Trans-Manhattan Expressway C-V2X Pilot: Scope and Procurement Forecast
Review Trans-Manhattan Expressway C-V2X Pilot scope, forecast timing and estimating questions before reviewing the issued documents and preparing a bid.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 2 min
- Published
On this page
The forecast describes a C-V2X pilot on the Trans-Manhattan Expressway, the New York approach between the George Washington Bridge and Alexander Hamilton Bridge. Its construction scope should be evaluated as a sensor-to-driver information chain, rather than priced as a single roadside device.
The proposed system uses high-resolution sensors and information channels including dynamic message signs, roadside alerts, data exchange and navigation messaging. The description says the pilot does not depend on in-vehicle sensors or connected-vehicle onboard units. A possible Stage 2, including the New Jersey side and other approaches, is conditional and is not established as the present pilot scope.
Forecast reference and procurement timing
The Port Authority construction forecast workbook lists the following entry:
- GWB C-V2X Deployment along TME (SMART GRANT): reference GWB243314; 2027 Q2 forecast procurement; published procurement approach SBE.
The workbook reference identifies the forecast entry; verify the solicitation identifier when an advertisement is issued. The quarter is a procurement forecast, not a bid deadline or construction start. The Port Authority construction procurements page says forecast information is the public information available until a solicitation becomes active. This independent Piper analysis is not an agency notice or confirmation of an open bid. Research checked November 15, 2026.
Trans-Manhattan Expressway C-V2X Pilot estimating questions
These are questions for the issued documents, not confirmed contract requirements:
- Which sensors, communications paths, signs and interfaces are in the issued installation package, and which are supplied by others?
- Where are power, mounting and network connection points, and who owns integration and acceptance testing?
- What data exchange and application interfaces are actually specified, and what constitutes a completed pilot?
The forecast leaves a material gap: Device counts, connection points, testing criteria and Stage 2 authorization are not stated. Record each open item with its source, a responsible reviewer and the assumed treatment in the estimate. Once drawings and specifications are issued, compare their limits and trade assignments before converting the forecast into a bid carry.
Review the issued package
Start with the current solicitation, drawings, specifications and any referenced reports, then track changes through construction addenda. Use the NYC public construction bid review to connect project interfaces to the estimate. The NYC public project directory provides a route to other named forecasts.
When actual project documents are available, Piper’s scope-generation workflow can be used with documents supplied by the team to prepare scope for review. The estimator remains responsible for resolving gaps and selecting the bid basis.
Related reading
NYC public construction bid review: connect the requirement to the number
A NYC public-bid review should trace owner requirements into scope, quotes, schedule and the final number. A practical review map for small GC precon teams.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.