Construction payment applications: review the evidence and timing behind each payment

Connect construction payment applications to the schedule of values, progress evidence and contract requirements, with clear ownership of missing support.

Guide2 min read

Published

Construction scaffolding interior

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Assemble the current request
  2. Example: one payment cycle
  3. Track review to actual cash

A construction payment application is a request supported by a record of work completed and, where the agreement allows, eligible stored materials. Before bidding, map the application dates, evidence, review and payment milestones to the cash forecast. The contract and applicable law determine the actual forms, entitlements and timing.

AIA's explanation of G702 and G703 describes using the schedule of values to report completed work, stored materials, retainage and changes for review and payment. Those forms are examples, not mandatory forms on every job. Start with the executed agreement and approved schedule of values, then forecast retainage and cash flow on that documented basis.

Assemble the current request

At each cutoff, reconcile the approved schedule of values and changes to field progress and prior applications. Collect the contract-required evidence, which may include progress records, invoices, stored-material documentation or other forms. Check the conditions for off-site or on-site stored material before including it; avoid billing the same material again when installed. Track disputed or pending changes separately until the contract permits their inclusion.

CheckpointEvidence to reconcileFollow-up
ProgressCurrent and previously billed work by schedule lineResolve unsupported percentages with project team
Stored materialEligibility and inventory records required by agreementRemove from stored column as installed
RetainageApplicable basis and rate under agreementForecast withheld and expected release separately
Review and receiptSubmitted amount, certified amount and actual receiptLog differences and payment date

Example: one payment cycle

Suppose an illustrative $100,000 schedule line is 40% complete to date, nothing has been billed previously, and the agreement permits 5% retainage on this completed work. The gross amount is $40,000; retainage is $2,000 and the current net request is $38,000, before other adjustments. If $10,000 was previously paid against that same line, calculate the current request using the form's cumulative fields and prior payments rather than adding $38,000 again. Changes, stored materials and differing retainage rules would alter the result.

Track review to actual cash

Send the application by the contractual cutoff, record the reviewer and follow up on questions. Log the amount requested, certified, disputed, paid and received, with dates and reasons for differences. Certification is not cash receipt. Reconcile subcontract applications and forecast funding gaps, taking care that payment obligations and rights depend on each agreement and applicable law.

For cost-plus construction contracts, the payment package may also need cost-of-work records under the agreement. Agree on the necessary backup and review time early; an unsupported reimbursement assumption can affect both the bid and the monthly cash plan.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow