Piers Park II M629: distinguish seawall removal, revetment and upland work

Use separate quantity and design evidence rows for the Piers Park II M629 seawall and shoreline rehabilitation notice.

Guide2 min read

Published

Tower crane against an overcast sky

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. What the design-build notice says
  2. Create a boundary and evidence register
  3. Resolve the design inputs

For M629, maintain separate quantities for the existing seawall to be demolished and the shoreline section receiving revetment and associated upland work. The two approximate lengths in the historical notice describe different scopes; subtracting them does not establish a ten-foot extension.

What the design-build notice says

Massport's M629 letter-of-interest notice described design and construction of seawall revetment along about 260 linear feet of shoreline with associated upland work at Piers Park II. It described demolition of an approximately 250-foot deteriorated granite and concrete seawall and construction of stone revetment in its place. The notice says Piers Park II was completed in December 2023; that fact does not establish completion of this separate rehabilitation.

The notice requested letters of interest by April 1, 2026 and anticipated a two-part RFQ/P process. It does not establish a design-build award. Its proposed $8.5 million construction estimate is a dated owner estimate, not a bid or current cost benchmark.

Create a boundary and evidence register

The following is an estimator's proposed record for the design-build review:

ScopeNotice-level basisEvidence needed before quantity and carry
DemolitionApproximately 250 feet of deteriorated granite and concrete seawallSurveyed limits, sections, removal extent and material disposition basis
New shorelineAbout 260 linear feet of shoreline revetmentDesign limits and sections, stone and foundation design, quantity takeoff basis
UplandAssociated upland workPlan limits, restoration and interfaces with existing park features
Design and deliveryDesign and construction included in the noticeDesign responsibilities, deliverables, design development and pricing assumptions

Retain both lengths with their source descriptions and drawing references when available. For an illustrative review, if a demolition bidder measures only the existing wall while another prices the full shoreline limit, flag the different quantity bases before comparing totals. Neither measure alone resolves upland restoration or design responsibility.

Resolve the design inputs

The notice does not specify stone sizing, toe depth, tides, in-water work windows, final permits or staging limits. Request the applicable design-build documents and site information, then identify the party responsible for developing and pricing each unresolved input. Do not assign this notice to Piers Park III or the entire park. Verify the project scope and track controlling revisions as the design basis develops.

ShareLinkedInX

Related reading

Guide4 min

Construction addenda management for GC estimators

Addenda are official bid-document revisions. Log them, distribute them, retakeoff the deltas, and require subcontractor acknowledgments so your estimate and every bid reflect the final scope.

Tower crane above steel reinforcement

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.