Construction recovery schedules: price the resources behind the revised date

Compare schedule-recovery options through access, logic, crew and productivity assumptions before pricing overtime, added shifts or resequenced work.

Guide4 min read

Published

Tower crane above steel reinforcement

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Find the time that can actually be recovered
  2. Compare two ways to recover an equipment handoff
  3. Build a comparable incremental cost bridge
  4. Separate authority, entitlement and field release
  5. Use a recovery decision register

Before a GC commits to a recovery date, test whether the proposed resources can actually shorten the current controlling sequence, then price the extra work against the existing plan. A recovery schedule is a proposed sequence and resource plan for regaining time after the current forecast slips. It is only credible when the crew, workfront, equipment and approvals needed to achieve it are available.

For a preconstruction leader supporting a commercial or industrial project, the decision has three separate parts: can the team recover the time, what will it cost, and who is authorized and responsible to pay? A plausible schedule does not answer the last two questions. Use the current statused schedule and the contract, not the original bid assumption alone, as the starting point.

Find the time that can actually be recovered

Establish the data date, actual progress and the present forecast finish. Trace the sequence driving the relevant milestone through remaining activities and calendars. Verify whether the proposed intervention advances that milestone or merely consumes float on a noncontrolling activity. Check other paths that could become controlling after compression, along with inspection, energization, access and owner acceptance windows.

Preserve the approved reference and compare it with the current forecast. The baseline, update and lookahead guide shows how to carry an access constraint into near-term crew commitments. Before committing to a recovery scenario, test the logic and the practical availability of each workfront with the superintendent and affected trades.

Compare two ways to recover an equipment handoff

In this illustrative industrial project, late equipment delivery moves a mechanical handoff four working days beyond the current milestone forecast. The statused schedule shows installation and testing as the controlling remaining sequence. Assume the equipment is now available, testing staff can attend, and the owner can accept the earlier handoff. The scheduler models two options, each forecast to recover four working days. Those assumptions need confirmation; four days is an example, not a promised production rate.

QuestionExtended hoursAdditional crew
Schedule mechanismSame crew works longer on installationSecond crew works a separate released workfront in parallel
Feasibility testConfirm access, supervision, testing and crew agreement for extended hoursConfirm spatial separation, equipment, competent supervision and no interference
Cost driversOvertime premium, assumed productivity loss and longer supervisionIncremental labor, mobilization, equipment and coordination
Stop conditionReforecast if hours do not produce the planned installed quantitiesReforecast if the second workfront is not released or crews interfere

Resequencing is a third option if another workfront can be released without the equipment. Model its handoffs and any temporary work or remobilization before treating overlap as recovered time. The guide to pricing phasing and handoffs helps identify those repeated costs.

Build a comparable incremental cost bridge

Assume the existing forecast already includes the straight-time labor and equipment for the remaining base installation. The figures below are hypothetical incremental costs over that same forecast, not market rates or a subcontract quotation. The scheduler's four-day recovery forecast and the estimator's productivity assumptions must be checked with the trade before use.

Incremental cost itemExtended hoursAdditional crew
Overtime premium: 128 hours at an additional $30 per hour$3,840$0
Productivity allowance: 40 additional hours at $90 per hour$3,600$0
Additional crew labor: 128 incremental hours at $60 per hour$0$7,680
Mobilization and additional equipment$0$2,000
Extra supervision and coordination$1,600$1,200
Total incremental forecast$9,040$10,880

The overtime entry is the premium only because the corresponding straight-time work is already in the base forecast. The 40 hours are a separate assumed loss of productivity priced at the illustrative extended-hours rate. For the added crew, 128 hours represent extra labor after deducting any labor displaced from the original crew plan. Verify that deduction in the trade's detailed estimate. The totals exclude tax, markup, financing and any change to project duration costs; add applicable items consistently and document exclusions. If either option changes those costs, recalculate the comparison.

On these assumptions, extended hours cost $1,840 less. That is not a recommendation until the trade confirms output, access and the quote. If overtime can recover only two days, compare the cost per achievable milestone date, not just the totals. Likewise, a second crew is not useful if the workfront opens too late. Set a production checkpoint, such as installed quantities after the first two shifts, and a decision date for abandoning or revising the plan.

Separate authority, entitlement and field release

The recovery plan may be necessary to protect a milestone even while payment responsibility is disputed. The PM should check the prime contract's notice, schedule submission, change and direction provisions, then document the cause, dates and correspondence. An owner-directed acceleration, a contractor-caused delay and an unresolved delay may receive different treatment under the actual contract. Do not infer entitlement from the existence of a recovery schedule.

For example, FAR 52.236-15, when included and applicable, permits the contracting officer in the specified behind-schedule circumstance to require measures such as overtime or additional shifts and a supplementary schedule, without additional cost to the government under that clause. Other facts, clauses and contracts can affect the outcome; this example does not settle a particular claim.

Separately, the GC must check the subcontract's direction and pricing process. A superintendent's request for a crew is not a substitute for the authorization required by that subcontract. Obtain a scope, hours, rates, schedule commitment, exclusions and written direction or other agreed authorization before releasing the additional work. Preserve daily time, quantities and equipment records so the actual cost and productivity can be reconciled with the forecast.

Use a recovery decision register

Decision or evidenceAccountable leadRecord before commitment
Current controlling sequenceSchedulerData date, activity IDs, logic and forecast milestone
Recovery feasibilitySuperintendent and tradeWorkfront release, crew availability, calendar and production target
Price and productivityEstimator and subcontractorCommon base forecast, incremental hours, rates, exclusions and checkpoint
Prime contract positionPM and commercial leadCause, notice deadlines, direction and unresolved entitlement
Subcontract releasePM and subcontract administratorWritten scope, price basis and authorization under the subcontract

Keep the register with the schedule version and trade proposal. Review actual progress at the agreed checkpoint, update the forecast and record who approves any new plan. To track schedule and cost risks, carry the unresolved productivity and payment assumptions separately rather than burying both in one contingency.

FAQ

Does an approved recovery schedule authorize extra payment?

Not necessarily. Schedule acceptance and compensation depend on the actual contract and the direction given. Document the recovery plan, any required notice and the separate commercial decision.

Which option is cheaper, overtime or another crew?

It depends on achievable output and the incremental resources required. Compare each against the same base forecast, including productivity, supervision, equipment and any displaced work, then verify that the option advances the relevant milestone.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.