AUS campus utilities GMP 3: review hydronic, electrical and telecom interfaces
Review AUS East Campus GMP 3: assign common excavation, duct banks, hydronic lines, reclaimed water and vault interfaces before carrying utility proposals.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 2 min
- Published
On this page
AUS lists East Campus Utilities as campus-wide utility infrastructure GMP 3, with a Q4 2026 anticipated release. The listed work includes medium-voltage and telecom duct banks, reclaimed water, hydronic piping, manholes and vaults. AUS planned subcontracting Source status checked November 17, 2026. Treat the trench and the service as separate estimating boundaries. A complete piping price may not include the duct-bank excavation, shared vault work, restoration or the plant-side connection needed to place it in service.
Separate shared civil work from each utility service
The following register is estimating analysis, not a statement of the owner’s contract assignments. The owner overview establishes the project context; the current drawings, specifications and package documents determine what a bidder must carry.
| Interface | Review boundary | Decision to resolve |
|---|---|---|
| Shared corridor | Excavation, support, backfill and restoration | Who controls the trench and allocates common work? |
| MV and telecom duct banks | Conduits, encasement and vault entries | Who supplies pull provisions, penetrations and final terminations? |
| Reclaimed water and hydronics | Pipe, fittings, isolation and tests | Where do campus lines stop and plant or building packages begin? |
| Manholes and vaults | Structures, access and crossing clearances | Which package constructs each structure and seals incoming services? |
| Cutovers | Connections to existing and future services | Who coordinates outages, temporary service and acceptance? |
The airport identifies Sundt-Archer Western as prime. Its broader campus program also describes power distribution, drainage and ponds; those program elements should not automatically be assigned to the East Campus GMP 3 listing. AUS expansion
Assign the East Campus connection points
Overlay the issued utility plan with the trench sections and plant connection drawings. For each crossing, log excavation owner, installation sequence, survey hold point and restoration limit. Carry an explicit qualification where the drawings do not establish whether one contractor installs another trade’s sleeves or vault entries.
Use the published East Campus list as a boundary check, not the whole campus utility program. A quote for hydronic piping can be complete within its limits while a shared vault, duct-bank crossing or campus-to-plant connection remains outside it. Mark those interfaces on the actual issued plan, then ask both affected packages to identify their termination points.
Documents to request before committing
Request the East Campus GMP 3 scope sheet, shared-corridor sections, vault schedules and campus-to-plant connection details. For reclaimed water and hydronics, distinguish service testing from testing the common civil structures. For medium voltage and telecom, identify the package furnishing conduits, the package pulling conductors or cable, and the party accepting each crossing.
The underground piping boundary review provides a broader method for documenting these boundaries and carrying unresolved assumptions through bid review.
Related reading
The five-foot line: plumbing and site utilities
Review plumbing and site-utility endpoints, connections, excavation and fees against actual project requirements before assigning scope or carrying a price.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.