I-10 White Oak Bayou kept the same girder length and changed six bid quantities

TxDOT’s White Oak Bayou addendum corrected five girder codes across two bridge sheets, changing six bid quantities while the combined length held steady.

Guide3 min read

Published

Tower crane above steel reinforcement

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Follow the codes on the two bridge sheets
  2. Check the price at the item level
  3. Reconcile the bid form and the supplier quote

TxDOT’s I-10 White Oak Bayou bid package in Houston still showed 246,174.560 linear feet across six prestressed girder items after Addendum 3. The six item quantities all changed. On two bridge sheets, TxDOT corrected five bid-code headings while the girder descriptions and the lengths beneath those headings stayed the same. If your takeoff and supplier quote already agree on the pieces, reconcile that code change in the estimate before you carry a new price. Addendum 2 plan revisions, pp. 53–54, Addendum 3 plan revisions, pp. 25–27

Follow the codes on the two bridge sheets

On sheet 2227, the I-45 HOV to I-10 westbound direct connector extension, the TX28 and TX40 columns both kept their lengths. On sheet 2249, the I-10 eastbound to I-45 northbound direct connector, the TX34, TX46 and TX54 columns kept theirs. Comparing the July 29 and July 30 issues gives these five transfers. July 29 revision, sheets 2227 and 2249, July 30 revision, sheets 2227 and 2249

SheetGirder seriesLength carriedPrior sheet codeCorrected code
2227TX28240.660 LF425-6038425-6035
2227TX40390.970 LF425-6039425-6037
2249TX343,444.600 LF425-6038425-6036
2249TX461,364.800 LF425-6039425-6038
2249TX541,731.200 LF425-6040425-6039

The five corrected columns cover 7,172.230 linear feet. One reason the change is easy to miss is that some bid codes gained and lost length. Item 425-6039, for example, lost 390.970 and 1,364.800 feet and picked up 1,731.200 feet. Its project quantity moved by only 24.570 feet. The TX34 item, 425-6036, moved from 2,062.590 to 5,507.190 feet. Both changes reconcile to TxDOT’s replacement bid insert and the project quantity sheet, 40B. Prior bid insert, p. 10, Replacement bid insert, p. 9, Revised sheet 40B

Check the price at the item level

At the August 1, 2024 letting for CSJ 0271-07-326, TxDOT tabulated $407,810,028.26 from Webber, LLC and $459,501,382.24 from Williams Brothers Construction Co., Inc., a difference of $51,691,353.98 for the whole contract. The public tab shows why the estimating key matters. Webber’s submitted unit prices for TX34 and TX46 were $211.190 and $201.260 per foot, respectively. Williams Brothers’ were $135.000 and $150.000. The tab reports submitted prices and final bid quantities. It gives no breakdown of the causes of the overall spread. TxDOT project bid tab

Reconcile the bid form and the supplier quote

Start with the changed bridge columns. Keep the bridge, girder series, length and corrected bid code together on each estimate row. Check the resulting item totals against the final bid insert, then match the supplier quote to the series and pieces it covers. If the quote used the old codes, ask the supplier to confirm which pieces, delivery and erection it priced before rolling the quote into the corrected items. Resolve any remaining scope or price question at that line while you can still trace it back to the sheet. The construction addenda management guide covers the wider process for review and acknowledgment.

ShareLinkedInX

Related reading

Guide4 min

Construction addenda management for GC estimators

Addenda are official bid-document revisions. Log them, distribute them, retakeoff the deltas, and require subcontractor acknowledgments so your estimate and every bid reflect the final scope.

Tower crane above steel reinforcement

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.