Atlantic Avenue BED778A: the 2020–2021 utility-to-street sequence

Use DDC’s archived 2020–2021 Atlantic Avenue plan to examine underground-to-street restoration and night-work handoffs.

Guide2 min read

Published

Tower crane above steel reinforcement

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Read the utility-to-street sequence
  2. Price the operating cycle, not only the pipe

The archived DDC presentation for BED778A, whose cover says March 2020 and whose filename is indexed March 2021, describes a planned sequence for Atlantic Avenue from Carlton Avenue to South Oxford Street. Its value to a GC is the relationship between underground utility work and street reconstruction, not a current work permit or a verified completion date. DDC records a March 30, 2020 notice to proceed and anticipated completion in winter 2021.

Read the utility-to-street sequence

The presentation describes one-block-at-a-time work. Its sequence separates preliminary work, DEP underground work and DOT above-ground work. DDC presentation, pages 4–6

SequenceActivities in the historical presentationQuestion for a new estimate
PreliminaryScheduling, outreach, tree protection, test pits and stagingWho owns each setup and how often does it recur?
DEP undergroundStreet cutting, excavation, watermain, hydrants, sewer and catch basinsWhat testing and handoff release the street phase?
DOT above groundCurbs, roadway and sidewalksWhat temporary surfaces and final restoration are included?

The sequence is an analysis aid. It does not establish that each block actually followed the plan or that the project finished on the anticipated date. For a new bid, trace the limits and acceptance of each underground segment before carrying final pavement. An apparently complete pipe installation can still leave testing, temporary protection and a later return for surface work; the issued contract determines which of those activities applies.

Price the operating cycle, not only the pipe

The historical schedule listed noisy work from 7 a.m. to 6 p.m. weekdays and pipe installation and necessary shutdowns from 9 p.m. to 5 a.m. weekdays, subject to event embargoes. It also described maintaining pedestrian and roadway access and coordinating temporary driveway restrictions case by case. These are project-specific historical arrangements, not current permission or a general NYC rule. DDC presentation, pages 9–10

For a new package, put the permitted window, setup, traffic maintenance, shutdown approval, temporary surface and restoration in the same schedule row. A night crew may have less installation time than its nominal window once setup and reopening are accounted for; price the actual documents and production assumptions. The night-work estimating guide develops that operating-cycle review.

Obtain the current contract, access conditions and addenda before applying any historical sequence. The NYC public bid review checklist helps separate the source presentation from the bidder's obligations. This is independent historical analysis.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow