Linear construction scheduling: connect work locations, production and CPM logic
Use a time-location view to expose crew conflicts, then reconcile quantities, access and logic with the contract schedule.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 3 min
- Published
A time-location view helps a GC see when crews need the same constrained work area, even when a bar chart shows each activity's dates. Use it for repetitive corridor or floor-by-floor work when crew continuity and access govern the sequence. Keep the contract-required schedule as the formal deliverable and reconcile the two views before adopting a resequence.
Trimble's time-distance explanation describes activities against both time and location; location can be vertical as well as horizontal. The slope reflects the chosen production and time scales. A crossing signals a question about physical access, not proof of a critical path or available float.
Test a corridor conflict by station
The following is a hypothetical planning exercise, not a field production benchmark. A corridor has three 100-foot segments, A through C. Each crew can complete one segment per working day. Only one crew can occupy a segment in a day, and installation follows excavation; backfill follows installation. Dates, quantities and access need superintendent validation.
| Working day | Excavation | Installation | Backfill |
|---|---|---|---|
| 1 | A | None | None |
| 2 | B | A | None |
| 3 planned | C | B | B |
| 4 planned | None | C | A |
On day 3, installation and backfill both occupy B. Backfill in B also lacks a completed installation predecessor under the one-segment-per-day assumptions, so the plan fails both access and predecessor tests. Moving backfill to A on day 3, B on day 4 and C on day 5 resolves those conflicts under the stated assumptions. Installation remains in B on day 3 and C on day 4; excavation finishes C on day 3. The backfill crew works continuously on days 3 through 5, but its completion shifts from the incomplete original plan to day 5. Verify that no inspection, utility, compaction or access release adds a hold.
Each crew's planned quantity is 300 feet, not an assumed 300 feet of identical effort. Check segment-specific obstructions and labor, equipment and disposal needs. If the crew is unavailable on day 5, or only one gate permits both crews to reach different segments, this apparent solution needs another iteration. Document the resulting resource and cost assumptions in the site access and logistics constraints and the construction phasing review.
Reconcile the diagram with the CPM update
Map each segment and operation to its CPM activity ID, or document how a single activity's progress is allocated across segments. Record the common data date, actual completed quantities, remaining work, calendars and access constraints. For the example, installation B must follow excavation B, and backfill B must follow installation B. Add any approved release or inspection dependency rather than assuming the graphic provides one.
Update milestones and lookahead with the scheduler and superintendent. A location line cannot itself calculate contract float or show whether a milestone is critical: those depend on the network, calendars, constraints and remaining work. If the diagram and CPM dates disagree, reconcile the mapping and logic before presenting a revised forecast.
The FHWA accelerated bridge manual, dated June 2013, discusses production-based linear planning followed by CPM detail in that specific context. It illustrates complementary views, not a universal contract requirement or a mandate to buy a particular scheduling product. Confirm deliverables and the owner's acceptance process in the actual contract.
Related reading
Construction logistics plans: turn access and storage assumptions into priced scope
A site logistics drawing is useful when its assumptions reach the estimate. Review access, storage, deliveries, handling and repeated moves before pricing.

Construction phasing: price the handoffs as well as the work periods
A construction phase is more than an activity label. Review pricing setup, temporary work, turnover, remobilization and the sequence behind the estimate.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow