Massachusetts 521 CMR: review cumulative renovation cost before fixing accessibility scope
Give the design team cumulative alteration costs and valuation evidence before limiting Massachusetts accessibility scope to a renovated room.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 1 min
- Published
A Massachusetts renovation estimate needs a cost and phase history before the design team can decide whether 521 CMR requires accessibility work beyond the immediate alteration. The Massachusetts Architectural Access Board identifies the 2006 edition as in force. Section 3.3 and 3.5 address alteration costs, full and fair cash value and work accumulated over 36 months, with qualifications and exceptions.
At 30% or more of the applicable full and fair cash value, section 3.3.2 can trigger whole-building compliance. Exempted work can still count in the calculation. Public-use status, tenant boundaries, exceptions and valuation need the designer's and, where appropriate, AAB's determination. Do not substitute a tax assessment or a single trade quote for that decision.
Assemble a cost-history worksheet
| Input | Evidence to request | Open decision |
|---|---|---|
| Public-use and tenant basis | Use, affected spaces and tenant boundaries | Designer determines applicable jurisdiction and exceptions |
| Work history | Costs and permits for work across the relevant 36 months | Designer identifies work included under the regulation |
| Current project | Trade and owner-furnished work, exclusions and phases | Reconcile complete alteration cost rather than just the current package |
| Valuation | Source and date of full and fair cash value evidence | Qualified reviewer establishes appropriate basis |
| Resulting scope | Designer or AAB decision and affected drawings | Carry building-wide work or unresolved allowance as appropriate |
If a fit-out is one of several phases, obtain earlier phase costs before fixing the GMP. List the valuation source and the person responsible for the determination; a missing history is a pricing uncertainty, not a conclusion that the threshold is or is not met. Confirm the code basis with the design team and review other Boston obligations.
Related reading
Construction code requirements: confirm the applicable basis before assigning scope
A model-code reference is not a project applicability decision. Review connecting adopted requirements, issued design information, trade scope and pricing.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow