LaGuardia Runway Deck Wearing Course: Scope and Procurement Forecast
Review LaGuardia Runway Deck Wearing Course scope, forecast timing and estimating questions before reviewing the issued documents and preparing a bid.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 2 min
- Published
On this page
LaGuardia’s runway deck forecast describes removing the existing concrete wearing course and applying an epoxy-based wearing course, with lighting reinstallation, markings and grooving. For a precon team, the work is a coordinated surface-and-lighting package, not simply a concrete removal quantity.
The row does not describe the underlying deck repair scope or the new course thickness. The interface between removal limits, preparation of the exposed substrate, application, lights and finishing needs to be resolved from issued documents before any unit-price basis is reliable.
Forecast reference and procurement timing
The Port Authority construction forecast workbook lists the following entry:
- RUNWAY DECKS WEARING COURSE REHABILITATION: reference LGA124887; 2027 Q2 forecast procurement; published procurement approach PA.
The workbook reference identifies the forecast entry; verify the solicitation identifier when an advertisement is issued. The quarter is a procurement forecast, not a bid deadline or construction start. The Port Authority construction procurements page says forecast information is the public information available until a solicitation becomes active. This independent Piper analysis is not an agency notice or confirmation of an open bid. Research checked November 15, 2026.
LaGuardia Runway Deck Wearing Course estimating questions
These are questions for the issued documents, not confirmed contract requirements:
- What are the deck limits, existing course thickness and substrate acceptance criteria?
- Which lighting components are removed and reinstalled, and who carries testing and adjustment?
- What application, curing, grooving and marking sequence is specified for the selected material?
The forecast leaves a material gap: Deck quantities, substrate conditions, material specification and sequencing are not stated. Record each open item with its source, a responsible reviewer and the assumed treatment in the estimate. Once drawings and specifications are issued, compare their limits and trade assignments before converting the forecast into a bid carry.
Review the issued package
Start with the current solicitation, drawings, specifications and any referenced reports, then track changes through construction addenda. Use the Airport scope and operational-interface review to connect project interfaces to the estimate. The NYC public project directory provides a route to other named forecasts.
When actual project documents are available, Piper’s scope-generation workflow can be used with documents supplied by the team to prepare scope for review. The estimator remains responsible for resolving gaps and selecting the bid basis.
Related reading
Airport construction phasing: price the operational interfaces before the package
Airport work can depend on closures, controlled access and staged handbacks. Review connecting the safety and phasing plan to scope, schedule and price.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow