Temporary construction power: assign the service, distribution and operating cost
Reconcile temporary construction power from service and distribution to usage, maintenance and removal, so electrical bids and general conditions carry the same basis.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 2 min
- Published
On this page
For a commercial GC, temporary power is a duration and distribution problem as well as an electrical installation. Before bid, identify the source, loads, changing floor locations and removal date; then reconcile the electrical quote with utility charges and GC operating costs. A service price alone does not cover the whole construction period.
Establish a phase-by-phase load plan
List major users such as hoists, temporary lighting, tools, offices and equipment startup, with the anticipated timing and locations. Ask the electrical designer and contractor to determine the installation and capacity, and consult the utility about its service process, charges and schedule. An estimator's load list is a basis for coordination, not an electrical design.
Read the site plan, general requirements, utility correspondence, project schedule and electrical specifications together. Link the plan to access, storage, and site logistics, because moving work fronts can change distribution and access. A constructability review in preconstruction can expose a service location that conflicts with the planned work.
Example: service for a multi-floor project
Assume a four-floor commercial project uses a utility temporary service and shifts interior work upward as each floor becomes available. The electrical bidder includes the service and initial distribution, but excludes utility fees, consumption and relocation. The GC should obtain prices or documented allowances for those exclusions, not assume that “temporary power included” covers them.
| Cost item | Proposed owner | Bid check |
|---|---|---|
| Utility application and connection charges | GC coordinates, utility charges as applicable | Confirm lead time, deposit and responsibility |
| Service equipment and initial distribution | Electrical contractor | Confirm capacity basis, floors and equipment rental duration |
| Floor-to-floor relocation | Electrical contractor at defined moves | Price number of moves and access assumptions |
| Energy consumption | GC allowance | Estimate duration and use; identify meter and tariff assumptions |
| Maintenance and damaged equipment | Allocate by contract | Confirm inspection, repair response and treatment of damage by others |
| Removal and restoration | Electrical contractor and GC as allocated | Define removal timing and restoration scope |
For an illustrative carry, assume initial electrical work is $24,000, two relocation visits total $4,000, and estimated utility charges are $1,000 per month for ten months. The arithmetic carry is $38,000 before maintenance, taxes, deposits, removal or other unpriced items. These figures are invented to show the split, not market pricing. If the electrical base already includes relocation, remove the duplicate add-back. A two-month extension changes the energy assumption by $2,000 before any additional rental or supervision; revisit all duration-sensitive lines.
Confirm safety and responsibility
OSHA 29 CFR 1926.405(a)(2) addresses temporary wiring and requires its removal immediately upon completion of construction or the purpose for which it was installed. Other applicable rules, utility requirements and project specifications also matter. Qualified electrical designers, contractors and employers determine the compliant arrangement and safe work practices.
Before the carry, record included equipment, service date, monthly operating allowance, move count and removal. Put unresolved utility charges in the estimate with an owner and due date. The allocation may appear in either general conditions and general requirements or a trade package; the cost needs one clear home.
Level the electrical quote against the plan
Piper Bid Leveling compares proposals with intended scope and links findings to sources. The estimator can review exclusions and decide the add-backs and duration assumptions.
Related reading
General conditions vs. general requirements: separate the contract from the cost plan
General conditions can mean contract terms or job costs. A GC review for separating that language from Division 01 requirements and package pricing assumptions.

Construction logistics plans: turn access and storage assumptions into priced scope
A site logistics drawing is useful when its assumptions reach the estimate. Review access, storage, deliveries, handling and repeated moves before pricing.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow