Court Square HWQ788CS: separate utility restoration from public-space work

Separate trench restoration, resurfacing and full-depth reconstruction in the Court Square design, with subway, bus and stormwater interfaces.

Guide3 min read

Published

Tower crane above steel reinforcement

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Build the restoration register by segment
  2. Price the public-space interfaces separately
  3. Coordinate subway, bus and park boundaries

The March 2026 Court Square presentation describes HWQ788CS as a design-stage pedestrian and infrastructure project. It tentatively estimated a summer 2027 construction start, subject to change. Its utility and roadway work cannot be priced as a uniform trench-and-pave operation: the proposed restoration treatment varies by street and even by project limits on the same street.

Build the restoration register by segment

The presentation separates DEP sewer and watermain work from DOT roadway and public-space work. Its DEP scope describes the following distinctions. These are presentation-level descriptions, so use current drawings to identify exact limits and quantities.

Location in presentationDescribed treatmentEstimate question
Thomson Avenue, Jackson Avenue and Court Square West within DOT project limitsWatermain work with full-depth pavement reconstructionWhich excavation and base are included in the roadway section, and who restores temporary openings before final reconstruction?
44th Drive, Jackson Avenue, 23rd Street and 45th AvenueWatermain work with standard trench restorationWhat are trench limits, temporary surfaces and adjacent curb or sidewalk repairs?
Court Square West, Court Square East and Pearson StreetStandard trench restoration followed by pavement resurfacingIs the final resurfacing in the same package and how are overlap and sequencing handled?

Jackson Avenue and Court Square West appear in more than one description. That is a reason to locate each segment on the drawings, not to apply both treatments to its entire length. Compare the utility profile, excavation width, traffic stages and pavement plans before allocating a quantity. A utility contractor's trench repair and a roadway contractor's full-depth section may overlap physically; define the handoff and avoid carrying the same finished surface twice.

Price the public-space interfaces separately

The presentation proposes concrete-top infiltration basins on Pearson Street and Thomson Avenue and illustrates suspended pavement soil cells along Thomson Avenue. Ask who excavates, protects and installs the basin and cells, how nearby utilities cross them, and who places the final surface and trees. The utility trench cannot simply be reinstated to a typical roadway detail where a specialized assembly is shown. Confirm the actual details and testing requirements in the issued documents.

Court Square West is shown as a raised shared street, while Thomson Avenue between Jackson Avenue and 44th Drive includes pedestrian-space changes. Establish temporary access and drainage assumptions separately from the finished public realm. The construction logistics review helps translate those arrangements into cost and package responsibilities.

Coordinate subway, bus and park boundaries

The presentation identifies MTA bus-stop rebuilding and construction over the subway as coordination matters. Request agency constraints, protection and review responsibilities, permissible access and any staging requirements before pricing; the presentation alone does not specify the protective method. Record who maintains passenger and pedestrian routes through each work stage and who owns their changes.

The presentation identifies Court Square Park as a separate Parks project. Carry only the work shown in the applicable contract and identify the interface with the park project, including access and final grade, rather than adding the park reconstruction to HWQ788CS. For a different multi-location utility example, see the QED1063AC watermain scope case.

Before committing a number, obtain the current contract drawings, agency requirements and project schedule. Tag every open restoration or protection assumption to a street segment, responsible package and estimate line. The March presentation is evidence of a design and tentative schedule, not evidence of award or current construction.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.