Temporary works in a bid: assign design, review, installation and removal separately

A prebid responsibility matrix separates temporary-work design and review from equipment supply, inspection, maintenance and removal.

Guide2 min read

Published

Construction scaffolding interior

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Build a design-to-removal matrix
  2. Test a formwork exclusion
  3. Close the bid basis

A rental price does not establish who designs, reviews, installs, inspects and removes temporary works. Before a GC estimator carries a formwork or shoring quote, map each service to a named party or record it as open. This is a commercial scope review, not an engineering design.

Build a design-to-removal matrix

Start with the project provisions and the actual proposal. The following are questions to assign, not default legal responsibilities.

FunctionEvidence to requestIf not assigned
Criteria and loadsResponsible designer's criteria and applicable project basisIdentify designer and obtain basis
Delegated designProposal, deliverables and design scopeObtain written service and price
Independent or owner reviewContract provisions and review scopeDetermine if required and who pays
Supply and erectionRental terms, installation and accessSeparate equipment from labor
Inspection and maintenanceInspection scope, timing and change responseAssign qualified service and carry
Changes and removalApproval and removal authorizationIdentify authority and closeout responsibility

The 1993 FHWA temporary works advisory addresses bridge owner agencies and calls attention to allocation among contractors, subcontractors and suppliers. It is guidance for those agencies, not an automatic allocation on every project. OSHA's cast-in-place concrete rule separately addresses formwork capacity, available drawings and shoring inspection. Its actual applicability and the project's requirements need qualified review.

Test a formwork exclusion

Suppose a formwork rental proposal includes equipment but excludes design and inspection. Mark both services open, ask for a written price and identify the party responsible for the criteria. Do not treat the rental company's equipment list as an installed and reviewed system. Check whether erection, maintenance, revisions and removal are included in another quote or the GC carry. If the answer is unknown, list the exposure and its owner rather than silently assigning it to the concrete trade.

Close the bid basis

Record the scope source, revision, estimated service cost, review requirement if any, and the person who must resolve each blank before commitment. Owner review, where required, does not itself establish the contractor's other obligations. If design or access assumptions change, return to each affected service rather than changing only the rental duration. Separate the project obligation from the cost code so an accounting classification does not conceal an unassigned service.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.