Daisy Field: separate field drainage from riparian restoration
Separate Daisy Field drainage from excluded riparian restoration, uncertain parking work and permanent-restroom assumptions.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 2 min
- Published
On this page
Carry the field drainage response separately from riparian restoration. The November 2025 briefing describes green infrastructure intended to address infield washout, while woodland and riparian restoration and permanent restrooms were outside the then-current scope.
The following register is an estimator's interpretation of the cited public records, not a contract scope or a substitute for the current procurement documents.
Define field, drainage and excluded restoration limits
| Work or location | Public record | Estimator's review |
|---|---|---|
| Fields | Two hybrid softball and little-league fields with skinned infields | Confirm grading, surfacing and field equipment in the issued set. |
| Stormwater | Green infrastructure intended to address infield washout | Define collection, overflow, outfall and restoration interfaces. |
| Pond edge and woodland | Restoration excluded from existing scope | Identify temporary protection and any separate package. |
| Parking | Renovation TBD because of a funding gap | Price separately until procurement documents establish inclusion. |
| Restrooms | Space and pad for two portable units; permanent facilities excluded | Confirm pad, service access and unit responsibility. |
Treat washout reduction as an intended result
The owner said existing permit-holder logistics required both fields to remain hybrid. That affects the review of skinned infields and transitions, but the meeting record is not a final field specification.
The briefing reported no formal comprehensive study of water quality or erosion impacts. The stated green infrastructure benefits are project intentions, not measured reductions. Keep a distinction between controlling sediment during the work and the permanent system’s designed performance.
The primary records are Improvements to Daisy Field (Olmsted Park) official City project page Daisy Field Community Briefing Notes (November 5, 2025).
Reconcile drainage, parking alternatives and portable facilities
Ask for drainage calculations, utility and pond-edge limits, temporary erosion controls, parking alternates and issued specifications. Separate field work from any restoration proposed by others, and reconcile the portable-restroom pad with access and maintenance. A historical 2027 expectation is not a current contract schedule.
Before relying on a public presentation, trace the official Boston project record and check the controlling issued revision.
Related reading
Construction addenda management for GC estimators
Addenda are official bid-document revisions. Log them, distribute them, retakeoff the deltas, and require subcontractor acknowledgments so your estimate and every bid reflect the final scope.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.