Logan L1741-C1: separate abandoned sanitary assets from active connections

Map abandoned pumps, piping and interceptor work separately from new fixtures and active sanitary connections at Logan Terminal B Pier A.

Guide2 min read

Published

Tower crane against an overcast sky

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. The advertised Terminal B work
  2. Create an asset and handoff record
  3. Resolve the limits before leveling

For L1741-C1, separate abandoned assets from the active sanitary system in the estimate. The notice pairs removal and filling with new fixtures connected to active drainage. A demolition row labeled “existing sanitary” is too broad to show that distinction or the concrete and finish handoffs.

The advertised Terminal B work

The Massport notice described abandoned ejector pumps on the first floor and in the basement, filling their pits and providing a finished slab. It also described cutting, capping and concrete-filling abandoned below-grade waste piping; removal of an existing below-grade oil interceptor and capping vents above the roof; and cutting and patching concrete and finishes at removed or installed floor fixtures.

Two new fixtures have distinct locations: a first-floor floor sink in the fire sprinkler valve room and a first-floor floor drain in the sanitary ejector room. Both connect to active below-grade sanitary drainage. The room name does not establish a sprinkler replacement. Plumbing and electrical were the listed filed trades.

Create an asset and handoff record

The following is an estimator's proposed review matrix. Confirm each location and responsibility against the issued documents.

Asset or interfaceNotice basisEstimator action
Abandoned ejector pumps and pitsRemove pumps; fill pits; finished slabIdentify each level and pit; record removal, fill and slab responsibilities
Abandoned below-grade waste pipingCut, cap and fill with concreteMark limits and separate from retained active drainage
Oil interceptor and roof ventsDemolish interceptor; cap vents above roofTrack below-grade removal and roof-level work separately
New floor sink and drainConnect each to active sanitary below gradeRecord room, tie-in reference, fixture and connection carry
Concrete and finishCut and patch at removed or installed fixturesRecord opening, patch and finish handoff for each location

For each row add drawing revision, quantity basis, proposal inclusion, exclusion and an owner for resolution. For example, record who carries the slab finish after pit fill rather than presuming the plumbing proposal includes it. This is an estimating question, not an instruction for construction sequencing.

Resolve the limits before leveling

The notice does not establish active-system shutdowns, temporary pumping, pipe sizes, slab reinforcement, contamination classification or closure durations. Obtain the drawings, specifications and clarifications before assigning those costs. The original general-bid date was August 12, 2026; the listing shows August 26, while the sub-bid date remained August 5. Retain those as separate historical records, not current response dates. Use revision tracking and the project-source guide to obtain the controlling amendments and any later package before making a new commitment.

ShareLinkedInX

Related reading

Guide4 min

Construction addenda management for GC estimators

Addenda are official bid-document revisions. Log them, distribute them, retakeoff the deltas, and require subcontractor acknowledgments so your estimate and every bid reflect the final scope.

Tower crane above steel reinforcement

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.