Construction submittals: build the register before procurement commitments

Build a submittal register from project requirements and connect review, procurement and installation dates to the cost and schedule assumptions in the bid.

Guide2 min read

Published

Construction scaffolding interior

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Extract the register from the bid set
  2. Example: air-handler shop drawing
  3. Transfer the register at award
  4. Develop the submittal scope

Build the submittal register before procurement dates are promised. For each required item, identify the source, preparer, GC review, designer or other reviewer, required lead time and release gate. Then include the work of preparing and coordinating it in the relevant trade and GC carries.

A submittal conveys required information for review, such as a product data sheet or shop drawing. An RFI asks for clarification; a response may change what the submittal must show. Under FAR 52.236-21, when that federal clause applies, the contractor must coordinate and review required shop drawings. Other contracts can assign different procedures and review periods. Read the actual agreement and specification rather than assuming this clause governs.

Extract the register from the bid set

Review Division 01 and each technical section for required items and review procedures. Capture specification section and paragraph, equipment or work area, required format, responsible trade, reviewers, review duration, resubmission allowance, milestone and cost owner. Cross-check procurement dates against required decisions. Turn specifications into trade scope, and connect RFIs to scope and pricing when the documents do not specify a review gate.

Example: air-handler shop drawing

Assume an illustrative contract requires a reviewed air-handler shop drawing before order release. The mechanical subcontractor prepares the drawing; the GC checks coordination; the designer responds. A supplier needs eight weeks after release. If preparation takes two weeks, GC review one week and designer review two weeks, the planned path is 13 weeks before delivery, excluding resubmission and holidays. These are assumed durations, not standard review periods. Add a project-specific resubmission allowance where justified, and confirm whether the schedule permits early procurement.

Register fieldIllustrative entryBid action
Source and itemMechanical specification, air-handler shop drawingVerify exact paragraph and model
PreparationMechanical trade and supplierConfirm quote includes drawing and revisions
Review gateGC then designer before orderConfirm contract language and durations
Release and deliveryAfter required response, eight weeks to deliveryCompare to construction milestone
Open issueDuct connection conflicts with steelAssign resolution before final drawing

The duct connection may require BIM coordination, but a model check does not replace the specified submittal review. If a bidder excludes coordination or revisions, normalize its price and ask for a defined scope. Include GC review time and avoid counting trade preparation twice.

Transfer the register at award

Mark each item pending, submitted, returned or accepted using the agreement's terminology. Preserve the controlling revision and show changes to dates and responsible parties. A register is a planning tool; it does not itself grant approval or alter the contract.

Develop the submittal scope

Piper's Scope Generation turns project requirements into trade scopes with source-linked findings. The team builds and maintains the register and decides the approval and procurement sequence.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.