TxDOT’s 3C-2 Pond A estimate starts with work assigned to 3B-1
Classify Pond A work across 3B-1 and 3C-2 before taking off quantities, and track the unresolved construction interface.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 3 min
- Published
On this page
A 3C-2 estimator should not price the whole conceptual Pond A footprint as new 3C-2 work. TxDOT's July 2026 project summary says part of the proposed pond is being constructed under 3B-1. Start by separating that portion, the potential 3C-2 work and the interface, then reconcile the issued limits and contract documents before locking a quantity.
The cross-package review was prepared with Piper, the AI operating system for preconstruction.
The important distinction is between a project description and a bid boundary. A pond can appear in the 3C-2 description while some construction is assigned to an adjacent project. That does not establish the finished interface, an accepted handoff or the quantities remaining to be built.
Read the two sections together
On page 6 of its July 21 project development summary, TxDOT describes Pond A near Elysian and Runnels and separately identifies South Canal and pump station elements. Page 1's adjacent-project coordination discussion says a portion of proposed Pond A is being constructed in 3B-1 and refers to a reference information document graphic showing construction limits. The 2025 workshop presentation also distinguishes the proposed pond from an area labeled “Pond by Others (Project 3B).”
The August 2026 reference document index identifies revision 1 of the South Canal and Ponds exhibit, issued January 30, 2026. Use the current applicable exhibit with the issued RFP when available. The early workshop drawing identifies the general interface. Exact construction limits and handoff status remain open.
Build an interface register before a takeoff
The following is an illustrative review register, not a statement of actual work limits or acceptance. The estimator should replace each open entry with a document reference and a responsible decision maker.
| Review item | Provisional classification | Evidence and next decision |
|---|---|---|
| Pond footprint or volume | Split is unconfirmed | Overlay latest issued limits and revisions; identify any overlap or gap before measuring |
| Work shown under 3B-1 | Adjacent project | Obtain current 3B-1 scope and status; do not assume completion or acceptance |
| Potential 3C-2 work | To be established | Match issued 3C-2 plans and pricing schedule to measured work; record exclusions |
| Tie-in and temporary work | Interface unresolved | Ask who provides access, protection, connections and restoration under the issued documents |
| Handoff condition | Open | Identify required condition, inspection and responsible parties from applicable documents; obtain confirmation |
Keep source, revision, measurement basis, quantity, estimate line, provisional owner and status together. A marked-up overlay can show two teams measuring the same area, but it cannot decide which contract owns excavation, protection or connection work. An RFI or issued clarification may be needed to settle those items.
Reconcile before committing the price
TxDOT’s RFQ page records October 23 qualification submitters. Use the latest limit exhibit and relevant 3B-1 records to prepare the scope questions, then reconcile them against the RFP and any addenda when issued. Compare their dates and stated applicability. Trace the pond boundary and each connection on the current drawing set, then record what the team can measure and what remains a question. Ask operations to review access and temporary work at the interface; price only on a stated basis pending resolution.
If an exhibit changes, preserve the old and new quantity bases and show the delta in the estimate. Do not treat a reference graphic as a promise that an adjacent contractor will deliver a particular condition. The construction scope generation guide provides a broader method for connecting each open responsibility to its source and estimate line.
Assign each part of Pond A in Piper
Piper produced a five-row register covering the adjacent 3B-1 work, potential 3C-2 quantities, physical protection and tie-in questions, and readiness evidence. Apply this approach to the controlling limits of each adjacent contract before releasing quantities. Keep the unresolved work visible until the current exhibits and issued scope identify who carries it.
Related reading
Construction scope generation: a practical guide for GCs
How general contractors turn drawings, specifications, addenda, and company standards into trade scopes a subcontractor can price, an estimator can trace, and a senior reviewer can challenge.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow