Lower Roxbury: trace drainage, curb work and final paving by location

Track utility, curb, sidewalk and final paving evidence by intersection across the Lower Roxbury Slow Streets project.

Guide2 min read

Published

Tower crane above steel reinforcement

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Location-by-stage evidence register
  2. Use the dependency without inventing progress

For Lower Roxbury Slow Streets, record status by intersection and by construction stage. A finished curb at one location does not establish final paving across the project, and the City's July 2026 handout was a tentative forecast, not proof of current production.

The July handout, page 4, separates utility work, curb excavation and forming, sidewalk pours, and signs followed by paving and markings. It labels the schedule tentative and weather-dependent. The City project page says in its August 2026 Harrison/Northampton update that final markings and paving follow completion of all project sidewalks and curbs.

Location-by-stage evidence register

Location from July handoutRecord separately for each stageNext evidence to obtain
Tremont / NorthamptonUtility; curb; sidewalk; signs and pavingDated field or owner update and issued scope
Harrison / NorthamptonUtility; curb; sidewalk; signs and pavingReconcile August owner update to current record
Shawmut / Kendall and Shawmut / LenoxUtility; curb; sidewalk; signs and pavingLocation-specific status and remaining interfaces
Washington / Thorndike and Shawmut / HammondUtility; curb; sidewalk; signs and pavingCurrent sequence and access constraints
Washington / East Lenox and Harrison / East LenoxUtility; curb; sidewalk; signs and pavingCurrent status and final-work dependency

For each cell, enter the date, source, status and next decision owner. Leave it unknown until supported. The handout gave tentative durations of one to two weeks per location for utility work, two to three for curb forming and two to three for sidewalk pours, followed by one to two weeks for signs, paving and markings. These historical forecasts are not trade production rates or a contractual schedule. The chart does not establish precise date intervals for each location in this record.

Use the dependency without inventing progress

If one intersection's drainage or utility work remains open, ask the owner and utility team for its current release and the curb subcontractor for the affected handoff. Compare that answer with the issued schedule and the City's stated project-wide final paving dependency. Record traffic access, restoration and remaining work as questions until supported by the package. Verify the procurement record and trace its revisions; an owner update alone does not establish final completion or a trade's contract obligations.

ShareLinkedInX

Related reading

Guide4 min

Construction addenda management for GC estimators

Addenda are official bid-document revisions. Log them, distribute them, retakeoff the deltas, and require subcontractor acknowledgments so your estimate and every bid reflect the final scope.

Tower crane above steel reinforcement

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.