JFK Building 14 Fleet Chargers: Scope and Procurement Forecast
Review JFK Building 14 Fleet Chargers forecast scope, procurement timing and estimating questions before reviewing the issued documents and preparing a bid.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 2 min
- Published
On this page
The JFK forecast calls for up to six Level 3 chargers for Port Authority fleet vehicles at Building 14, with electrical, civil, structural, traffic and environmental components needed for startup. A useful early estimate separates charger equipment from the site and power work needed to put it into service.
The row identifies a maximum, not six confirmed installations. It does not establish charger capacity, power source, layout or a division of supply responsibility. Those details can change both the electrical carry and the associated civil scope.
Forecast reference and procurement timing
The Port Authority construction forecast workbook lists the following entry:
- JFK - PA Fleet Charger Installation at Buildings 14: reference JFK154041; 2027 Q2 forecast procurement; published procurement approach PA.
The workbook reference identifies the forecast entry; verify the solicitation identifier when an advertisement is issued. The quarter is a procurement forecast, not a bid deadline or construction start. The Port Authority construction procurements page says forecast information is the public information available until a solicitation becomes active. This independent Piper analysis is not an agency notice or confirmation of an open bid. Research checked November 15, 2026.
JFK Building 14 Fleet Chargers estimating questions
These are questions for the issued documents, not confirmed contract requirements:
- How many chargers and what power ratings are specified, and who supplies each unit?
- Where are the point of connection, distribution equipment and cable routes, and what existing capacity can be used?
- Which foundations, traffic measures, environmental work and startup tests are actually required at Building 14?
The forecast leaves a material gap: Equipment ratings, layout, available capacity and quantities are not provided. Record each open item with its source, a responsible reviewer and the assumed treatment in the estimate. Once drawings and specifications are issued, compare their limits and trade assignments before converting the forecast into a bid carry.
Review the issued package
Start with the current solicitation, drawings, specifications and any referenced reports, then track changes through construction addenda. Use the Airport scope and operational-interface review to connect project interfaces to the estimate. The NYC public project directory provides a route to other named forecasts.
When actual project documents are available, Piper’s scope-generation workflow can be used with documents supplied by the team to prepare scope for review. The estimator remains responsible for resolving gaps and selecting the bid basis.
Related reading
Airport construction phasing: price the operational interfaces before the package
Airport work can depend on closures, controlled access and staged handbacks. Review connecting the safety and phasing plan to scope, schedule and price.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.