans, quantities, maintenance-of-traffic requirements and addenda.
Before relying on a public presentation, trace the official Boston project record and check the controlling issued revision.
Related reading
Construction addenda management for GC estimators
Addenda are official bid-document revisions. Log them, distribute them, retakeoff the deltas, and require subcontractor acknowledgments so your estimate and every bid reflect the final scope.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow