Harrison Ink Block: trace interim median, signals and final surfaces

Trace Harrison Ink Block’s temporary median, remaining signals, final asphalt and weather-dependent striping as separate handoffs.

Guide2 min read

Published

Tower crane above steel reinforcement

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Track temporary median, islands and final surfaces separately
  2. Read September counts as a dated construction snapshot
  3. Request current signal cutover, staging and payment quantities

Track the temporary asphalt after median demolition as an interim condition, then separately track islands, remaining signals and final surfaces. The September 2026 presentation is a dated snapshot, not a current completion count.

The following register is an estimator's interpretation of the cited public records, not a contract scope or a substitute for the current procurement documents.

Track temporary median, islands and final surfaces separately

Work or locationPublic recordEstimator's review
MedianDemolished and temporarily asphalted in September reportConfirm remaining light posts and raised catch basin removals.
SignalsThree of five new mast arms reported installedVerify current inventory and remaining foundations and connections.
RoadwayExcavation and initial repaving forecastCoordinate sections with access and later island work.
Crossing islandsForecast after initial repavingIdentify layout, curbs, paving tie-ins and traffic staging.
Final surface and markingsTop layer and weather-dependent striping listed separatelyTrack final placement and acceptance independently.

Read September counts as a dated construction snapshot

The September 16 owner report also recorded 17 reconstructed ramps and updated meters. It forecast remaining mast arms and islands in October or November, and said final striping might move to spring 2027 because of weather. These counts and dates should not be treated as present-day progress.

The City said residence and business access would be maintained and described weekday working hours. Those are owner-stated constraints in the presentation; they do not establish the contractor’s detailed means and methods. An end-of-2026 substantial-completion forecast and a 2027 hub completion expectation describe different statements, not verified acceptance.

The primary records are September 16, 2026 Washington Harrison Neighborhood Association Presentation official primary document Harrison Avenue Reconstruction (Ink Block) live official body.

Request current signal cutover, staging and payment quantities

Use a section register with existing condition, access route, initial pavement, island, signal, final asphalt and striping columns. Request current updates, issued staging, signal cutover and inspection requirements, and payment quantities before forecasting remaining work.

Before relying on a public presentation, trace the official Boston project record and check the controlling issued revision.

ShareLinkedInX

Related reading

Guide4 min

Construction addenda management for GC estimators

Addenda are official bid-document revisions. Log them, distribute them, retakeoff the deltas, and require subcontractor acknowledgments so your estimate and every bid reflect the final scope.

Tower crane above steel reinforcement

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow