Deductive alternates in a bid level: compare the same base before taking the credit

Normalize base and selected alternate scope, then trace residual work and overlapping credits across trade packages before setting the carry.

Guide6 min read

Published

Construction scaffolding interior

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Choose the common base first
  2. Three fictional proposals on different bases
  3. Separate bidder credits from GC adjustments
  4. Preserve the residual work and its owner
  5. Record the authorized scenario and the next decision

Before taking a deductive alternate credit, establish what every bidder's base contains and who owns the work that remains. A quote that already prices the alternate is not directly comparable to a quote that prices the original base. Nor can a GC take a second credit from another package simply because both trades mention the same removed work.

For a chief estimator selecting an interior package before award, the decision record should show the original base, the selected alternate, each bidder's price basis, and the source for every adjustment. Then trace the removed work and the remaining interface across packages. The objective is a comparable carry with a defensible scope owner, not the largest apparent deduction.

For public highway procurement, FHWA’s alternate-bidding guidance distinguishes the base from alternate scope and calls for a predefined order of consideration. That owner-agency procedure is not a universal award rule for subcontractor quotes. It illustrates why the chosen base and selection basis must be explicit; the commercial-interior example below uses its own stated assumptions.

Choose the common base first

Assume the team is leveling an interior package against the project documents and a defined alternate. Identify the document revision, quantities or areas in the alternate, the point at which selection is expected, and the scope required whether or not the alternate is selected. The common basis for a bid level is the starting point. The base and selected-alternate views are two scenarios on that basis, not two independent credits to stack.

The following proposals and amounts are fictional. They are a teaching example, not a record of a project or a recommendation for an award formula. Assume all other scope is equivalent and no taxes or other adjustments are needed for this illustration.

Baseline: The original interior scope calls for a decorative wall panel system and associated final edge trim in a reception area. The interior package owns panels and trim. The painting package separately carries painting a small adjacent return wall, including preparation. The base does not call for painting behind the panel system.

Alternate D1: Omit the decorative panel system and its final edge trim. Finish the exposed main wall with paint. The adjacent return wall still requires paint and preparation. The project team has selected D1 for the carry scenario, subject to the decision record below. The painting bidder has not yet priced the newly exposed main wall.

Three fictional proposals on different bases

  • Interior A, proposal A-1: $500,000 for the original base, with a separately stated $80,000 credit for D1. The credit omits the panels and final edge trim. The quote does not include the new main-wall painting.
  • Interior B, proposal B-1: $425,000 for the package with D1 already folded into its price. B states that the original panel and edge-trim work is omitted and gives no price to restore it. B does not include main-wall painting.
  • Painting C, proposal C-1: $50,000 for the base painting package, including the adjacent return wall. A note offers a $5,000 credit “if decorative wall finish is omitted,” but does not identify whether the return wall is removed or whether the newly exposed main wall is included.

These are three proposals across two packages, not three interchangeable interior bids. A's selected interior price is $420,000 ($500,000 less $80,000). B's selected price is $425,000. On this narrow selected-scope comparison A is $5,000 lower, before resolving painting. B's $425,000 is not an original-base price, so do not subtract D1 again. Without a supported restoration price, B's original-base equivalent is unknown. Request it if the team needs to compare the original-base scenario.

The painting note is the consequential interface. A's credit already removes the interior panel and trim. C's note might refer to a different painting item, or it might mistakenly remove the adjacent return that D1 still requires. Its wording does not say. Taking $5,000 merely because the decorative finish is omitted could leave the return wall uncovered; treating it as an automatic duplicate would also be unsupported. The reviewer needs the actual work and price behind C's credit.

Separate bidder credits from GC adjustments

In the selected scenario, A's $80,000 is a bidder-stated credit against A's $500,000 base. B's $425,000 is already a bidder-stated selected-scope price. Neither number provides a price for the new main-wall painting. C's $5,000 is conditional and ambiguous, so leave it out of the active carry until the scope and basis are clarified.

Suppose the GC prepares a fictional $12,000 allowance for painting the exposed main wall pending a written price. Using A and C, the selected-scope working carry is $420,000 interior plus $50,000 painting plus $12,000 GC allowance, or $482,000. Using B and C on the same assumptions gives $487,000. The allowance is a GC estimate, not C's quote. These sums explain the register; they are not an assertion of savings or an industry finding.

If C later confirms a $12,000 addition for the main wall, replace the allowance with the confirmed addition in the selected painting price. Do not retain the allowance as a second $12,000. Separately, ask C to identify exactly what its $5,000 credit removes. If it removes the still-required return-wall work, do not take it unless that work is reassigned and separately covered. If it applies to an actually omitted, separately priced item, assess the credit once against that item and retain its written basis.

A bidder's credit, a GC allowance and a transfer to another trade are different entries. A transfer requires an identified receiving package, defined scope and a price or explicit unresolved allowance. Moving a line to “painting” without C's inclusion does not establish coverage.

Preserve the residual work and its owner

Use an interface review before approving the selected carry. In this fixture the original panel and trim disappear, but preparation and finish of the newly exposed wall appear. The return wall was already required and remains required. The estimator should ask the design and project team to confirm the D1 finish extent and the relevant scope documents, then request C's written price and a breakdown of its proposed credit. If another trade is to own the new finish, document that trade's inclusion and remove only the overlapping allowance once verified.

Also check whether the omitted panel work has associated protection, substrate preparation or transition details that remain necessary under the actual documents. Do not assume every associated task disappears with the panel, or that the painter has included all of it. Record each open item as unresolved, its interim cost treatment, the owner of the question and the date needed for a carry decision. Reviewing exclusions and qualifications helps separate an explicit omission from silence.

Record the authorized scenario and the next decision

The chief estimator can carry D1 as a planning selection while the project team's formal selection remains pending, but the register must say which it is. Identify who selected or authorized the scenario, the source and date, and what happens to the carry if D1 is rejected. Revisit the base comparison when the selected scope, schedule or package assignments change. For the broader choice of how to support a carry, see a defensible carry number.

Piper bid leveling compares subcontractor bids against project scope with source-linked findings. The estimating team reviews and decides the carry, including how to resolve the cross-package scope and pricing questions.

Use this matrix for each alternate and review it with the package owners:

Decision fieldBase scenarioSelected alternate scenario
Scope and sourceDocument revision and original required workAlternate ID, document revision and exact work removed or added
Decision authorityBase used for comparison; reviewer and dateSelection status, decision owner, evidence and date
Interior proposalSubmitted base, inclusions and sourceBidder credit or already-adjusted price; source and reviewer
Other packageIts original price and named scope ownerConfirmed changed scope and price; no assumed transfer
Residual workWork that must remain covered and ownerNewly exposed and retained work, receiving owner and source
GC adjustmentsSeparate allowance or plug and rationaleActive, retired or unresolved adjustment; avoid duplicate credit
Open decisionsMissing source or price, question owner and due dateWritten clarification needed, next review and effect if selection changes
ShareLinkedInX

Related reading

Guide7 min

How to set a carry number you can defend

The method for getting from a submitted subcontractor bid to the number that actually goes in the estimate, including evaluated cost, expected-value risk pricing, and the duplicate-contingency trap.

Construction scaffolding interior

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.