DBIA Liberty Region Conference 2026: check the teaming assumptions before pricing a pursuit

Prepare a design-build teaming review from the DBIA Liberty conference context, recording design scope, pursuit costs, estimate basis and decision owners.

Guide2 min read

Published

Construction scaffolding interior

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Create an alignment record before pricing
  2. Worked boundary: design-build building services
  3. Connect the agreement to the estimate

A conference contact is not a teaming agreement. Before a design-builder prices a pursuit with a designer, document the assumed design scope, maturity, decision authority and pursuit cost responsibility. If those boundaries remain open, present the estimate as conditional and send the commercial issues to the people authorized to resolve them.

The DBIA Liberty event listing places its past September 15–16, 2026 conference in Breinigsville, Pennsylvania. Its regional audience includes Upstate New York. Separately, DBIA's May 2026 teaming guidance announcement emphasizes early alignment and team responsibilities. The announcement does not establish that the conference covered that guidance. DBIA's best-practices overview organizes general guidance around procurement, contracting and execution; applicability depends on the project. This is independent analysis, not a conference recap.

Create an alignment record before pricing

DecisionEvidence to captureEscalation
Design scopeDisciplines, deliverables, interfaces and exclusionsDesign lead confirms who does what
Estimate basisIssued documents, allowances, pricing assumptions and revisionChief estimator approves basis
Pursuit costWho authorizes work and tracks proposal expense?Commercial lead resolves authority
Design maturityWhat is drawn, implied or still owner-selected?Designer and owner decision lead identify gaps
CommunicationsWho sends questions and approves commitments?Name a single decision owner and backup
Changes and exclusionsWhich boundary or later change remains unresolved?Counsel and authorized commercial leads review allocation

Use the matrix to expose commercial questions, not to write contract clauses. Preserve each party's assumptions and the unresolved decisions alongside the estimate. The team's counsel and design lead should review risk allocation and the actual agreement. A contact's willingness to discuss a pursuit is not authority to commit either firm.

Worked boundary: design-build building services

For a fictional design-build renovation, the design-builder expects the designer's fee to include coordination of existing services. The designer's initial scope covers new systems but does not describe investigation of concealed services. The estimator must not assume both descriptions mean the same work. Record the existing-services investigation as open, ask the designer for a defined deliverable and fee assumption, and ask operations how access limitations affect investigation. The commercial lead determines who can authorize additional pursuit work.

If the owner has not decided the extent of renovation, identify the decision and its effect on scope and schedule. Carry a documented assumption or alternative for internal approval; do not present unresolved investigation as a committed price. Record who approves any change to the basis after the team's agreement is signed.

Connect the agreement to the estimate

The delivery-method comparison shows why design-build changes estimating interfaces. The incomplete-drawings guide helps distinguish documented design from assumed intent. If a GMP is contemplated, the GMP basis review connects outstanding owner decisions to the proposed ceiling. None of those resources substitutes for project-specific legal or design review. The conference selection guide notes the event's out-of-state location.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.