Brookville and Kissena restroom bundle: separate site scope from shared approvals
A five-park package shares qualification steps, but Brookville and Kissena still need separate evidence for foundations, utilities and access.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 2 min
- Published
On this page
One bundle, two Queens site reviews
Brookville and Kissena belong to a five-site citywide design-build restroom bundle, not a Queens-only contract. The DDC August 2025 presentation also names East River Park, Murphy Brothers Playground and Van Cortlandt Park. It describes one-story buildings with women's and men's restrooms and mechanical rooms. That common program is a starting point for review, not proof of matching site conditions.
The presentation lists opportunities including piling, site and utility work, foundations, roofing and MEP trades. A bundle-wide list does not establish that each listed trade, quantity or foundation solution applies at each Queens park. A bidder needs the applicable site plans and specifications before allocating work.
Separate approval evidence from site work
The dated presentation distinguishes design-builder Armand's prequalification from DDC's separate subcontractor approval process, including RFAS and supporting documentation. Those are two different review gates in that presentation. Package-specific references to PASSPort, the project labor agreement and labor documentation are not a general rule for every city project or evidence that a particular firm is approved.
| Level | Shared evidence or site question | Review action |
|---|---|---|
| Bundle | Building program and common procurement instructions | Identify governing package and latest amendments |
| Bundle | Design-builder prequalification and DDC subcontractor approval | Track each gate and its current required evidence separately |
| Brookville | Foundation and utility connections | Obtain site plans, geotechnical basis and connection limits |
| Kissena | Foundation and utility connections | Repeat the site review without copying Brookville quantities |
| Each site | Roof, finishes, access and protection | Compare issued details and site-specific constraints |
| Each handover | Utilities and completed building | Identify testing, restoration and acceptance responsibilities |
A shared mechanical room description may support a common scope template. It does not resolve a utility route, excavation depth, roof detail or park-access restriction. List those as separate site rows, and invite each bidder to identify what it has priced at each location. The bid-leveling documentation guide explains how to keep package qualification and trade-scope evidence separate.
Refresh the instructions before a pursuit
The 2025 slides describe a historical process and forecast, not live registration slots, final site designs or a current opportunity. Confirm the controlling package, amendments and approval instructions with the issuing parties before relying on any gate or submitting a price.
Related reading
Public bid leveling: the file is the evidence
Prepare a source-backed leveling file before a sealed public bid. Keep scope coverage, bid compliance and permitted post-opening procedures distinct under the governing rules.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.