BIM coordination vs. clash detection: turn model findings into decisions

Distinguish BIM coordination from detecting clashes. Track model issues through ownership, resolution and issued documents before relying on an estimate assumption.

Guide2 min read

Published

Construction scaffolding interior

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Establish what was checked
  2. Work the issue through a decision
  3. Close against documents, not a colored status

A clash report identifies a potential geometric conflict. Coordination decides whether it matters, who must resolve it, what the resolution changes and how the team will verify closure. A clear model report alone is not proof that the design is buildable, that every required clearance was checked or that the revised work is included in the bid.

buildingSMART's BIM Collaboration Format description uses a beam and duct example to illustrate assigning an issue, discussing it and tracking its resolution. The format supports communication; the project team still decides the solution.

Establish what was checked

Record model authors, versions, dates, coordinate alignment, included trades, model detail and check rules. A check of physical intersections may not test access for maintenance, insulation thickness, installation sequence or components absent from the model. Ask the model manager what was included before interpreting a clean report. Compare the model to current contract documents and read between the drawings where the design information is incomplete.

Work the issue through a decision

Illustration: a duct intersects a beam above a corridor. The mechanical trade proposes a lower duct; the ceiling subcontractor warns that this would reduce ceiling clearance. The coordinator assigns the designer to decide the route and the structural engineer to evaluate any proposed structural change. Neither a clash marker nor a trade suggestion authorizes a beam penetration.

StageRecordRequired next action
DetectedDuct and beam locations plus model versionsCheck actual clearance and document scope
AssignedDesigner and affected mechanical and structural tradesCompare feasible alternatives
PricedReroute length, fittings, ceiling and access changesGet revised trade prices and schedule effect
ClosedAccepted design revision and updated modelsVerify affected bids and estimate reflect the decision

If the accepted route adds fittings and requires a ceiling adjustment, request separate price revisions and check whether the original mechanical and ceiling carries already cover the work. Assign MEP coordination interfaces so that a solution does not leave another trade unassigned. If a response is pending at bid, record the assumed route, pricing basis, risk owner and decision deadline.

Close against documents, not a colored status

Record the design response, affected drawing revision, model update, proposal revision and estimate adjustment. Trace drawing revisions into the estimate, and reopen the issue if a later change invalidates the solution. For an equipment change requiring shop drawings, carry the accepted decision into construction submittals and the procurement schedule. A coordination log is a decision record, not a substitute for the governing design documents.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow